Official user manual

Emerson 7ADTB

17 pages·4.5 MB·Switch·PDF·ENDEFRITNLJA
Emerson 7ADTB
Table of Contents 65 sections 7000 Series 7ADTB Automatic Delayed–Transition Transfer · Operator’s · Manual · Rating Label · … ShowHide
Page 2 of the Emerson 7ADTB user manual — G 277 F 240
Page 2 · click to enlarge
Page 2

Nameplate The Transfer Switch nameplate includes data for each specific 7000 Series ADTB. Use the switch only within the limits shown on this nameplate. A typical Catalog Number is shown below with its elements explained.

Catalog Number Identification

Typical 7000 Series ADTB catalog no. for overlapping neutral, 3 pole, 600 amp, 480 V, ATS in Type 1 enclosure:

J7ADTB C 3 600 N 5 C

Amperes Voltage Controller Enclosure

3. three Ø 2 – single Ø

150 A 115 B 120

J 400

5. standard

C – type 1 F – type 3R

B – switched 5X – if

K 415

G – type 4

L – type 12

D 220

M 460

blank – open type

G 277 F 240

Q 575 P 550

R 600

H 380

Emerson 7ADTB — G 277 F 240 diagram (page 2)
Fig. 1
Show 18 more labels / short text on this page
Phase Poles Neutral · A – solid · 600 400 260 · accessories · ordered · blank – none · Standard · optional Accessory · Controls & Indicators · Transfer/Bypass · Status Panel · Group 5 Controller · Bypass · Handle · Isolation · Handle · Transfer · Switch (inside)
Page 3 of the Emerson 7ADTB user manual — Harnesses
Page 3 · click to enlarge
Page 3

SECTION 1 INSTALLATION

ASCO 7000 Series Automatic Delayed–Transition Transfer & Bypass–Isolation Switches (7ADTBs) are factory wired and tested. Field installation requires mounting and connection of service cables, and auxiliary control circuits (if required).

Testing Power Conductors

Do not connect the power conductors to the transfer switch until they are tested. Installing power cables in conduit, cable troughs and ceiling-suspended hangers often requires considerable force. The pulling of cables can damage insulation and stretch or break the conductor’s strands. For this reason, after the cables are pulled into position, and before they are connected, they should be tested to verify that they are not defective or have been damaged during installation.

Remove the Shipping Skid

Open the front door and remove the four lag screws (2 in front, 2 in rear) securing enclosure to the shipping skid.

Supporting Foundation

Protect the switch from construction grit and metal chips to prevent malfunction or

The supporting foundation for the enclosure must be level and straight. Refer to the applicable enclosure outline drawing included with the switch for all mounting details including door opening space.

shortened life of the 7ADTB switch.

Connecting Power Conductors

If bottom cable entry is used, the foundation must be prepared so that the conduit stubs are located correctly. Refer to the enclosure outline drawing for specified area and location. Provide cable bending space and clearance to live metal parts. When a concrete floor is poured, use interlocking conduit spacer caps or a wood or metal template to maintain proper conduit alignment.

After the power cables have been tested, connect them to the appropriate terminal lugs on the bypass switch as shown on the wiring diagram provided with the switch. Make sure the lugs provided are suitable for use with the cables being installed. Standard terminal lugs are solder- less screw type and will accept the wire sizes listed on the drawings provided with the 7ADTB. Be careful when stripping insulation from the cables; avoid nicking or ringing the conductor. Remove surface oxides from cables by cleaning with a wire brush. When aluminum cable is used, apply joint compound to conductors. Tighten cable lugs to the torque specified on rating label.

Mounting

Refer to the applicable enclosure outline drawing fur- nished with this switch and mount the automatic transfer switch according to details and instructions shown on diagram.

Controller Ground

A grounding wire must be connected to the controller’s lower left mounting stud. Because the controller is mounted on the enclosure door, a conductive strap must be used between the enclosure and the door. This connection provides proper grounding which does not rely upon the door hinges.

Line Connections

Refer to the Wiring Diagram provided with the switch. All wiring must be made in accordance with the National Electrical Code and local codes.

Do not remove the interphase barriers from the transfer switch. Always protect the transfer switch, bypass switch, and isolation contacts and mechanisms from construc- tion grit and metal chips when cabling.

Harnesses

The transfer switch is connected to the left side of the controller by a plug–in harness (two plugs).

