5.2 Drycooler Installation 27 5.3 Electrical Connections 27 5.3.1 Line Voltage 27 5.3.2 Low Voltage 27 5.3.3 Pump and Drycooler 27 5.4 Glycol Piping 28 5.4.1 Expansion Tanks, Fluid Relief Valves and Other Devices 28 5.5 Filling Instructions 29 5.5.1 Preparing the System for Filling 29 5.5.2 Glycol Solutions 30 5.5.3 Filling the System 31 5.6 Condenser 36 5.7 Glycol Regulating Valve 36 5.7.1 Glycol Regulating Valve Adjustment 36 5.7.2 Testing Valve Function 36 6.0 CHILLED WATER MODELS 37 6.1 Piping Considerations 37 7.0 SPLIT SYSTEM MODELS 38 7.1 Location Considerations 38 7.1.1 Air-Cooled Condensing Units 38 7.1.2 Water/Glycol-Cooled Condensing Units 38 7.2 Electrical Connections 38 7.2.1 Line Voltage 38 7.2.2 Low Voltage 38 7.3 Piping Considerations 39 7.3.1 Refrigerant Loop 39 7.3.2 Quick Connect Fittings 42 7.4 Outdoor Air-Cooled Condensing Units 43 7.5 Centrifugal Air-Cooled Condensing Units 48 7.5.1 Installing the Indoor Condensing Unit 48 7.5.2 Ducting 49 7.6 Water and Glycol-Cooled Condensing Units 53 7.6.1 Piping Considerations 53 7.6.2 Condenser Water Requirements 53 7.6.3 Regulating Valve Adjustment and Testing 53 7.6.4 Glycol Systems 53 8.0 R407C REFRIGERANT 56 8.1 Calculating Subcooling 57



Liebert Challenger ITR™ environmental control systems are available in three main system configu- rations:
All three types are available in horizontal flow configurations. Each model requires three-phase power. Units are available in 208, 230, 460, or 575 V, 60 Hz; and 200, 230 or 380/415 V, 50 Hz.
The following features are included as standard in all room units regardless of the type of system: V-frame coil, infrared humidifier, finned tubular stainless steel electric reheat, 2" filter, individual high voltage fused protection, and fan assembly.
Each configuration can operate with either Advanced Microprocessor Controls (A), or Advanced Microprocessor Controls with Graphics (G). A brief description of each, including operational differ- ences, is listed below. Check model numbers to see what is supplied with your unit.
Air-Cooled Models
Complete refrigeration system including hot gas bypass and crankcase heater with standard con- denser and fan speed control for 95°F (35°C) ambient at sea level.
Compete refrigeration system including hot gas bypass with water/glycol-cooled condenser and two- way water regulating valve with bypass.
The water-cooled model as described above plus pump package and 95°F (35°C) design ambient dry- cooler.
Complete refrigeration system including hot gas bypass with glycol condenser and three-way water reg- ulating valve plus an integrally piped Econ-O-Coil with three-way modulating control valve.
Chilled Water models include chilled water piping, three-way modulating valve and actuator assembly.
Each Air-Cooled split system consists of an evaporator section and one of the following condensing units.
Includes scroll compressor, condenser coil, prop fan, high pressure switch, and Lee-Temp head pres- sure control. Unit is designed for outdoor location.
Includes scroll compressor, condenser coil, centrifugal blower assembly, high pressure switch, head pressure control valve, Lee-Temp receiver and liquid line solenoid valve. Unit must be mounted indoors. Duct flanges are optional.
Each water-cooled split system consists of an evaporator section and a water/glycol condensing unit, which includes scroll compressor, coaxial condenser, water regulating valve, and high pressure switch. Design pressure is 150 psi (1034 kPa) as standard and 350 psi (2413 kPa) as optional.
Each glycol-cooled split system consists of an evaporator section, a water/glycol condensing unit (as described above), a pump package and a 95°F (35°C) design ambient drycooler.
Introduction

The room should be well insulated and must have a sealed vapor barrier. The vapor barrier in the ceiling can be a polyethylene film type. Use a rubber or plastic base paint on concrete walls and floors. Doors should not be undercut or have grilles in them.
Outside (or fresh) air should be kept to an absolute minimum. Outside air adds to the heating, cool- ing, humidifying and dehumidifying loads of the site. It is recommended that outside air be kept below 5% of the total air circulated in the room and be preconditioned.
Upon arrival of the unit, inspect all items for visible and concealed damage. Damage should be imme- diately reported to the carrier and a damage claim filed with a copy sent to Liebert or to your sales representative.
The Liebert Challenger ITR can sit on top of an accessible elevated flooring system. It may be neces- sary to furnish additional pedestal support below the unit to ensure maximum structural support (see Table 1). A separate floor stand for the unit may be used as support, independent of the elevated floor and installed prior to the flooring system.
Provide approximately 34" (864 mm) service clearance in the front and rear of the unit.
The unit can be installed between equipment racks or at the end of a row of racks. Consideration should be given before installing refrigerant and liquid lines next to, under or above electronic equip- ment. Avoid placing the Liebert Challenger ITR in an alcove. Placing units too close together will reduce the effectiveness of the air distribution.
The remote temperature and humidity sensor should be installed in the cold aisle in front of the equipment to be cooled. It should be mounted at the farthest point from the cooling unit that supply air needs to reach but still within the unit's area of influence. The sensor should be installed at the highest point that equipment will draw in cooled air.
! WARNING Risk of equipment tipping over. Can cause damage, injury or death. The instructions listed below must be adhered to when handling this unit with or without the skid. There is the potential for this unit to tip over if handled improperly.
Installation

Do not attempt to lift the Liebert Challenger ITR with the extended rear door frame. Attempting to do so will damage the unit. Lift the unit only from its main base. NOTICE
While on the skid, the Liebert Challenger ITR is too tall to fit through a standard height doorway (83 inches or 2108 mm tall). Any attempt to move the unit, while on the skid, through a standard doorway will damage the unit.
2.4.2 Removal of Skid 1. Remove the plywood skirting that keeps the skid and unit in place. 2. Raise the Liebert Challenger ITR off the skid. Liebert recommends using a fork lift (see Figure 1) or similar machine to ensure that the unit is lifted properly.

Remove plywood skirting holding unit and skid in place.
Raise unit with fork lift or similar machine.
Installation


Installation

1" (25.4mm)
30-1/2" (775mm) 30-1/2" (775mm)
See Specification Sheet for height of floor stand ordered. SL-11897 Pg. 7
Installation

Consideration should be given before installing refrigerant and liquid lines next to, under or above electronic equipment.
A 3/4" (19.1 mm) female pipe thread (FPT) connection is provided for the evaporator coil condensate drain. This drain line also drains the humidifier, if applicable. The drain line must be located so it will not be exposed to freezing temperatures. The drain should be at least the full size of the drain connec- tion and pitched a minimum of 1/8" per ft. (11 mm per meter).
The Challenger ITR comes standard with a condensate pump will require a field-supplied trap downstream from the pump. The drain line must comply with all applicable codes.
Installation


Piping outlet locations through the plenum are the same as the unit. See below for descriptions and connection sizes.
Hot Gas Refrigerant Line 7/8" OD CU on Models BR067A/BR065A
Liquid Refrigerant Line 1/2" OD CU on Models BR067A/BR065A
Installation


Piping outlet locations through the plenum are the same as the unit. See below for descriptions and connection sizes.
Suction Refrigerant Line 1 1/8" OD CU on Models BR060E/BR059E
Liquid Refrigerant Line 1/2" OD CU on Models BR060E/BR059E
Hot Water Supply 5/8" OD CU (optional) Condensate Pump Line 1/2" OD CU
Installation


Piping outlet locations through the plenum are the same as the unit. See below for descriptions and connection sizes.
Condenser Return Line 1 1/8" OD CU on Models BR071WG/BR070WG
Condenser Supply Line 1-1/8" OD CU on Models BR071WG/BR070WG
Hot Water Supply 5/8" OD CU (optional) Condensate Pump Line 1/2" OD CU
Installation


Piping outlet locations through the plenum are the same as the unit. See below for descriptions and connection sizes.
Installation

Three-phase electrical service is required for all models in either 208, 230, 460, or 575 V, 60 Hz; or 200, 230, or 380/415 V, 50 Hz. Electrical service shall conform to national and local electrical codes. Refer to equipment nameplate regarding wire size and circuit protection requirements. Refer to elec- trical schematic when making connections. A manual electrical disconnect switch should be installed within 5 feet (1.6 m) of the Liebert Chal- lenger ITR in accordance with codes. A factory-supplied, locking disconnect switch is factory-mounted within the unit behind the front door.
! WARNING Risk of electric shock. Can cause injury or death. Disconnect all local and remote electric power before working within the unit. Use a voltmeter to make sure power is turned off before making any electrical connections.
Three-phase power must be connected to the Liebert Challenger ITR line voltage terminals in the proper sequence so that scroll the compressor rotates in the proper direction.