De–energize the conductors before making any line or auxiliary circuitry connections. Be sure that Normal and Emergency line connections are in proper phase rotation. Place engine gen- erator starting control in the OFF position. Make sure engine generator is not in operation.

Page 4 of the Emerson 7ADTB user manual — Functional Test
Page 4 · click to enlarge
Page 4

INSTALLATION (continued)

Engine Starting Contacts

All customer connections, including the engine control contact connections, are located on terminal block TB which is mounted on the top right side of the enclosure. Refer to the wiring diagram provided with the automatic transfer switch and connect the engine start wires to the appropriate terminals. See Figure 1–1 and Table A.

Emerson 7ADTB — Engine Starting Contacts diagram (page 4)
Fig. 2 · Engine Starting Contacts

Table A. Engine start connections.

When normal source failsTerminals on Terminal Block TB contact closesTB1 and TB2 contact opensTB1 and TB3

Auxiliary Circuits

Connect auxiliary circuit wires to appropriate terminals on transfer switch terminal block TB as shown on the wiring diagram provided with this automatic transfer switch.

Figure 1-1. Customer terminal block on the top right

side of the enclosure.

Functional Test

The Functional Test consists of two checks:

Read all instructions on the Wiring Diagram and labels affixed to the automatic transfer & bypass–isolation switch. Note the control features that are provided and review their operation before proceeding.

❐1 — Voltage Checks, page 1–3

❐2 — Electrical Operation, page 1–4

Continue to 1 – Voltage Checks on next page.

Do these checks in the order presented

to avoid damaging the 7ADTB.

engine start connections · on customer · terminal block TB

Page 5 of the Emerson 7ADTB user manual — 1 – Voltage Checks
Page 5 · click to enlarge
Page 5

INSTALLATION (continued)

Emerson 7ADTB — INSTALLATION (continued) diagram (page 5)
Fig. 3 · INSTALLATION (continued)
Emerson 7ADTB — INSTALLATION (continued) diagram (page 5)
Fig. 4 · INSTALLATION (continued)

GREEN

RED

RED GREEN

AMBER

Figure 1-2. Standard controls and indicators.

1Close the normal source circuit breaker. The Transfer Switch Connected To Normal and the Normal Source Accepted lights should come on.Load Disconnect Active 2Use an accurate voltmeter to check phase to phase and phase to neutral voltages present at the transfer switch normal source terminals. 3Close the emergency source circuit breaker. (Start generator, if necessary.) The Transfer Switch Connected To Normal & Emergency Source Accepted lights should come on.Load Disconnect Active 4Use an accurate voltmeter to check phase to phase and phase to neutral voltages present at the transfer switch emergency source terminals.* 5Use a phase rotation meter to check phase rotation of emergency source; it must be the same as the normal source.A B C 6Shut down the engine–generator, if applicable. The Emergency Source Accepted light should go off. Then put the starting control selector switch (on the generator set) in the automatic position. Close enclosure door.Load Disconnect Active
Emerson 7ADTB — GREEN diagram (page 5)
Fig. 5

Functional Test

Read all instructions on the Wiring Diagrams and labels affixed to the 7ADTB. Note the control features that are provided and review their operation before proceeding.

After installing the 7ADTB check the following:

– Bypass Handle should be in the NORMAL position. – Isolation Handle should be in the CONN position. – CN transfer switch should be C (closed) – CE transfer switch should be O (open)

Emerson 7ADTB — Functional Test diagram (page 5)
Fig. 6 · Functional Test

If handles are not in correct positions, follow instructions for Bypassing and Isolating the automatic transfer switch in Section 3. Do not force the handles. Electrical interlocks prevent a wrong sequence of operation.

1 – Voltage Checks

First check nameplate on transfer switch; rated voltage must be the same as normal and emergency line voltages.

Use extreme caution when using a meter to measure voltages. Do not touch power terminals; shock, burns, or death could result !

Perform steps 1–6 at the right. Observe the status lights. See Figure 1–2.

Emerson 7ADTB — 1 – Voltage Checks diagram (page 5)
Fig. 7 · 1 – Voltage Checks
  • Black square means light is on. ❐ White square means light is off.

* If necessary, adjust voltage regulator on generator per the manufacturer’s recommendations. The 7ADTB will respond only to rated voltage specified on the nameplate.

Now continue to 2 – Electrical Operation on next page.

observe these lights

Page 6 of the Emerson 7ADTB user manual — Transfer Test
Page 6 · click to enlarge
Page 6

INSTALLATION (continued)

GREEN

RED

RED GREEN

AMBER

Figure 1-3. Standard controls and indicators.

1Turn and hold Transfer Control switch clockwise to Transfer Test until the engine starts and runs (within 15 sec.). The Emergency Source Accepted light should come on.Load Disconnect Active 2Transfer switch CN opens and the Transfer Switch Connected to Normal light should go off and the Load Disconnect Active light should come on. Both CN & CE contacts are now open.Load Disconnect Active 3After the delay transition time delay, the CE Transfer switch will operate to the Emergency position. The Transfer Switch Connected To Emergency light should come on and Load Disconnect Active light goes off.Load Disconnect Active 4Transfer switch will operate back to Normal position after Feature 3A time delay. For immediate retransfer turn Transfer Control counterclockwise to Retransfer Delay Bypass. The Transfer Switch Connected To Normal light should come on; Transfer Switch Connected to Emergency light should go off.Load Disconnect Active 5The engine–generator will stop after the Feature 2E time delay (unloaded running engine cooldown). The Emergency Source Accepted light should go off.Load Disconnect Active
Emerson 7ADTB — GREEN diagram (page 6)
Fig. 8

2 – Electrical Operation

This procedure checks electrical operation of the ADTS.

Close enclosure door before proceeding to prevent personal injury in case of electrical system fault.

Emerson 7ADTB — 2 – Electrical Operation diagram (page 6)
Fig. 9 · 2 – Electrical Operation

Transfer Test

The ATS should still be bypassed. Both normal and emergency sources must be available and the emergency source generator (if used) must be capable of being started; put engine starting control in automatic position. The Transfer Switch Connected to Normal light and the Normal Source Accepted light should be on.

Emerson 7ADTB — Transfer Test diagram (page 6)
Fig. 10 · Transfer Test
1. Turn the Isolation Handle counterclockwise to the TEST position.
Emerson 7ADTB — Transfer Test diagram (page 6)
Fig. 11 · Transfer Test
2. Perform steps 1–5 at right. Observe the status lights. See Figure 1–3.
  • Black square means light is on. ❐ White square means light is off.
3. Turn the Isolation Handle clockwise to the CONN (connected) position.
Emerson 7ADTB — Transfer Test diagram (page 6)
Fig. 12 · Transfer Test
4. Turn Bypass Handle clockwise to the OPEN position.

This completes the Functional Test of the 7ADTB.

operate this switch · observe these lights

Page 7 of the Emerson 7ADTB user manual — MANUAL LOAD TRANSFER
Page 7 · click to enlarge
Page 7

SECTION 2 TESTING & SERVICE

TRANSFER TEST

REPLACEMENT PARTS

Test the Automatic Transfer Switch portion of the 7000 Series 7ADTB at least once a month. This procedure checks the electrical operation of the Transfer Switchand Controller. Put the engine–generator starting control (at the engine–generator set) in automatic mode.

Replacement parts are available in kit form. When or- dering parts provide the Serial No., Bill of Material No. (BOM), and Catalog No. from the transfer switch name- plate. Contact your local ASCO Power Technologies Sales Office or ASI:

In the United States

In the following test the generator will start, the load will be transferred to the Emergency source, then back to the Normalsource. Aninterruptiontothe loadwill occur, un- less the the Transfer Switch contacts are bypassed before the test. See pages 3–1 through 3–4 for bypassing & iso- lating instructions if no interruption of load is required.

call 1 – 800 – 800 – ASCO ( 2726 )

In Canada

call 1 – 888 – 234 – ASCO ( 2726 )

DISCONNECTING THE CONTROLLER

The harness disconnect plugs are furnished for repair purposes only and should not have to be unplugged. If the controller must be isolated, follow these steps:

Be sure to close the enclosure door before proceeding to prevent personal injury

in case of electrical system fault.

Perform the five–step Electrical Operation – Transfer Test procedure on page 1–4.

Bypass–Isolation Switch is energized! Do not touch isolation contact fingers;

PREVENTIVE MAINTENANCE Reasonable care in preventive maintenance will insure high reliability and long life for the 7000 Series 7ADTB. An annual preventive maintenance program is recom- mended.

shock, burns, or death could result!

1. Bypass and Isolate the Automatic Transfer Switch.
2. Open the upper enclosure door.

ASCO Services, Inc. (ASI) is ASCO Power Technologies’s national service organization. In the US ASI can be contacted at 1-800-800-2726 for in- formation on preventive maintenance agreements.