11 13 12 17 16 14 13 10 9 8 8 9
75 76 82 83 84 85 88 89 91 92 93 94 95 96 97 1 37C 38C 37B 37 38 24 50 51 55 56 77 78 4
1. Electric conduit knockouts on top and bottom of electric box. Knockout size 1-3/4" (44.5mm). 2. Three phase connection. Electric service connection terminals when factory disconnect switch is supplied. 3. Factory-installed locking disconnect switch. 4. Three-phase electric service not by Liebert. 5. Earth ground connection (50/60Hz). Connection terminal for field-supplied earth grounding wire. 6. Earth ground bar (50Hz only). Connection terminals with factory ground from each high voltage component for field supplied earth grounding wire. 7. Control and monitoring section of electric box. 8. Remote unit shutdown. Replace existing jumper between Terminals 37 + 38 with normally closed switch having a minimum 75VA, 24VAC rating. Use field-supplied Class 1 wiring. Two additional contact pairs available as an option (labeled as 37B & 38B, 37C & 38C). Replace existing jumper for appropriate pair as done for 37 & 38.
Installation

9. Special alarm connections. Field-supplied 24V Class 1 wiring for special alarm. Connection made by adding normally open contacts between terminals 24 + 50. Optional additional connections available with Advanced or Advanced with Graphics controls and appropriate optional accessories (connections 51, 55, and 56). 10. Liebert SiteScan® connection. Terminals 77 (-) and 78 (+) are for connection of a 2-wire, twisted pair, communication cable (available from Liebert or others) to optional Liebert SiteScan. 11. Remote condensing unit connection. Field-supplied 24V Class 1 wiring to remote condensing unit terminals 1, 2, 3, & 4 from (R2) relay (split system only). 12. Smoke detector alarm connections. Field-supplied 24V Class 1 wiring to remote alarm circuits. Factory-wired contacts from optional smoke detector are #91-comm., #92-NO, and #93-NC. 13. Common alarm connection. Field-supplied 24V Class 1 wiring to common alarm terminals 75 + 76 (and optional 94 + 95, and 96 + 97), which are factory-connected to common alarm relay (R3). 14. Reheat and Humidifier Lockout. Optional emergency power lockout of reheat and/or humidifier: connections provided for remote 24V AC source. 15. Heat rejection connection. Field-supplied 24V Class 1 wiring to interlock heat rejection from pigtails 70 + 71 which are factory-connected to compressor side switch (self-contained units only and to Glycool relay (R5), Glycool units only). 16. Main Fan Auxiliary Switch. Optional main fan auxiliary side switch. Terminals located in field wiring compartment for remote indication that the evaporator fan motor/unit is on. Field to connect 24V maximum. 17. Optional Condensate Alarm (Dual Float Condensate Pump only). Relay terminals located in field wiring compartment for remote indication.
*Located inside Liebert Challenger ITR on top.
2.7.1 Ducted Applications For ducted applications, the duct work may be attached to the top perimeter of the Liebert Challenger ITR (see Figure 2). The duct work must allow access to the motors/blowers for maintenance. The duct work must be designed within the capacity of the Liebert Challenger ITR, otherwise air flow and performance will be compromised. 2.7.2 Plenum Installation A solid plenum or plenum with discharge grille(s) may be installed. The plenum and instructions for its installation ship separately from the Liebert Challenger ITR.
Installation

___ 1. Unpack and check received material.
___ 2. Proper clearance for service access has been maintained around the equipment.
___ 3. Equipment is level and mounting fasteners are tight.
___ 4. Piping completed to refrigerant or coolant loop (if required). Piping has been leak checked, evacuated and charged (if required).
___ 5. Check piping within the Liebert Challenger ITR and outside of the unit. Remove potential of rub-through or chaffing.
___ 6. Condensate pump installed.
___ 7. Drain line connected.
___ 8. Water supply line connected to humidifier (if required).
___ 9. Field provided pan with drain installed under all ceiling mounted fluid condensing units (if installed).
___ 10. Ducting completed (if applicable).
___ 11. Filter(s) installed.
___ 12. Line voltage to power wiring matches equipment serial tag.
___ 13. Power wiring connections completed between disconnect switch, evaporator and condensing
unit, including earth ground.
___ 14. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 15. Control wiring connections completed to evaporator and condensing unit.
___ 16. Verify water detection is properly installed around all units (if installed).
___ 17. All wiring connections are tight.
___ 18. Control panel DIP switches set based on customer requirements.
___ 19. Foreign materials have been removed from, in and around all equipment installed (literature,
shipping materials, construction materials, tools, etc.).
___ 20. Fans and blowers rotate freely.
___ 21. Inspect all piping connections for leaks during initial operations. Correct as needed.
___ 22. Verify that a blank start-up sheet has been sent with the unit(s) and is ready to be completed
by the installer.
Installation

The air-cooled condenser should be located for maximum security and maintenance accessibility. Avoid ground level sites with public access or areas that contribute to heavy snow or ice accumula- tions. Utilize centrifugal condensers whenever interior building locations must by used. To assure adequate air supply, it is recommended that condensers be located in a clean air area, away from loose dirt and foreign matter that may clog the coil. In addition, condensers should not be located in the vicinity of steam, hot air, or fume exhausts. Also, condensers should be located no closer than three feet (1 meter) from a wall, obstruction, or adjacent unit. Install condensers in a level position to assure proper refrigerant flow and oil return. For roof instal- lation, mount condensers on steel supports in accordance with local codes. To minimize sound and vibration transmission, mount steel supports across load bearing walls. For ground installation, a concrete pad will provide adequate support. Condenser legs have mounting holes for securing the con- denser to the steel supports or concrete pad.
Refer to equipment nameplate regarding wire size and circuit protection requirements. Refer to elec- trical schematic when making connections. Make all wiring and electrical connection in accordance with local and national codes.
! WARNING Risk of electric shock. Can cause injury or death. Disconnect all local and remote electric power before working within the unit. Use a voltmeter to make sure power is turned off before making any electrical connections.
3.2.1 Line Voltage Line voltage electrical service is required for all air-cooled condensers at the location of the condenser. This power supply does not have to be the same voltage as the indoor unit. This separate power source may be 208, 230, 460, or 575 V, 60 Hz; or 200, 230, or 380/415 V, 50 Hz. The disconnect switch may be factory-supplied and mounted in the electrical panel or field-supplied and mounted per local and national codes. 3.2.2 Low Voltage A control interlock between the condenser and the indoor unit is required and is connected between 70 and 71 in the handy box of the indoor unit and the electric panel of the air-cooled condenser. NEC Class 1 wiring is required. 3.2.3 Lee-Temp/Flood Back Head Pressure Control Condensers Lee-Temp condensers require a separate power supply for the heated receivers. This power supply is connected to the electrical connection box on the end of the receiver.
Air-Cooled Models

LEE-TEMP CONDENSER FAN SPEED CONDENSER
Lee-Temp heater pad connection box


Electric service supplied by others
Electric service supplied by others
*B - Inverted traps are to be field-supplied and installed (typ). When installing traps, provide clearance for swing end of access door. Traps are to extend above base of coil by a minimum of 7-1/2" (190 mm)
Secure each leg to condenser frame at all points shown using hardware provided.

1" typ. (25.4mm)
9/16" (14.3mm) diameter holes 8 places for 1/2" (12.7mm) diameter bolts
1" typ. (25.4mm)
1-3/4" (44.5mm)
Common to all models. See Table 3 below for key to “A” dimension.
Table 3 Air-cooled condenser statistics

Air-Cooled Models · Hot gas line

All refrigeration piping should be installed with high temperature brazed joints. Prevailing good refrigeration practices should be employed for piping supports, leak testing, dehydration and charg- ing of the refrigeration circuits.
Unit refrigeration components and piping are shipped from the factory with a nitrogen holding charge.
NOTE When installing field piping, care must be taken to protect all refrigerant lines from the atmosphere, especially when using refrigerants with POE oils. Do not allow the piping to stand open to air for more than 15 minutes. Units designed for R407C have a compressor that contains POE oil that is very hygroscopic; that is, it quickly absorbs water from the air. The longer the compressor piping is left open to air, the harder it will be to fully evacuate. If left open too long, the POE oil may need to be replaced before achieving the required vacuum level.
NOTE Keep the evaporator unit and condenser closed with their factory charge of dry nitrogen while all field piping is installed. Keep the field piping clean and dry during installation, and do not allow it to stand open to the atmosphere. When all the field interconnecting piping is in place, vent the condenser dry nitrogen charge and connect to the field piping. Finally, vent the evaporator unit dry nitrogen charge and make its piping connections last.
Follow all proper brazing practices including a dry nitrogen purge to maintain system cleanliness.
Traps should be installed in the hot gas line on vertical risers at the base and every 25 feet (7.6 meters) in elevation. These traps will collect condensed refrigerant and refrigerant oil during the off cycle of the unit and ensure flow of refrigerant oil during operation.
A check valve is factory-supplied with the unit to be field-installed on the discharge side of the scroll compressor. Be sure to install the check valve with the refrigerant flow in the proper direction. When soldering or brazing the valve, it is very important to protect the internal parts by wrapping the valve with a damp cloth to keep the valve temperature below 250°F (121°C).
Approval is required whenever:
Total discharge line pressure drop must not exceed 10 PSIG (69 kPa).
Consult your local Liebert representative when considering installations outside these guidelines.
23 & 33 kW 067A (065A) Hot Gas Line Liquid Line 50 ft. (15 m) 7/8 1/2 100 ft. (30 m) 7/8 5/8 150 ft. (45 m) 7/8 5/8 *Recommended vertical line sizes must be used for proper oil return at all cooling and dehumidification steps.
Air-Cooled Models · Equivalent Length

90 Degree Elbow Copper
90 Degree Elbow Cast
45 Degree Elbow Tee
Valve 1/2 0.8 1.3 0.4 2.5 0.26 7.0 4.0 5/8 0.9 1.4 0.5 2.5 0.28 9.5 5.0 3/4 1.0 1.5 0.6 2.5 0.3 12.0 6.5 7/8 1.45 1.8 0.8 3.6 0.36 17.2 9.5 1-1/8 1.85 2.2 1.0 4.6 0.48 22.5 12.0 1-3/8 2.4 2.9 1.3 6.4 0.65 32.0 16.0 1-5/8 2.9 3.5 1.6 7.2 0.72 36.0 19.5 Refrigerant trap = 4 times equivalent length of pipe per this table.
O.D. in.
Table 6 Indoor unit refrigerant charge lb (kg) R22 or R407C (per unit serial tag)
67A/65A 1.5 (0.68) 1.4 (0.6)
Table 7 Line charges - refrigerant per 100 ft (30 m) of Type “L” copper tube
O.D.
1/2" 7.3 (3.3) 1.3 (0.6) 6.9 (2.9) -
5/8" 11.7 (5.3) 2.1 (1.0) 11.0 (4.6) 2.2 (0.9)
3/4" 16.6 (7.5) 3.0 (1.4) 15.7 (6.5) 3.1 (1.3)
7/8" 24.4 (11.1) 4.4 (2.0) 23.0 (9.6) 4.5 (1.9)
R22 R407C
Fan Speed Lee-Temp* Fan Speed Lee-Temp*
083 5 (2.27) 27 (12.3) 8 (3) 25 (12)
104 8 (3.63) 39 (17.7) 9 (4) 37 (17)
* Charge includes the receiver charge.
Fan Speed Control provides an infinite number of speed variations on specially designed, permanent split-capacitor motors. The control module varies the air quantity passing over the condenser coil by monitoring refrigerant pressure.
3.4.1 Materials Supplied 1. Built-in pre-wired condenser control box 2. Air-cooled condenser 3. Piping access cover to be reinstalled when piping is complete 4. Bolts (four per leg) 3/8" x 5/8" 5. Terminal block for two-wire, 24-volt interlock connection between unit and condenser 6. Condenser legs, four on one-fan models

Fan Speed Control Type Condenser
! CAUTION All local codes for handling refrigerant must be followed.
NOTE When installing field piping, care must be taken to protect all refrigerant lines from the atmosphere, especially when using refrigerants with POE oils. Do not allow the piping to stand open to air for more than 15 minutes. Units designed for R407C have a compressor which contains POE oil that is very hygroscopic; that is, it quickly absorbs water from the air. The longer the compressor piping is left open to air, the harder it will be to fully evacuate. If left open too long, the POE oil may need to be replaced before achieving the required vacuum level.
Dehydration/Leak Test 1. Make sure unit is OFF. Open all disconnects and remove all fuses except control fuses. On units supplied with circuit breakers, open all breakers except for the transformer. 2. Add a jumper to the Fan Safety Switch between Common and Normal Open and disconnect the wire connected to the Normally Closed. Turn unit disconnect ON. (Fan operation not required.)
NOTE The above allows the technician to use unit 24 VAC power and controls to open liquid line solenoid valve(s) and hot gas bypass solenoid valve(s) for the dehydration process. If no power is at the unit disconnect, the technician is to use a separate 24 VAC source rated at 75 VA and connect to the system liquid line solenoid valve(s) and hot gas bypass solenoid valve(s) directly.
3. Connect refrigeration gauges to the suction and discharge service valves of the compressor. Open all compressor service valves. 4. To energize the liquid line solenoid valves through the control system power, set the control temperature setpoint (see operation manual) to 60°F (15°C) and set the % relative humidity setpoint higher than the conditioned room ambient to ensure that solenoid valves and hot gas bypass valves are open during the dehydration process. 5. Pressurize the system circuit(s) to 150 PSIG (1034 kPa) by using dry nitrogen with a trace of refrigerant. Check system for leaks with suitable leak finder. 6. After completion of leak testing, release the test pressure (per local code) and pull a deep vacuum on the system with a suitable pump. 7. After four hours, check the pressure readings, and if they have not changed, break vacuum with refrigerant. Pull another vacuum to 250 microns or less. Recheck the pressure after two hours. After completing this step, pressurize the circuits with refrigerant (R407C liquid or R22 vapor per unit nameplate) until suction and discharge pressures have equalized.
Air-Cooled Models


In ve rted Trap s* on disch ar ge an d retu rn li ne s to ex te nd ab ov e ba se of co il by a mi ni mu m of 7 1 /2" (1 90 mm )
Tr ap s* ev er y 25 ft. (7.6 m) of ris e
Se rv ic e Va lves Hot Ga s Bypass
Che ck Va lv e (S hi pp ed Lo os e fo r Fi el d In st al la ti on )
SI NG LE CIRC UI T SH OW N
*Comp on ent s ar e no t su pp li ed by Li eb ert bu t ar e re co mm en d ed fo r pr op er ci rcui t op er at io n an d ma in te na nc e.
FA CT OR Y PI PI NG FI EL D PI PI NG
Air-Cooled Models

3.4.3 Charging 1. Make sure unit is OFF. Open all disconnect switches and, on units supplied with circuit breakers, open all breakers. Replace all fuses for the Fan and Compressors or close breakers. 2. Remove jumper on the Fan Safety Switch and reconnect the system wire connections. Ensure that all operational components are clear of debris. Turn unit ON. (Fan operation is required.) Check the evaporator fan for proper rotation and correct if necessary. 3. Connect the refrigerant gauge charging hose to the drum of refrigerant and to the suction and discharge service valves of the compressor. 4. Calculate the amount of charge for the system. Weigh in as much of the system charge as possible. Refer to the unit, condenser and refrigerant line charge tables. 5. Set the control temperature setpoint (see operation manual) to 60°F (15°C) and set the % relative humidity setpoint higher than the conditioned room ambient to ensure that solenoid valves and hot gas bypass valves are open during the charging procedure. You may have to bypass the LP Switch (low pressure switch) to start the compressors and stop short cycling. Reset the Head Pressure switch(es) if open. 6. Add refrigerant (R407C liquid, or R22 vapor per unit nameplate) to the suction side of the compressor until there is sufficient pressure to energize the low-pressure switch.
NOTE When adding refrigerant to an operating system, it may be necessary to add the refrigerant through the compressor suction service valve. Because the refrigerant leaving the refrigerant cylinder must be in a liquid state, care must be exercised to avoid damage to the compressor. It is suggested that a sight glass be connected between the charging hose and the compressor suction service valve. This will permit adjustment of the cylinder hand valve so that liquid can leave the cylinder while allowing vapor to enter the compressor.
Then you may remove the manual bypass you applied earlier. 7. Charge the unit until the liquid line sight glass becomes clear. Then add one additional pound of refrigerant. 8. As head pressure builds, the condenser fan starts rotating. The fan becomes fully energized when sufficient head pressure is developed. (Fan starts to rotate at 190 psi and is full speed at 250 psi.)
20 (137.9) 65 (448.2) 360 (2482)
The Lee-Temp system consists of a modulating type head pressure control valve and insulated receiver with heater pad to ensure operation at ambient temperatures as low as -30°F (-34.4°C).
Lee-Temp systems have two factory-supplied, field-installed check valves: one on the discharge side of the scroll compressor and one on the inlet side of the receiver. Be sure to install the check valves with the refrigerant flow in the proper direction. When soldering or brazing the valves, it is very important that the internal parts be protected by wrapping the valve with a damp cloth to keep the valve tem- perature below 250°F (121°C).