3. Separate the two quick disconnect plugs by squeezing the latches. Do not pull on the harness wires.
1. The ATS should be still bypassed and isolated.

Checklist for Yearly Inspection

2. The two harness plugs and sockets are keyed. Carefully align the plugs with the sockets and press straight in until the latches click.

Hazardous voltage capable of causing shock,

3. Close the enclosure doors.

burns, or death is used in this switch. Deenergize both Normal – Emergency power

4. Follow Return to Service instructions on page 3–5.

sources before performing inspections!

MANUAL LOAD TRANSFER

❐Clean the 7ADTB enclosure.

Brush and vacuum away any excessive dust accumu- lation. Remove any moisture with a clean cloth. ❐Check the transfer switch contacts.

This procedure manually transfers load to other source if the Transfer Switch or Controller are out of service.

Bypass, isolate, and withdraw the transfer switch. Then remove the transfer switch interphase barriers andcheckthe conditionof thecontacts. Replacecon- tacts when pitted or worn excessively. Reinstall the interphase barriers carefully. See page 3–4. ❐Maintain transfer switch lubrication.

Close enclosure doors to prevent personal

injury in case of electrical system fault.

1. Bypass the connectedACTB source. Turn BypassHandle to EMERGENCY or NORMAL (see page 3–2).
2. Isolate to Test. Turn the Isolation Handle to TEST position (see page 3–3).

If switch is subjected to severe dust or abnormal operating conditions, renew factory lubrication on all movements and linkages. Relubricate solenoid operator if TS coil is replaced. Don’t use oil; order lubrication kit 75-100. ❐Check all cable connections & retighten them.

3. Turn the Bypass Handle to OPEN , then to the other source (see page 3–1). The load will be interrupted. 4. Turn the Isolation Handle clockwise to the CONN [connected] position (see page 3–4).

Disconnecting the Plugs · Reconnecting the Plugs

Page 8 of the Emerson 7ADTB user manual — MAINTENANCE HANDLE
Page 8 · click to enlarge
Page 8

TESTING & SERVICE (continued)

TROUBLE-SHOOTING

Hazardous voltage capable of causing shock,

burns, or death is used in this switch. Do not touch the power or load terminals

of the bypass switch or transfer switch!

Table B. Trouble-Shooting Checks.

PROBLEMCHECK IN NUMERICAL SEQUENCE 1 OPERATION2 GEN-SET3 VOLTAGE Engine–generator set does not start when the Transfer Control switch is turned and held in Transfer Test position or when normal source fails.Hold Transfer Test switch 15 seconds or the outage must be long enough to allow for Feature 1C time delay plus engine cranking and starting.Starting control must be in the automatic position. Batteries must be charged and connected. Check wiring to engine starting contacts.--- Transfer switch does not transfer the load to the emergency source after the engine–generator set starts.Wait for Feature 2B time delay to time out.Generator output circuit breaker must be closed. Generator frequency must be at least 95% of nominal (57 Hz for a 60 Hz system.) *Voltmeter should read at least 90% of nominal phase to phase voltage between terminals EA and EC (or EL1 and EL2 for 2 pole switches)* Transfer switch does not transfer the load to normal source when normal returns or when the Transfer Control switch is released.Wait for Feature 3A time delay to time out.---Voltmeter should read at least 90% of nominal phase to phase voltage between terminals NB and NC, NC and NA, and NA and NB (or NL1 and NL2 for 2 pole switches). Gen. does not stop after load retransfer to normal source.Wait for Feature 2E time delay to time out.Starting control must be in the automatic position.--- Load Disconnect Active light comes on.Wait for load disconnect time delay to time out.Explanation: Transfer switch in delayed transition transfer mode. Load disconnect time delay is adjustable from 0 to 5 min. 59 sec. Load Disconnect Active light stays on longer than 6 min.Check load disconnect time delay setting. Call ASI.Explanation: Transfer switch contacts are open longer than 5 min. 59 sec (maximum setting). Load remains disconnected.

* These are factory settings. Refer to Controller’s User’s Guide.

If the problem is isolated to circuits on the controller or the transfer switch, call your local ASCO Power Technologies sales office or ASI: in the United States, call 1–800–800–2726 or in Canada call 1–888–234–2726. Furnish the Serial No., Catalog No., and Bill of Material (BOM) No. from the transfer switch nameplate.