3.5.2 Materials Supplied 1. Built-in pre-wired condenser control box 2. Air-cooled condenser 3. Piping access cover to be reinstalled when piping is complete 4. Bolts (four per leg) 3/8" x 5/8" 5. Terminal block for two-wire 24V interlock connection between the unit and the condenser 6. Condenser legs: four on one-fan models 7. Lee-Temp system: a. Insulated storage receiver b. Head pressure control valve with integral check valve c. Adapter assembly d. Rotalock valve e. Pressure relief valve f. Liquid level sight glass g. Check valve
Lee-Temp Control Type Condenser
! CAUTION All local codes for handling refrigerant must be followed.
NOTE When installing field piping, care must be taken to protect all refrigerant lines from the atmosphere, especially when using refrigerants with POE oils. Do not allow the piping to stand open to air for more than 15 minutes. Units designed for R407C have a compressor which contains POE oil that is very hygroscopic; that is, it quickly absorbs water from the air. The longer the compressor piping is left open to air, the harder it will be to fully evacuate. If left open too long, the POE oil may need to be replaced before achieving the required vacuum level.
Air-Cooled Models

Dehydration/Leak Test 1. Make sure unit is OFF. Open all disconnect switches and pull all fuses except control fuses. On units supplied with circuit breakers, open all breakers except for the transformer. 2. Add a jumper to the Fan Safety Switch between Common and Normal Open and disconnect the wire connected to the Normally Closed. Turn unit disconnect ON. (Fan operation not required.)
NOTE The above allows the technician to use unit 24 VAC power and controls to open liquid line solenoid valve(s) and hot gas bypass solenoid valve(s) for the dehydration process. If no power is at the unit disconnect, the technician is to use a separate 24 VAC source rated at 75 VA and connect to the system liquid line solenoid valve(s) and hot gas bypass solenoid valve(s) directly.
3. Connect refrigeration gauges to the suction and discharge service valves of the compressor and open. 4. Attach a “jumper” hose from the Rotalock fitting on the outlet of the receiver and the Schrader fitting on the liquid header of the condenser. Front seat the Rotalock valve approximately two turns. 5. To energize the liquid line solenoid valve(s) through the control system, set the temperature setpoint (see operation manual) to 60°F (15°C) and set the % relative humidity setpoint higher than the conditioned room ambient to ensure that solenoid valves and hot gas bypass valves are open during the dehydration process. 6. Pressurize system circuit(s) to 150 PSIG (1034 kPa) by using dry nitrogen with a trace of refrigerant. Check system for leaks with suitable leak finder. 7. After completion of leak testing, release test pressure (per local code) and pull a vacuum on the system. 8. After 4 hours, check pressure readings and, if they have not changed, break vacuum with refrigerant. Pull a second and third vacuum of 250 microns or less. Recheck pressure after 2 hours.
3.5.4 Charging 1. Make sure unit is OFF. Open all disconnect switches and, on units supplied with circuit breakers, open all breakers. Replace all fuses for the Fan and Compressors or close breakers. 2. Remove jumper on the Fan Safety Switch and reconnect the system wire connections. Ensure that all operational components are clear of debris. Turn unit ON. (Fan operation is required.) Check the evaporator fan for proper rotation and correct if necessary. 3. Connect the refrigerant gauge charging hose to the drum of refrigerant and to the suction and discharge service valves of the compressor(s). 4. Calculate the amount of charge for the system. Weigh in as much of the system charge as possible. Refer to the unit, condenser and refrigerant line charge tables. 5. Set the control temperature setpoint (see operation manual) to 60°F (15°C) and set the % relative humidity setpoint higher than the conditioned room ambient to ensure that solenoid valves and hot gas bypass valves are open during the charging procedure. You may have to bypass the LP Switch (low pressure switch) to start the compressors and stop short cycling. Reset the Head Pressure switch(es) if open. 6. Add refrigerant (R407C liquid or R22 vapor per unit nameplate) to the suction side of the compressor until there is sufficient pressure to energize the low pressure switch.
NOTE When adding refrigerant to an operating system, it may be necessary to add the refrigerant through the compressor suction service valve. Because the refrigerant leaving the refrigerant cylinder must be in a liquid state, care must be exercised to avoid damage to the compressor. It is suggested that a sight glass be connected between the charging hose and the compressor suction service valve. This will permit adjustment of the cylinder hand valve so that liquid can leave the cylinder while allowing vapor to enter the compressor.
Then you may remove the manual bypass you applied earlier. 7. Charge the unit until the proper charge is weighed in.
Low Pressure Cut Out Low Pressure Cut In High Pressure Cut Out
20 (137.9) 65 (448.2) 360 (2482)
Air-Cooled Models


Inverted Trap * on discharge line to extend above base of coil by a minimum of 7 1/2" (190mm)
Traps * Every 25 Ft. (7.6m) of rise on Hot Gas Line only
* Components are not supplied by Liebert but are recommended for proper circuit operation and maintenance.
* * Components supplied by Liebert and must be field installed.
Air-Cooled Models

Manual shut-off valves should be installed at the supply and return lines of each unit. This will pro- vide for routine maintenance or emergency isolation of the unit.
When the water source for the condenser is of poor quality, it is good practice to provide cleanable fil- ters in the supply line. These filters will trap the particles in the water supply and extend the service life of the water-cooled condenser.
To provide for the emergency of water leaks and the consequences of sub-floor flooding, floor drains should be provided with wet traps or a water detection system such as a Liqui-tect sensor that is installed near the base of the unit or below the elevated floor.
The condenser is designed to operate in conjunction with either a cooling tower or city water. The maximum water pressure is 150 psig (1034 kPa). A high pressure system rated at 350 psig (2413 kPa) is available as an option.
Water-Cooled Models


*Components are not supplied by Liebert but are recommended for proper circuit operation and maintenance.
Water-Cooled Models

The water regulating valve automatically regulates the amount of fluid necessary to remove the heat from the refrigeration system, permitting more fluid to flow when load conditions are high and less fluid to flow when load conditions are low. The valve consists of a brass body, balance spring, valve seat, valve disc holders, capillary tube to discharge pressure, and adjusting screw.
The Liebert Challenger ITR may be equipped with either a standard Johnson Controls valve, 150 psig (1034 kPa) or with a high-pressure Johnson Controls valve, 350 psig (2413 kPa).
The valve may be adjusted with a standard refrigeration service valve wrench or screw driver.
To lower the head pressure setting, turn the square adjusting screw clockwise until the high pressure gauge indicates the desired setting.
To raise the head pressure setting, turn the adjusting screw counterclockwise until the desired set- ting is obtained.

Insert screwdrivers underneath the valve spring guide
The valve may be flushed by inserting screwdrivers or similar tools under the opposing sides of the main spring and lifting. This action will open the valve seat and flush any dirt particles from the seat. If this fails, the valve must be disassembled for cleaning the seat.
When the refrigeration system has been off for 10-15 minutes, the water flow should stop.
Should the water continue to flow, the valve is either improperly adjusted or the pressure sensing capillary is not properly connected to the condenser.

The drycooler should be located for maximum security and maintenance accessibility. Avoid ground- level sites with public access or areas which contribute to heavy snow or ice accumulations. To assure adequate air supply, it is recommended that drycoolers be located in a clean air area, away from loose dirt and foreign matter that may clog the coil. In addition, drycoolers should not be located in the vicinity of steam, hot air or fume exhausts. Also, drycoolers should not be located closer than 3 feet (1 meter) from a wall, obstruction or adjacent unit.
For roof installation, mount drycoolers on steel supports in accordance with local codes. To minimize sound and vibration transmission, mount steel supports across load bearing walls. For ground instal- lation, a concrete pad will provide adequate support. Drycooler legs have mounting holes for securing the drycooler to steel supports or concrete pad.
Refer to equipment nameplate regarding wire size and circuit protection requirements. Refer to elec- trical schematic when making connections. Make all wiring and electrical connections in accordance with local and national codes.
! WARNING Risk of electric shock. Can cause injury or death. Disconnect all local and remote electric power before working within the unit. Use a voltmeter to make sure power is turned off before making any electrical connections.
Line voltage electrical service is required for all drycoolers at the location of the drycooler. This power supply does not have to be the same voltage as the indoor unit. This separate power source may be 208, 230, 460, or 575 V, 60 Hz; or 200, 230, or 380/415 V, 50 Hz. The disconnect switch is factory-sup- plied and mounted in the electric panel.
A control interlock between the drycooler and the indoor unit is required and is connected between 70 and 71 in the handy box of the indoor unit and the pump and drycooler control box of the drycooler. NEC Class 1 wiring is required.
All wiring to the pump and drycooler from the control box should be done in accordance with the elec- trical schematic on the inside lid of the drycooler control box and with local and national codes.
Glycol/GLYCOOL-Cooled Models

NOTICE
Galvanized pipe must not be used in or with systems or units that contain glycol. The phosphates in the inhibitor can react with the zinc in the galvanized pipe, precipitating an insoluble material that can eventually foul the system. To help prevent piping failures, supply and return lines must be supported in a way that keeps their weight from bearing on the piping of the unit, drycooler or pumps. To avoid the possibility of burst pipes, it is necessary to install a relief valve in the system. This valve may be obtained from the supplier as an option or obtained from another vendor. Fluid-cooled condensers have small internal flow passages. To avoid clogging and other resulting system operation problems, install a 16-20 mesh filter in the fluid supply line to the indoor unit. The filter should be located where it can be easily serviced or replaced. Do not install unit on open-loop systems. Debris carried by the fluid will clog the brazed plate condenser.
It is recommended that manual service shut-off valves be installed at the supply and return connec- tions to each unit. This enables routine service and/or emergency isolation of the unit. In addition, multiple pump packages require a check valve at the discharge of each pump to prevent back flow through the standby pump(s).
To facilitate filling, installation of hose bibs at the lowest point of the system is recommended.
Consideration of the minimum glycol temperature to be supplied from the drycooler will determine if the need exists to insulate the glycol supply and return lines. Insulation will prevent condensation on the glycol lines in low ambient conditions.
All fluid piping must comply with local codes. Care in sizing pipes will help reduce pumping power and operating costs.
°F (°C)
°F (°C)
°F (°C)
70 (21.1) 70 (21.1) 57.2 (14.0) 58.5 (14.7) 45 50 48.0 (8.9) 50.5 (10.3)
72 (22.2) 72 (22.2) 58.9 (24.9) 60.0 (15.5) 45 50 50.0 (10.0) 52.4 (11.3)
75 (23.8) 75 (23.8) 61.2 (16.2) 62.5 (16.9) 45 50 52.4 (11.3) 55.0 (12.7)
* Minimum glycol temperature before condensation will occur.
An expansion tank must be provided for expansion and contraction of the fluid due to temperature change in this closed system. Vents are required at system high points to vent trapped air when fill- ing the system. A relief valve is a also a necessary piping component.
Depending on the complexity of the system, various other devices may be specified. Pressure gauges, flow switches, automatic air separator, tempering valves, standby pumps, sensors for electrical con- trols, and flow switches are just a few of these devices.
Immediately following the use of water for leak testing or system cleaning, charge the tested system with the proper percentage of glycol and water for the application’s coldest design ambient. Complete system drain-down cannot be assured, and equipment damage could result from freezing of residual water.

It is important to remove any dirt, oil or metal filings that may contaminate the cooling system piping in order to prevent contamination of the fresh glycol solution and fouling of the drycooler piping. The system should be flushed thoroughly using a mild cleaning solution or high-quality water and then completely drained before charging with glycol. Cleaning new systems is just as important as clean- ing old ones. New systems can be coated with oil or a protective film; dirt and scale are also common. Any residual contaminants could adversely affect the heat transfer stability and performance of your system. In many cases, in both old and new systems, special cleaners are needed to remove scale, rust and hydrocarbon foulants from pipes, manifolds and passages. Clean heat transfer surfaces are important in maintaining the integrity of the heating/cooling system. For more information on clean- ers and degreasers, contact your sales representative. Follow the manufacturer's instructions when using these products.
Calculate the internal volume of the system as closely as possible. See Table 12 and Table 14 for unit volumes. Use volume in Table 13 for glycol piping volumes.
Table 12 Indoor unit glycol volume approximate gallons (liters) max.
Model (50 Hz) Glycol-Cooled GLYCOOL
061G/(058G) — 4.0 (15.1)
Table 13 Volume in standard Type “L” copper piping
Diameter (in.) Volume
Outside Inside Gal/Ft L/M
1/2 0.123 0.008 (0.01)
5/8 0.555 0.012 (0.15)
3/4 0.666 0.018 (0.22)
7/8 0.785 0.025 (0.31)
1-1/8 1.025 0.043 (0.53)
Glycol/GLYCOOL-Cooled Models

When considering the use of any glycol products in a particular application, you should review the lat- est Material Safety Data Sheets and ensure that the use you intend can be accomplished safely. For Material Safety Data Sheets and other product safety information, contact the supplier nearest you. Before handling any other products mentioned in the text, you should obtain available product safety information and take necessary steps to ensure safety of use.
When mishandled, glycol products pose a threat to the environment. Before using any glycol products, review the latest Material Safety Data Sheets and ensure that you can use the product safely. Glycol manufacturers request that the customer read, understand and comply with the information on the product packaging and in the current Material Safety Data Sheets. Make this information available to anyone responsible for operation, maintenance and repair of the drycooler and related equipment.
No chemical should be used as or in a food, drug, medical device, or cosmetic, or in a product or pro- cess in which it may contact a food, drug, medical device, or cosmetic until the user has determined the suitability and legality of the use. Since government regulations and use conditions are subject to change, it is the user's responsibility to determine that this information is appropriate and suitable under current, applicable laws and regulations.
Automotive antifreeze is unacceptable and must NOT be used.
Typical inhibited formula ethylene glycol and propylene glycol manufacturers and suppliers are Union Carbide (Ucartherm) or Dow Chemical (Dowtherm SR-1, Dowfrost). These glycols are supplied with corrosion inhibitors and do not contain a silicone anti-leak formula. Commercial ethylene glycol, when pure, is generally less corrosive to the common metals of construction than water itself. Aque- ous solutions of these glycols, however, assume the corrosivity of the water from which they are pre- pared and may become increasingly corrosive with use if not properly inhibited.
There are two basic types of additives: corrosion inhibitors and environmental stabilizers. The corro- sion inhibitors function by forming a surface barrier that protects the metals from attack. Environ- mental stabilizers, while not corrosion inhibitors in the strictest sense of the word, decrease corrosion by stabilizing or favorably altering the overall environment. An alkaline buffer such as borax is a sim- ple example of an environmental stabilizer since its prime purpose is to maintain an alkaline condi- tion (pH above 7).
The percentage of glycol to water must be determined by using the lowest design outdoor temperature in which the system is operating. Table 14 indicates the solution freeze point at several concentra- tion levels of ethylene glycol. Propylene glycol concentrations should be 1% higher than the ethylene glycol table values to find the freeze point. For example, 41% propylene glycol freezes at -10°F (-23°C).
% Glycol by Volume 0 * 10 20 30 40 50 Freezing Point °F (°C) 32 (0) 25 (-3.9) 16 (-8.9) 5 (-15.0) -10 (-23.3) -32 (-35.5) Apparent Specific Gravity @ 50°F (10°C) 1 1.014 1.028 1.042 1.057 1.071
* A minimal amount of glycol should be considered for inhibitive coil protection.
The quality of water used for dilution must be considered because water may contain corrosive elements that reduce the effectiveness of the inhibited formulation. Water classified as soft (low in chloride and sulfate ion content less than 100 parts per million each) should be used.
Glycol/GLYCOOL-Cooled Models

5.5.3 Filling the System Installation of hose bibs at the lowest point of the system is recommended. When filling a glycol sys- tem keep air to a minimum. Air in glycol turns to foam and is difficult and time-consuming to remove. (Anti-foam additives are available and may be considered.) Open all operating systems to the loop. With the top vent(s) open, fill the system from the bottom of the loop. This will allow the glycol to push the air out of the top of the system, minimizing trapped air. Fill to approximately 80% of calcu- lated capacity. Fill slowly from this point, checking fluid levels until full.
Glycol/GLYCOOL-Cooled Models


See Table 16 for keys to dimensions “A”, “B” and “C”.

See Table 15 for keys to dimensions “A”, “B” and “C”.
For expansion tank dimensions, see Figure 15 on page -33.

Glycol/GLYCOOL-Cooled Models · 3/4" (19mm)



SINGLE (0.75 - 7.5 hp) 15-1/4 (387.4) 2-1/2 (63.5) 22-1/2 (571.5)
DUAL (0.75 - 5 hp) 30-1/4 (768.4) 2-1/2 (63.5) 22-1/2 (571.5)
DUAL (7.5 hp) 39-5/16 (998.5) 1-3/4 (44.5) 26-7/8 (682.6)

-069 1 410 (186) 1-1/4 51-1/2 (1308) 44 (1118) 42 (1067) 2.4 (9.2)
-092 1 430 (195) 1-1/2 51-1/2 (1308) 44 (1118) 42 (1067) 3.7 (13.9)
-109 1 450 (204) 2 51-1/2 (1308) 44 (1118) 42 (1067) 4.9 (18.6)
-112 1 470 (213) 2 51-1/2 (1308) 44 (1118) 42 (1067) 5.8 (22.0)
-139 2 565 (256) 2 91-1/2 (2324) 84 (2134) 82 (2083) 4.8 (18.2)
-197 2 605 (274) 2 91-1/2 (2324) 84 (2134) 82 (2083) 9.0 (34.1)

* Connection sizes apply to primary pump supplier
Glycol/GLYCOOL-Cooled Models


Expansion Tank Field Installed at Highest Point in System.
*Components are not supplied by Liebert but are recommended for proper circuit operation and maintenance.
Glycol/GLYCOOL-Cooled Models


Expansion Tank Field Installed at Highest Point in System
Fluid Supply from Pump Air Vents* at Top of Risers
Tube in Tube Condenser Fluid Supply to Unit Fluid Return from Unit Isolation Valves*
*Components are not supplied by Liebert but are recommended for proper circuit operation and maintenance.
Glycol/GLYCOOL-Cooled Models

The condenser is designed to operate in conjunction with a drycooler. The maximum coolant pressure is 350 psig (2413 kPa).
The glycol regulating valve automatically regulates the amount of coolant necessary to remove the heat from the refrigeration system, permitting more fluid to flow when load conditions are high and less fluid to flow when load conditions are low. The valve consists of a brass body, balance spring, valve seat, valve disc holders, capillary tube to discharge pressure, and adjusting screw.
The Liebert Challenger ITR may be equipped with either a standard Johnson Controls valve, 150 psig (1034 kPa) or with a high-pressure Johnson Controls valve, 350 psig (2413 kPa). For details on adjust- ing the valve, refer to 4.3.1 - Water Regulating Valve Adjustment.
When the refrigeration system has been off for approximately 10-15 minutes, the coolant flow should stop.
Should the coolant continue to flow, the valve is either improperly adjusted or the pressure sensing capillary is not connected properly to the condenser.
20 (137.9) 65 (448.2) 360 (2482)

Manual shut-off valves should be installed at the supply and return lines to each unit. This will pro- vide for routine service and emergency isolation of the unit.
Consideration of the minimum water temperature to be supplied from the chiller will determine if the need exists to insulate supply and return lines. Insulation will prevent condensation on the supply and return lines.
To provide for the emergency of water leaks and the consequences of sub-floor flooding, floor drains should be provided with wet traps or a water detection system, such as a Liqui-tect, that is installed near the base of the unit or below the elevated floor.