MAINTENANCE HANDLE

both upper and lower contact shafts. Observe the window indicators (right side). Remove the mainte- nance handle and store it on the lower left side.

Bypass and isolate the Transfer Switchbefore using the maintenance handle! See pages 3–1 through 3–4. Remove the maintenance handle after using it; store it inside.

window indicators O is open C is closed

contact position indicators (right side)

1. Bypass, isolate, and withdraw the transfer switch (pages3–1through 3–4). Then locateand removethe maintenance handle from the clip (inside lower left side). Insert the handle onto the shaft on the left side of the operator of the transfer switch See Figures 2–1, 2–2, 2–3 and Table C.
2. Move the maintenance handle up or down as shown to manually operate the transfer switch. Operate

Figure 2–1. Contact position indicators.

Show 4 more labels / short text on this page
Emergency contacts · (upper shaft) · Normal contacts · (lower shaft)
Page 9 of the Emerson 7ADTB user manual — LOWER SHAFT
Page 9 · click to enlarge
Page 9

TESTING & SERVICE (continued)

Emerson 7ADTB — TESTING & SERVICE (continued) diagram (page 9)
Fig. 13 · TESTING & SERVICE (continued)
Emerson 7ADTB — TESTING & SERVICE (continued) diagram (page 9)
Fig. 14 · TESTING & SERVICE (continued)

UP opens the Emergency source contacts

UPPER SHAFT

DOWN closes the Emergency source contacts

Figure 2–2. Maintenance handle operation for Emergency source contacts (upper shaft).

UP closes the Normal source contacts

LOWER SHAFT

DOWN opens the Normal source contacts

Figure 2–3. Maintenance handle operation for Normal source contacts (lower shaft).

Table C. Maintenance handle positions. ALL POWER MUST BE OFF !

Transfer Switch PositionInterlocked ShaftsMaintenance HandleShaft Indicators NormalE Nshaft extension cont act sh a f ts link shaft extensionupE = O upper contacts open N = C lower contacts closed up Load DisconnectedE NupE = O upper contacts open N = O lower contacts open down EmergencyE NdownE = C upper contacts closed N = O lower contacts open down

* Link between contact shafts prevents closing both N and E contacts. The shaft extension and contact shaft turn in opposite directions through a cam–follower mechanism. If Normal and Emergency connectios are reversed this operation is also reversed.

Show 6 more labels / short text on this page
handle · frame · shaft extension · handle · frame · shaft externsion
Page 10 of the Emerson 7ADTB user manual — TS ISOLATED
Page 10 · click to enlarge
Page 10

SECTION 3 BYPASSING & ISOLATING

Emerson 7ADTB — SECTION 3 BYPASSING & ISOLATING diagram (page 10)
Fig. 15

BYPASSING THE ATS* This procedure explains how to Bypass the closed transfer switch contacts. Bypassing is required before the Transfer Switch can be tested or isolated. The Bypass Switch Handle must be in the OPEN position (green window indicator) and the Isolation Handle must be in the CONN [connected] position (window indicator). The TS Connected light must be on. See Figures 3–1, 3–2, 3–3.

You can only bypass to the same source

that the Transfer Switch is connected. Solenoid interlock prevents incorrect operation.

1. Observe which Transfer Switch Connected To light is on ( Normal or Emergency) on the door. This is the position of the transfer switch (see Figure 3–2).
2. Follow the directions on next page to Bypass to the same source as connected to transfer switch (select Normal or Emergency).
Emerson 7ADTB — SECTION 3 BYPASSING & ISOLATING diagram (page 10)
Fig. 16

Window indicator shows yellow when ATS is bypassed to Emergency.

Window indicator shows green when the ATS is not bypassed.

Figure 3–1. Status lights and Engine Control.

Emerson 7ADTB — SECTION 3 BYPASSING & ISOLATING diagram (page 10)
Fig. 17

TRANSFER SWITCH

Upper green light is on if Transfer Switch is on Normal.

Window indicator shows yellow when ATS is bypassed to Normal.

CONNECTED TO NORMAL

Lower red light is on if Transfer Switch is on Emergency.

Figure 3–4. Bypass Handle and three position window indicators.

CONNECTED TO EMERGENCY

Figure 3–2. Status lights for Transfer Switch main

contact position.

Emerson 7ADTB — CONNECTED TO EMERGENCY diagram (page 10)
Fig. 18

TS CONNECTED Upper amber light should be on.