*Components are not supplied by Emerson but are recommended for proper circuit operation and maintenance.
Chilled Water Models

Three (3) condensing unit styles are available: two (2) air-cooled and one (1) water/glycol-cooled con- densing unit.
To assure an adequate air supply, it is recommended that all condensing units be located in a clean air area, away from loose dirt and foreign matter that may clog the coil.
Condensing units must not be located in the vicinity of steam, hot air, or fume exhausts or closer than 18" from a wall, obstruction, or adjacent unit.
The outdoor condensing unit should be located for maximum security and maintenance accessibility. Avoid ground-level sites with public access or areas that will contribute to heavy snow accumulations. Do not allow the discharge air to blow into another condensing unit.
A solid base, capable of supporting the weight of the condenser and at least 2" (51 mm) higher than the surrounding grade and at least 2" (51 mm) larger than the condensing unit base dimensions, should be installed at the pre-determined location. In snow areas, a base of sufficient height to clear snow accumulation must be installed.
The centrifugal fan air-cooled condensing unit may be located above the dropped ceiling or any remote indoor area. If noise is of concern, the condensing unit should be located away from personnel. Normal operating sound may be objectionable if the condensing unit is placed near quiet work areas.
To mount the unit in the ceiling, refer to 7.5.1 - Installing the Indoor Condensing Unit for hang- ing guidelines and to Figure 23 - Detail of ceiling hanging bracket for dimensional data.
The condensing unit may be located above the dropped ceiling or any remote indoor area. If noise is of concern, the condensing unit should be located away from personnel. Normal operating sound may be objectionable if the condensing unit is placed near quiet work areas. To mount the unit the in ceiling, refer to 7.5.1 - Installing the Indoor Condensing Unit.
Refer to equipment nameplate regarding wire size and circuit protection requirements. Refer to elec- trical schematic when making connections. Make all wiring and electrical connections in accordance with local and national codes.
! WARNING Risk of electric shock. Can cause injury or death. Disconnect all local and remote electric power before working within the unit. Use a voltmeter to make sure power is turned off before making any electrical connections.
Line voltage electrical service is required for all condensing units at the location of the condensing unit. This power supply does not have to be the same voltage as the indoor unit. This separate power source may be 208, 230, 460 or 575V, 60 Hz; or 200, 230, or 380/415V, 50 Hz. A disconnect switch is required and must be mounted per local and national codes to isolate the unit for maintenance.
The control cable between the condensing unit and the evaporator unit is connected between termi- nals 1,2 and 3 on the terminal strip in the evaporator unit and the condensing unit control box. A fourth wire is required on systems with hot gas bypass. NEC Class 1 wiring is required. Glycol-cooled units also require a two-wire control connection to the drycooler and pump package.
Split System Models

! CAUTION All local codes for handling refrigerant must be followed.
NOTE When installing field piping, care must be taken to protect all refrigerant lines from the atmosphere, especially when using refrigerants with POE oils. Do not allow the piping to stand open to air for more than 15 minutes. Units designed for R407C have a compressor which contains POE oil that is very hygroscopic; that is, it quickly absorbs water from the air. The longer the compressor piping is left open to air, the harder it will be to fully evacuate. If left open too long, the POE oil may need to be replaced before achieving the required vacuum level.
Follow all proper brazing practices including a dry nitrogen purge to maintain system cleanliness.
All split systems require two refrigerant lines (an insulated copper suction line and a copper liquid line) between the evaporator and the condensing unit.
Two possible methods exist for installing the copper suction and liquid lines.
All refrigeration piping should be installed with high temperature brazed joints. Prevailing good refrigeration practices should be employed for piping supports, leak testing, evacuation, dehydration, and charging of the refrigeration circuits. The refrigeration piping should be isolated from the build- ing by the use of vibration isolating supports.
It is important to handle the pre-charged lines with care so they will not get kinked or damaged. Use tube benders and make all bends before making connections to either end. Coil any excess tubing in a horizontal plane with the slope of the tubing toward the condensing unit.
To prevent tube damage when sealing openings in walls and to reduce vibration transmission, use a soft flexible material to pack around the tubes.
When installing remote condensing units mounted above the evaporator, the suction gas line should be trapped at the evaporator. This trap will retain refrigerant oil in the off cycle. When the unit starts, oil in the trap is carried up the vertical riser and returns to the compressor.
Refrigerant charge requirements: Total refrigerant charge will be required only if units are evacuated during installation or maintenance. Total refrigerant charge = evaporator + lines + condensing unit.
Split System Models

Once all piping is complete, check for leaks and dehydrate the field piping as follows:
1. Pressurize the field piping to 150 PSIG (1034 kPa) using dry nitrogen with a trace of refrigerant. Check system for leaks with a suitable leak detector. 2. After completion of leak testing, release the test pressure (per local code) and pull a deep vacuum on the field piping with a suitable pump. 3. After 15 minutes, check the pressure readings and, if they have not changed, break vacuum with dry nitrogen. Pull a second vacuum to 250 microns or less. Recheck the pressure after 15 minutes.
R22 Charge R407C Charge
R22 Charge R407C Charge
lb (kg) lb (kg) lb (kg) lb (kg)
060E 0.81 (0.37) 0.8 (0.4) PF_Z67A-_L 51.69 (23.45) 50.1 (22.7)
059E 0.81 (0.37) 0.8 (0.4) PF_Z66A-_L 51.69 (23.45) 50.1 (22.7)
MC_65/64A 27.00 (12.25) 26.1 (11.8) PF_067A-_H 51.69 (23.45) 50.1 (22.7)
PF_067A-_L 26.63 (12.08) 25.8 (11.7) PF_066A-_H 51.69 (23.45) 50.1 (22.7)
PF_066A-_L 26.63 (12.08) 25.8 (11.7) MC_69/68W 5.88 (2.67) n/a
Table 20 Line charges - refrigerant per 100 ft (30 m) of Type “L” copper tube
O.D.
1/2" 7.3 (3.3) 0.2 (0.1) 6.9 (2.9) -
5/8" 11.7 (5.3) 0.3 (0.2) 11.0 (4.6) 0.4 (0.2)
7/8" 24.4 (11.1) 0.7 (0.3) 23.0 (9.6) 1.0 (0.4)
1-1/8" 41.6 (18.9) 1.2 (0.6) 39.3 (16.3) 1.7 (0.7)
1-3/8" 63.3 (28.7) 1.9 (0.8) 59.8 (24.8) 2.7 (1.1)
3.5 Tons 036E (035E) 23 & 33 kW 060E (059E)
Suction Liquid Suction Liquid
0-50 (0-15) 7/8" 1/2" 1-1/8" 1/2"
51-100 (16-30) 1-1/8" 1/2" 1-1/8" 5/8"
101-150 (31-45) 1-1/8" 5/8" 1-3/8" 5/8"
Line Size OD Cu, in.
lb-ft. 1/2 & 5/8 #10 35-45 1-1/8 #12 50-65


Refrigerant trap = 4 times equivalent length of pipe per this table

Suction Line Piping Condensing unit above evaporator . Traps recommended at the base of riser and every 25 feet (7.6m) of vertical rise.
Split System Models

Be especially careful when connecting the quick connect fittings. Read through the following steps before making the connections.
1. Remove protector caps and plugs. 2. Carefully wipe coupling seats and threaded surfaces with a clean cloth. 3. Lubricate the male diaphragm and synthetic rubber seal with refrigerant oil. 4. Thread the coupling halves together by hand to ensure that the threads mate properly. 5. Tighten the coupling body hex nut and union nut with the proper sized wrench until the coupling bodies “bottom out” or until a definite resistance is felt. 6. Using a marker or pen, make a line lengthwise from the coupling union nut to the bulkhead. 7. Tighten the nuts an additional quarter turn; the misalignment of the lines shows how much the coupling has been tightened. This final quarter turn is necessary to ensure that the joint will not leak. Refer to Table 22 for torque requirements. 8. Add charge for the additional piping (refer to Table 20).
Split System Models


SHADED AREA INDICATES A MINIMUM CLEARANCE OF 18" (457mm) FOR PROPER AIR FLOW
ACCESS TO HIGH VOLTAGE & LOW VOLTAGE CONNECTIONS, AND REFRIGERATION COMPONENTS.
Split System Models

Model Numbers Dimensional Data in. (mm) Module
Weight lb (kg) net 60 Hz 50 Hz A B C
53 (1343) 36-1/4 (918) 18 (457) 351 (159) PFH067A-_L
Model Numbers Dimensional Data in. (mm) Piping Connections in. (mm)
60 Hz 50 Hz A B C D E F G
2 (51) 6 (152) 8-1/2 (216) 4-3/4 (121) 7-3/4 (197) - 8-1/2 (216) PFH067A-_L
Split System Models