Allowable Positions of the Bypass Switch in relation to Positions of the Transfer Switch

TS TEST

(with Isolation Handle in the Conn [connected]

TS ISOLATED

position and TS Connected light on)

Transfer SwitchBypass Switch can be in either If Transfer Switch is in Normal position.Open orNormal If Transfer Switch is in Emergency position.Open orEmergency

Figure 3–3. Status lights for Transfer Switch isolation

contact position.

Page 11 of the Emerson 7ADTB user manual — BYPASSED TO EMERGENCY
Page 11 · click to enlarge
Page 11

To Bypass Normal Source* To Bypass Emergency Source* (Load connected to Normal Source) The Transfer Switch Connected To Normal light is on and Transfer Switch Connected To Emergency light is off.

(Load connected to Emergency Source) The Transfer Switch Connected To Emergency light is on

and Transfer Switch Connected To Normal light is off.

Push in the handle and turn it counterclockwise.* Turn the handle clockwise.*

Push in* the Bypass Handle all the way, then turn it counterclockwise until Bypass Switch Position shows closed on NORMAL (yellow window indicator). The green light Bypassed to Normal will come on and the amber light Not In Automatic will flash.

Turn* the Bypass Handle clockwise until Bypass Switch Position shows closed on EMERGENCY (yellow window indicator). The red lightBypassed toEmergency willcome on and the amber light Not In Automatic will flash.

Push in Bypass Handle

Bypass Switch Turn Bypass Handle clock- wise.

and turn it counter- clockwise.

ATS

ATS

Figure 3–5. Bypass to Normal diagram.

Figure 3–7. Bypass to Emergency diagram.

Emerson 7ADTB — ATS diagram (page 11)
Fig. 19
Emerson 7ADTB — ATS diagram (page 11)
Fig. 20

Upper green light comes on

BYPASSED TO NORMAL

BYPASSED TO NORMAL

Lower red light comes on

BYPASSED TO EMERGENCY

BYPASSED TO EMERGENCY

Emerson 7ADTB — BYPASSED TO EMERGENCY diagram (page 11)
Fig. 21

Upper window indicator EMERGENCY shows yellow

Lower window indicator NORMAL shows yellow

Figure 3–6. Status light and window indicator for

Figure 3–8. Status light and window indicator for

Bypassed to Emergency Source. The automatic transfer switch can now be put in the TEST or OPEN position. See ISOLATING on page 3–3.

Bypassed to Normal Source.

* NOTE: When Accessory 40*B (reversed Normal & Emergency connections) is specified, the handle operation is reversed. Follow instructions on the door.

Page 12 of the Emerson 7ADTB user manual — CONN
Page 12 · click to enlarge
Page 12

ISOLATING THE ATS

Isolating is required before any service work can be performed on the automatic transfer switch (ATS). Refer to Figures 3–9, 3–10, 3–11, and 3–12.

Hazardous voltage capable of causing

1. Bypass the closed automatic transfer switchcontacts. See BYPASSING on pages 3–1 and 3–2.

electrical shock, burns, or death; do not touch any control circuit terminals.

2. TurntheIsolationHandle counterclockwise(approx. 8 turns) until window shows TEST . The TS Test amber light should come on. The ATS can be tested now without load interruption (see page 2–1).
3. Continue turningIsolation Handlecounterclockwise (approx. 6 turns) until the window shows ISOLATE . The TS Isolated amber light should come on.

Turn crank counter- clockwise until window shows ISOLATE.

Turn crank counter- clockwise until window shows TEST.

Figure 3–11. TEST to ISOLATE position.

Figure 3–9. CONNECTED to TEST position.

Emerson 7ADTB — ISOLATING THE ATS diagram (page 12)
Fig. 22
Emerson 7ADTB — ISOLATING THE ATS diagram (page 12)
Fig. 23

TS CONNECTED Middle amber light should be on.

TS CONNECTED

TS TEST

TS TEST

Lower amber light should be on.

TS ISOLATED

TS ISOLATED

Emerson 7ADTB — TS ISOLATED diagram (page 12)
Fig. 24

CONN

CONN

TEST ISOLATE

TEST ISOLATE

out the transfer switch

out the transfer switch

Figure 3–10. Isolation Handle turned to TEST.

Figure 3–12. Isolation Handle turned to ISOLATE.