ACCESS TO HIGH VOLTAGE & LOW VOTLAGE CONNECTIONS, AND REFRIGERATION COMPONENTS.
* System 1 and System 2 on 8 Ton only.
Split System Models

Table 26 Cabinet and floor planning dimensional data - prop fan condensing modules, top air discharge
Model Numbers Dimensional Data, in. (mm) Module
Weight lb (kg) net 60 Hz 50 Hz A B C D
53 (1343) 36-1/4 (918) 38-1/2 (978) 5-1/2 (140) 488 (222) PFH067A-_H
Table 27 Piping and electrical connections - top air discharge
Model Numbers Dimensional Data in. (mm) Piping Connections, in. (mm)
60 Hz 50 Hz A B C D E F
2 (51) 6 (152) 8-1/2 (216) 4-3/4 (121) 7-3/4 (197) 8-1/2 (216) PFH067A-_H
Split System Models

TOP AIR DISCHARGE MODELS (23 & 33kW High Ambient and 23 & 33kW Quiet-Line)
Field-supplied unit disconnect switch

Field-supplied 24V NEC Class 2 wiring to evaporator module
Heat rejection connection. Field- supplied 24V NEC class 2 wiring. Wire connections from evaporator module: 1. 24V GND 2. 24V Supply 3 High Pressure Alarm 4. Hot Gas Bypass Connection (only on units with hot gas bypass. If no hot gas bypass, connection is provided in the evaporator module. Connect wire 4 with wire 2 to the 24V supply).
Split System Models

Refer to drawings for unit dimensions and component locations.
! WARNING Risk of structure collapse. Can cause equipment damage, injury or death.
Before beginning installation, make sure that the supporting roof structure is capable of supporting the weight of the unit(s) and the accessories during installation and service. (See Table 28 - Indoor centrifugal condensing unit.)
Be sure to securely anchor the top ends of the suspension rods. Make sure all nuts are tight.
The indoor condensing unit is usually mounted above the ceiling and must be securely mounted to the roof structure. The ceiling and ceiling supports of existing buildings may require reinforcements. Be sure to follow all applicable codes. Use field-supplied threaded suspension rods and 3/8"-16 factory hardware kit.
Recommended clearance between ceiling grids and building structural members is unit height plus three inches.
Install the four field-supplied rods by suspending them from suitable building structural members. Locate the rods so that they will align with the four mounting holes in the flanges that are part of the unit base.
Using a suitable lifting device, raise the unit up and pass the threaded rods through the four mount- ing holes in the flanges that are part of the unit base.
Attach the threaded rods to the unit flanges using the supplied nuts and grommets. (See Figure 23 - Detail of ceiling hanging bracket, Threaded Rod and Hardware Kit Installation). The rubber grommets provide vibration isolation.
lb (kg) 60 Hz 50 Hz
MC_69W MC_68W 282 (128)
Split System Models · Model Net Weight


3/8" threaded rod (field-supplied)
3/8" washer Sleeve Isolator
3/8" hex nut 3/8" hex nut Nylock Unit base pan (ref)
The total external static pressure for the inlet and outlet ducts, including grille, must not exceed 0.5 inches of H2O. Hood intake dimensions should be the same as the condensing unit duct dimen- sions.
If the condensing unit is located close to the outside of the building, rain hoods must be installed. In addition, install a triple layer bird screen over rain hood openings to eliminate the possibility of insects, birds, water, or debris entering the unit.
Use flexible ductwork or nonflammable cloth collars to attach ductwork to the unit and to control vibration transmission to the building. Attach the ductwork to the unit using the flanges provided. Locate the unit and ductwork so that the return air does not short circuit to the supply air inlet.
Avoid directing the hot exhaust air toward adjacent doors or windows.
Normal operating sound may be objectionable if the condensing unit is placed directly over quiet work areas. Ductwork that runs through a conditioned space or is exposed to areas where condensation may occur must be insulated. Whenever possible, ductwork should be suspended using flexible hang- ers. Ductwork should not be fastened directly to the building structure. In applications where the ceil- ing plenum is used as the heat rejection domain, the discharge air must be directed away from the condensing unit air inlet and a screen must be added to the end of the discharge duct to protect ser- vice personnel.
For multiple unit installations, space the units so that the hot condensing unit exhaust air is not directed toward the air inlet of an adjacent unit.
23 & 33 kW
60 Hz 3500 (5947)
50 Hz 3500 (5947)
Split System Models · 3/8" hex nut · 3/8" fender washer

(812.8mm)
(1371.6mm)
(41.1mm)
(1219.2mm)
Customer-supplied threaded rods for module support from ceiling (typ. 4)
(85.7mm)
(368.3mm)
(539.8mm)
(44.5mm)
Shaded area indicates a recommended clearance of 30" (762mm) for component access and removal. Hanger Bracket
(854.1mm) (1316mm)
CENTERS THREADED ROD
CENTERS
1/2" (12.7mm) dia. holes for threaded rods (typ. 2 each end)
7/8" (22.2mm) & 1 1/8" (28.6mm) dia. knockouts electrical entrance for high voltage connection (Single Point Power Kit).
7/8" (22.2mm) & 1 1/8" (28.6mm) dia. knockouts electrical entrance for high voltage connection.
Single Point Power Kit connection to Evaporator.
Liquid Line male quick connect location
Suction Line male quick conect location.
7/8" (22.2mm) dia. electrical entrance for low voltage connection. 7/8" (22.2mm) dia. knockout electrical entrance for altermate control panel low voltage routing.


Field-supplied unit disconnect switch when factory unit disconnect switch is not supplied.
Heat rejection connection. Field-supplied 24V NEC Class 2 wiring. See Note 2. Wire connections from evaporator module. 1. 24V GND 2. 24V supply 3. High pressure alarm (optional) 4. Hot gas bypass connection (only on units with hot gas bypass)
Field-supplied 24V NEC Class 2 wiring between condensing unit and fan/coil unit
Split System Models


*Components are not supplied by Liebert but are recommended for proper circuit operation and maintenance.
Fluid Supply to Unit 3-Way Water Regulating Valve (optional)
Split System Models

For installation guidelines, refer to Installing the Indoor Condensing Unit on page 48.
It is recommended that manual service shut-off valves be installed at the supply and return line to each unit. This will provide for routine service or emergency isolation of the unit.
When the water source for the condenser is of poor quality, it is good practice to provide cleanable fil- ters in the supply line. These filters will trap the particles in the water supply and extend the service life of the water-cooled condenser.
Connection Size and Type
Condenser Water Inlet 1-1/8" OD Cu
Condenser Water Outlet 1-1/8" OD Cu
Suction Line 1-7/16" - 16 male #12 quick connect
Liquid Line 1-1/16" - 12 male #10 quick connect
Net Weight Glycol Volume
lb kg gal liters
7.6.2 Condenser Water Requirements
The standard maximum water pressure is 150 psig (1034 kPa). For applications above this pressure, consult the factory about high pressure systems.
The system will operate in conjunction with a cooling tower, city water, or drycooler.
Refer to 4.3.1 - Water Regulating Valve Adjustment and 4.3.3 - Testing Valve Function.
For split system glycol systems, use drycooler and pump data found in 5.0 - Glycol/GLYCOOL- Cooled Models. See Table 16 - Drycooler data.
Electrical control interconnect to drycooler is wired from water/glycol condensing unit.
Split System Models · Model

32 " 32 "
(812.8mm)
(812.8mm)
CABINET DIMENSION
Customer supplied threaded rods for module support from ceiling (typ. 4).
1/2" (12.7mm) dia. holes for module rigging (typ. 2 each end).
Shaded area indicates a recommended clearance of 30" (762mm)for component access and removal.
29 13/16 " 33 5/8 "
(854.1mm) (757.2mm)
THREADED ROD
CENTERS
CENTERS
to threaded rod centers.
7/8" (22.2mm) & 1 1/8" (28.6mm) dia. knockouts electrical entrance for line voltage connection 7/8" (22.2mm) & 1 1/8" (28.6mm) dia. knockouts electrical entrance for line voltage connection (Single Point Power Kit)
8 7/16 " (214.4mm)
7 " 3 3/4 "
(95.2mm) (177.8mm)
Suction Line male quick connect location
Liquid Line male quick connect location
1" (25.4mm) NPT Female Water/Glycol Inlet Connection
1" (25.4mm) NPT Female Water/Glycol Outlet Connection
7/8" (22.2mm) dia. knockout electrical entrance for alternate control panel low voltage routing. 7/8" (22.2mm) dia. electrical entrance for low voltage connection.