Show 6 more labels / short text on this page
Automatic Transfer Switch · Automatic Transfer Switch · position window · counterclockwise – draws · position window · counterclockwise – draws
Page 13 of the Emerson 7ADTB user manual — Contact Inspection
Page 13 · click to enlarge
Page 13
4. Open the lower enclosure door. Pull outboth leftand right side rails then use the two tab handlesto rollout the transfer switch. It can be safely inspected in this position. Thetransfer switchcan alsobe removedfor easier maintenance operations. See Figure 3–13.

1. Deenergize transfer switch (pages 3–1 thru 3–4) Bypass, isolate, and withdraw transfer switch. Use a voltmeter to verify that no electrical power is present at the transfer switchterminals. 2. Use the maintenance handle (page 2–2). Open the contacts that will be inspected by using the detachable maintenance handle. 3. Remove the barrier (Figure 3–14). Use a phillip screwdriver to loosen (ccw) four or six captive round–head screws holding the barrier to the arc chutes. Then pull the barrier straight outward to remove it.

Hazardous voltage capable of causing

electrical shock, burns, or death; do not touch any control circuit terminals.

Emerson 7ADTB — Contact Inspection diagram (page 13)
Fig. 25 · Contact Inspection
4. Reinstall the barrier . Install the barrier over the arc chutes. Use a phillips screwdriver to tighten (cw) the four or six round–head screws to secure the barrier to the arc chute insulator nuts. See Figure 3–14.
Emerson 7ADTB — Contact Inspection diagram (page 13)
Fig. 26 · Contact Inspection

right rail left rail

Figure 3–13.Transfer switch isolated

and pulled out for inspection. See page 2–2 for maintenance handle use. A lifting yoke 812053 is available to facilitate lifting by using an overhead crane or similar equipment. See WARNING.

The Transfer Switch weighs about 150 lbs. depending upon the number of poles. Use lifting device 812053 or other device capable of lifting this weight to avoid personal injury or equipment damage. Two persons are recommended.

Contact Inspection

Contact condition should be checked annually. Discoloration is normal. Do not file contacts because it wastes material. Instead use light emery paper to clean up the contact surfaces. The non–replaceable main contacts are designed to last the life of the transfer switch.

To prevent the possibility of fatal electrical shocks and burns, bypass, isolate, and withdraw the transfer switch before working on it.

Figure 3–14. Barrier removal.

tab handles

Page 14 of the Emerson 7ADTB user manual — To change the position of transfer switch
Page 14 · click to enlarge
Page 14

RETURN TO SERVICE

This procedure explains how to return the automatic transfer switch (ATS) to service after inspection and maintenance. Observe the Bypass Switch Position indica- tor and lights).

TS CONNECTED Middle amber light should come on.

TS TEST

TS ISOLATED

1. Use the two tab handles to roll the transfer switch into the enclosure (isolation contacts facing inward) until the crank bearings stop against the draw–in plates. Then push in both side rails and close the enclosure door.
Emerson 7ADTB — TS TEST diagram (page 14)
Fig. 27

position window TEST clockwise – draws in

the transfer switch Figure 3–17. Isolation Handle turned to TEST. 3. TheATScan betested nowwithout loadinterruption (see page 2–1).

right rail left rail

Figure 3–15.Transfer switch isolated

Solenoid interlock prevents you from closing

and pulled out for inspection.

the isolation contacts until the ATS is in the

same position as the Bypass Switch.

4. Observewhich Bypass Switch Position windowindicator is yellow ( NORMAL or EMERGENCY ) at the Bypass Switch Handle. This indicates the source connected to the load. 5. Observe which Transfer Switch Connected To light is on ( Normal or Emergency ) on the door. This is the positionoftheTransferSwitch. If itis notin thesame position as the Bypass Handle change the position of the Transfer Switch as follows:

Close the enclosure door to prevent personal

injury in case of electrical system fault.

2. Turn Isolation Handle clockwise (approx. 6 turns) until the window shows TEST and TS TEST light comes on.

Turn crank clockwise until window shows TEST.

To change the position of transfer switch

Operate to NORMAL Operate to EMERGENCY Turn Transfer Control switch to Retransfer Delay Bypass.

Turn Transfer Control switch to Transfer Test (hold 15 seconds).* Connected To Normal light should come on.

Connected To Emergency light should comes on.

* If Feature 2B time delay is used, there will be a delay before transfer to Emergency.

Figure 3–16. ISOLATE to TEST position.

tab handles · Automatic Transfer Switch

Page 15 of the Emerson 7ADTB user manual — TS TEST
Page 15 · click to enlarge
Page 15

Do not close the isolation contacts unless

the Transfer Switch (ATS) and Bypass

Switch are in the same position!