Field-supplied unit disconnect switch when factory unit disconnect switch is not supplied
Field-supplied 24V NEC Class1 wiring to drycooler (glycol-cooled units only)
Heat rejection connection. Field-supplied 24V NEC Class 2 wiring. Wire connections from evaporator mod: 1. 24V ground 2. 24V supply 3. High pressure alarm (optional) 4. Hot gas bypass connection (only on units with hot gas bypass)
Field-supplied 24V NEC Class 1 wiring between glycol condensing unit and drycooler
Remote drycooler connection; field-supplied 24V NEC Class 1 wiring (glycol-cooled units only)
Split System Models

Table 32 R407C pressure/temperature chart for operation and superheat (discharge/hot gas and suction gas)
Temperature Gauge Pressure Temperature Gauge Pressure Temperature Gauge Pressure
°F °C Psig kPa °F °C Psig kPa °F °C Psig kPa
0.0 -17.8 18.9 130 35.0 1.7 54.8 378 70.0 21.1 114.9 792
1.0 -17.2 19.6 135 36.0 2.2 56.1 387 72.0 22.2 119.3 822
2.0 -16.7 20.4 141 37.0 2.8 57.5 396 74.0 23.3 124 853
3.0 -16.1 21.2 146 38.0 3.3 58.9 406 76.0 24.4 128 885
4.0 -15.6 22.0 152 39.0 3.9 60.3 415 78.0 25.6 133 917
5.0 -15.0 22.8 157 40.0 4.4 62.2 429 80.0 26.7 138 950
6.0 -14.4 23.6 163 41.0 5.0 63.1 435 82.0 27.8 143 984
7.0 -13.9 24.5 169 42.0 5.6 64.6 445 84.0 28.9 148 1019
8.0 -13.3 25.4 175 43.0 6.1 66.1 456 86.0 30.0 153 1054
9.0 -12.8 26.2 181 44.0 6.7 67.6 466 88.0 31.1 158 1091
10.0 -12.2 27.1 187 45.0 7.2 69.1 476 90.0 32.2 164 1128
11.0 -11.7 28.0 193 46.0 7.8 70.7 487 92.0 33.3 169 1167
12.0 -11.1 28.9 200 47.0 8.3 72.2 498 94.0 34.4 175 1206
13.0 -10.6 29.9 206 48.0 8.9 73.8 509 96.0 35.6 181 1246
14.0 -10.0 30.8 213 49.0 9.4 75.4 520 98.0 36.7 187 1287
15.0 -9.4 31.8 219 50.0 10.0 77.1 531 100.0 37.8 193 1329
16.0 -8.9 32.8 226 51.0 10.6 78.7 543 102.0 38.9 199 1372
17.0 -8.3 33.8 233 52.0 11.1 80.4 554 104.0 40.0 205 1416
18.0 -7.8 34.8 240 53.0 11.7 82.1 566 106.0 41.1 212 1461
19.0 -7.2 35.8 247 54.0 12.2 83.9 578 108.0 42.2 219 1507
20.0 -6.7 36.9 254 55.0 12.8 85.6 590 110.0 43.3 225 1553
21.0 -6.1 38.0 262 56.0 13.3 87.4 603 112.0 44.4 232 1601
22.0 -5.6 39.0 269 57.0 13.9 89.2 615 114.0 45.6 239 1650
23.0 -5.0 40.1 277 58.0 14.4 91.0 628 116.0 46.7 247 1701
24.0 -4.4 41.3 284 59.0 15.0 92.9 640 118.0 47.8 254 1752
25.0 -3.9 42.4 292 60.0 15.6 94.8 653 120.0 48.9 262 1804
26.0 -3.3 43.6 300 61.0 16.1 96.7 666 122.0 50.0 269 1858
27.0 -2.8 44.7 308 62.0 16.7 98.6 680 124.0 51.1 277 1912
28.0 -2.2 45.9 317 63.0 17.2 100.5 693 126.0 52.2 285 1968
29.0 -1.7 47.1 325 64.0 17.8 102.5 707 128.0 53.3 294 2025
30.0 -1.1 48.4 333 65.0 18.3 104.5 721 130.0 54.4 302 2083
31.0 -0.6 49.6 342 66.0 18.9 106.5 735 132.0 55.6 311 2143
32.0 0.0 50.9 351 67.0 19.4 108.6 749 134.0 56.7 320 2203
33.0 0.6 52.1 359 68.0 20.0 110.7 763 136.0 57.8 329 2265
34.0 1.1 53.5 369 69.0 20.6 112.8 778 138.0 58.9 338 2329
- 140.0 60.0 347 2393
R407C Refrigerant

Temperature Pressure Gauge Temperature Pressure Gauge Temperature Pressure Gauge
°F °C Psig kPa °F °C Psig kPa °F °C Psig kPa
36.0 2.2 73 500 59.0 15.0 114 786 94.0 34.4 203 1402
37.0 2.8 74 511 60.0 15.6 116 801 96.0 35.6 209 1444
38.0 3.3 76 522 61.0 16.1 118 815 98.0 36.7 216 1488
39.0 3.9 77 533 62.0 16.7 120 830 100.0 37.8 222 1532
40.0 4.4 79 544 63.0 17.2 123 845 102.0 38.9 229 1578
41.0 5.0 81 556 64.0 17.8 125 860 104.0 40.0 236 1624
42.0 5.6 82 567 65.0 18.3 127 875 106.0 41.1 242 1671
43.0 6.1 84 579 66.0 18.9 129 891 108.0 42.2 249 1720
44.0 6.7 86 591 67.0 19.4 131 906 110.0 43.3 257 1769
45.0 7.2 87 602 68.0 20.0 134 922 112.0 44.4 264 1819
46.0 7.8 89 615 69.0 20.6 136 938 114.0 45.6 271 1870
47.0 8.3 91 627 70.0 21.1 138 954 116.0 46.7 279 1922
48.0 8.9 93 639 72.0 22.2 143 987 118.0 47.8 287 1975
49.0 9.4 95 652 74.0 23.3 148 1021 120.0 48.9 294 2029
50.0 10.0 96 664 76.0 24.4 153 1055 122.0 50.0 302 2085
51.0 10.6 98 677 78.0 25.6 158 1090 124.0 51.1 310 2141
52.0 11.1 100 690 80.0 26.7 163 1126 126.0 52.2 319 2198
53.0 11.7 102 704 82.0 27.8 169 1163 128.0 53.3 327 2256
54.0 12.2 104 717 84.0 28.9 174 1201 130.0 54.4 336 2315
55.0 12.8 106 730 86.0 30.0 180 1239 132.0 55.6 345 2376
56.0 13.3 108 744 88.0 31.1 185 1279 134.0 56.7 354 2437
57.0 13.9 110 758 90.0 32.2 191 1319 136.0 57.8 363 2500
58.0 14.4 112 772 92.0 33.3 197 1360 138.0 58.9 372 2563
- 140.0 60.0 381 2628
Measure the liquid pressure (e.g., 200 psig). Find the liquid saturation temperature at that pressure on Table 33 (e.g., 93°F). Measure the temperature of the liquid line (e.g., 90°F). Subtract the actual temperature from the liquid saturation temperature to obtain the subcooling (e.g., 93 – 90 = 3°F). If the actual temperature is greater than the liquid saturation temperature, then there is no subcooling, and the fluid may be a mixture of liquid and vapor.
R407C is a blend of refrigerants that exhibits a temperature “glide” of approximately 8 to 12°F (4 to 7°C. This “glide” is the difference between the liquid and vapor saturation temperatures at a given pressure. Use the correct table for the saturation temperature you need. Table 32 is for super- heat or operating controls. Table 33 is for subcooling only.
R407C Refrigerant

Ensuring The High Availability Of Mission-Critical Data And Applications.
Emerson Network Power, the global leader in enabling business-critical continuity, ensures network resiliency and adaptability through a family of technologies—including Liebert power and cooling technologies—that protect and support business-critical systems. Liebert solutions employ an adaptive architecture that responds to changes in criticality, density and capacity. Enterprises benefit from greater IT system availability, operational flexibility and reduced capital equipment and operating costs.
Web Site www.liebert.com
Monitoring 800-222-5877 Liebert.monitoring@emerson.com
800-222-5877 upstech@emersonnetworkpower.com
800-543-2378 powertech@emersonnetworkpower.com
800-543-2778 Outside the United States
614-888-0246 Locations United States 1050 Dearborn Drive P.O. Box 29186 Columbus, OH 43229
Europe Via Leonardo Da Vinci 8 Zona Industriale Tognana 35028 Piove Di Sacco (PD) Italy +39 049 9719 111 Fax: +39 049 5841 257
While every precaution has been taken to ensure the accuracy and completeness of this literature, Liebert Corporation assumes no responsibility and disclaims all liability for damages resulting from use of this information or for any errors or omissions. © 2008 Liebert Corporation All rights reserved throughout the world. Specifications subject to change without notice. ® Liebert is a registered trademark of Liebert Corporation. All names referred to are trademarks or registered trademarks of their respective owners.
Asia 7/F, Dah Sing Financial Centre 108 Gloucester Road, Wanchai Hong Kong 852 2572220 Fax: 852 28029250
EmersonNetworkPower.com Emerson Network Power. The global leader in enabling Business-Critical Continuity.
Embedded Computing Embedded Power Power Switching & Controls
Services Racks & Integrated Cabinets Outside Plant
Business-Critical Continuity, Emerson Network Power and the Emerson Network Power logo are trademarks and service marks of Emerson Electric Co.
©2008 Emerson Electric Co.
Pages referenced in this manual — manufacturer, support and downloads.
Owners and our team usually reply within a day — and your question helps the next person too.
Be the first to ask — other owners or our team will answer.