6. When the transfer switch is in the same position as the Bypass Switch handle, continue turning the Isolation Handle clockwise (about 8 turns) until the window shows CONN (connected).

Turn crank clockwise until window shows TEST.

Figure 3–18. TEST to CONN (connected) position.

TS CONNECTED Upper amber light should be on.

TS TEST

TS ISOLATED

Emerson 7ADTB — TS TEST diagram (page 15)
Fig. 28

position window CONN clockwise – draws in

Figure 3–19. Isolation Handle turned to CONN.

Automatic Transfer Switch · the transfer switch

Page 16 of the Emerson 7ADTB user manual — ATS
Page 16 · click to enlarge
Page 16

RETURN TO SERVICE continued*

Window indicator shows yellow when ATS is bypassed to Emergency.

This procedure explains how to return the Bypass Switch Handle to the OPEN position. The Bypass Handle must be in the CLOSED position (yellow indicator on NOR- MAL or EMERGENCY) and the Isolation Handle must be in the CONN position (window). See Figures 3–20, 3–21, and 3–22.

Window indicator shows green when the ATS is not bypassed.

You can only bypass to the same source

that the ATS is connected. Solenoid interlock prevents incorrect operation.

1 Observe which Bypass Switch Position indicator is yellow (NORMAL or EMERGENCY) at the Bypass Switch Handle. This indicates the source connected to the load. 2 Un–Bypass to same source as the Bypass Switch Position as follows (select Normal or Emergency).

Window indicator shows yellow when ATS is bypassed to Normal.

Figure 3–20. Bypass Handle and position indicators.

To Un–Bypass Normal Source* To Un–Bypass Emergency Source* (Load connected to Normal Source) The Transfer Switch Connected To Normal light is on and Transfer Switch Connected To Emergency light is off.

(Load connected to Emergency Source) The Transfer Switch Connected To Emergency light is on

and Transfer Switch Connected To Normal light is off.

Turn the handle clockwise.* Turn the handle counterclockwise.*

Turn* the Bypass Handle clockwise until the Bypass Switch Position shows OPEN (green window indicator). The Bypassed to Normal light should go off and the Not In Automatic light should go off.

Turn* the Bypass Handle counterclockwise until the Bypass Switch Position shows OPEN (green window indicator). The Bypassed to Emergency light should go off and the Not In Automatic light should go off.

Bypass Switch Turn Bypass Handle counter- clockwise.

Turn Bypass Handle clockwise.

ATS

ATS

Figure 3–21. Un–Bypass Normal diagram.

Figure 3–22. Un–Bypass Emergency diagram.

The Automatic Transfer & Bypass–Isolation Switch should be left in this position.

* NOTE: When Accessory 40*B (reversed Normal & Emergency connections) is specified, the handle push–pull operation is reversed. Follow instructions on the door.

Sources

References & links

Pages referenced in this manual — manufacturer, support and downloads.

Fix-it

Troubleshooting

Common problems, likely causes, and what to do.

ProblemPossible causeRemedy
1 OPERATION p.8
Engine–generator set does not start when the Transfer Control switch is turned and held in Transfer Test position or when normal source fails.Hold Transfer Test switch 15 seconds or the outage must be long enough to allow for Feature 1C time delay plus engine cranking and starting. p.8
Transfer switch does not transfer the load to the emergency source after the engine–generator set starts.Wait for Feature 2B time delay to time out. p.8
Transfer switch does not transfer the load to normal source when normal returns or when the Transfer Control switch is released.Wait for Feature 3A time delay to time out. p.8
Gen. does not stop after load retransfer to normal source.Wait for Feature 2E time delay to time out. p.8
Load Disconnect Active light comes on.Wait for load disconnect time delay to time out. p.8
Load Disconnect Active light stays on longer than 6 min.Check load disconnect time delay setting. Call ASI. p.8

Ask about the Emerson 7ADTB

Owners and our team usually reply within a day — and your question helps the next person too.

Add your email to get notified when it’s answered — no spam, ever.

0 questions
No questions yet about the Emerson 7ADTB

Be the first to ask — other owners or our team will answer.

Original document

Emerson 7ADTB manual PDF

17 pages·4.5 MB·Switch·PDF
Click any page above to open it here
Page 1 / …
100%
Loading pages…