This manual must only be used by a qualified heating installer / service technician. Read all instructions, including this manual and the Crest Service Manual, before installing. Perform steps in the order given. Failure to comply could result in severe personal injury, death, or substantial property damage.
Save this manual for future reference.
FB-I-O Rev I



Installer – Read all instructions, including this manual and the Crest Service Manual, before installing. Perform steps in the order given.
User – This manual is for use only by a qualified heating installer/ service technician. Refer to the User’s Information Manual for your reference.
Have this boiler serviced/inspected by a qualified service technician, at least annually.
Failure to comply with the above could result in severe personal injury, death or substantial property damage.
When calling or writing about the boiler – Please have the boiler model and serial number from the boiler rating plate.
Consider piping and installation when determining boiler location.
Any claims for damage or shortage in shipment must be filed immediately against the transportation company by the consignee.
Factory warranty (shipped with unit) does not apply to units improperly installed or improperly operated.
Failure to adhere to the guidelines on this page can result in severe personal injury, death, or substantial property damage.
If the information in this manual is not followed exactly, a fire or explosion may result causing property damage, personal injury or loss of life.
This appliance MUST NOT be installed in any location where gasoline or flammable vapors are likely to be present.

The Crest - How it works...
1. Front access panels Provides access to the controls compartment. 2. Top access panel Provides access to the burner compartment. 3. Air pressure switch The air pressure switch detects blocked flue/vent conditions. 4. Blowers The blowers pull in air and gas through the venturis (item 34). Air and gas mix inside the blowers and are pushed into the burner, where they burn inside the combustion chamber. 5. Boiler drain connection Location from which the heat exchanger can be drained. 6. Boiler inlet temperature sensor The boiler inlet temperature sensor monitors system return water temperature. If selected as the controlling sensor, the control module will adjust the boiler firing rate so the inlet temperature matches the set point. 7. Boiler outlet temperature sensor The boiler outlet temperature sensor monitors boiler outlet water temperature. If selected as the controlling sensor, the control module will adjust the boiler firing rate so the outlet temperature matches the set point. 8. Burner (not shown) Integral dual chamber design with a stress free metal fiber outer mesh and durable stainless steel structure. Provides two (2) independent firing rates up to 25:1 turndown. 9. Condensate drain connection The condensate drain connection provides a connection point to install a condensate drain line using flexible hose provided. 10. Control module (on control panel assembly) The control module responds to internal and external signals and controls the blowers, gas valves, and pump(s), depending on the application, to meet the heating demand. 11. Electronic display Digital controls with SMART TOUCH screen technology, full color display, and an 8" user interface screen. 12. Flame inspection windows Two large high temperature quartz observation windows provide views of each independent burner surface during firing. 13. Dual flame sensors The dual flame sensors are used by the control module to detect the presence of a burner flame at both independent burner surfaces. 14. Flue temperature sensor The flue sensor monitors flue gas temperature. The control module will modulate or shut the boiler down if the flue gas temperature gets too high. 15. Gas connection pipe The gas connection pipe is a threaded black iron pipe connection (see Gas Connections Section for specific model pipe size requirements). This pipe should be connected to the incoming gas supply to deliver gas to the boiler. 16. Gas shutoff valve (inside unit) The manual gas shutoff valve is used to isolate the boiler gas train from the gas supply. 17. Gas valves The gas valves sense the negative pressure created by the blowers, allowing gas to flow only if the gas valves are powered and combustion air is flowing. 18. Blower proving switches Prove adequate airflow during prepurge.
19. High limit devices (primary and backup) The high limit devices are used to monitor the outlet water temperature - if either device senses the water temperature exceeding the predetermined setting, the boiler will shut down. 20. Ignition electrode An electrical spark across the electrodes will ignite the first burner. 21. Line voltage junction box The line voltage junction box contains the connection points for the line voltage power to the boiler (and pumps if used). 22. Line voltage wiring connections (knockouts) Conduit connection points for the high voltage junction box. 23. Low gas pressure switch Monitors gas supply pressure to the boiler and shuts the boiler down in the event a low gas pressure condition occurs. 24. High gas pressure switch (not shown) Monitors gas supply pressure to the burner and shuts the boiler down in the event a high gas pressure condition occurs. 25. Low voltage connection board(s) Connection boards used to connect external low voltage devices. 26. Low voltage wiring connections (knockouts) Conduit connection points for the low voltage connection boards. 27. Low water cutoff probe (LWCO) Ensures adequate water is supplied to the boiler. In the event of inadequate water levels, the boiler will shut down. 28. Power switch The On/Off power switch provides the ability to turn line voltage power to the boiler on and off. 29. Relief valve The safety relief valve protects the heat exchanger from an over pressure condition. The boiler comes with a 50 PSI relief valve as standard equipment. Optional settings are available. 30. Reset switch Reset switch for the low water cutoff. Hold the switch for 10 seconds to reset. 31. Test switch The test switch permits manual triggering of the LWCO safety circuit to test the contacts and evaluate the integrity of the circuit. Hold the switch for 10 seconds to test. 32. Firetube heat exchanger High grade stainless steel WAVE
TM firetube design that extracts heat from flue gases and transfers it directly into boiler water. 33. Temperature and pressure gauge Monitors the outlet temperature of the boiler as well as the system water pressure. 34. Venturis Separate venturis control air and gas flow into two (2) independent burner sections. 35. Water inlet A 4" ANSI flange connects the return water from the system to the heat exchanger. 36. Water outlet A 4" ANSI flange connects the hot water supply from the boiler to the system. 37. Ignition transformer The transformer provides voltage to the ignition electrode (item 20). 38. Air arm temperature sensors (not shown) Monitors fuel-air delivery temperature to the burner. 39. Air inlet cover (shipped loose) Used with room air for combustion and to prevent debris from entering the boiler.




*For LP models the minimum input is 420 MBH.
Maximum allowed working pressure is located on the rating plate. NOTICE
Notes: 1. The ratings are based on standard test procedures prescribed by the United States Department of Energy. 2. Net AHRI ratings are based on net installed radiation of sufficient quantity for the requirements of the building and nothing need be added for normal piping and pickup. Ratings are based on a piping and pickup allowance of 1.15. 3. Crest boilers require special gas venting. Use only the vent materials and methods specified in the Crest Installation and Operation Manual. 4. Standard Crest boilers are equipped to operate from sea level to 4,500 feet only with no adjustments. 5. High altitude Crest boilers are equipped to operate from 3,000 to 12,000 feet. High altitude models are manufactured with different control parameters for high altitude operation, but the sequence of operation given in this manual remains the same as the standard boilers. A high altitude label (as shown in FIG A.) is also affi xed to the unit. 6. Standard Crest boilers will de-rate by 2.2% for each 1,000 feet above sea level up to 4,500 feet when combustion calibration is performed and CO2’s are adjusted to the recommended levels. 7. High altitude Crest boilers will de-rate by 1.4% for each 1,000 feet above sea level up to 5,500 feet and 1.8% for each 1,000 feet above 5,500 feet. 8. Ratings have been confi rmed by the Hydronics Section of AHRI.

Figure A High Altitude Label Location
of

Installation must comply with:
WARNING This appliance is certified as an indoor appliance.
Do not install the appliance outdoors or locate where the appliance will be exposed to freezing temperatures or to temperatures that exceed 100°F (37.8°C).
Do not install the appliance where the relative humidity may exceed 93%. Do not install the appliance where condensation may form on the inside or outside of the appliance, or where condensation may fall onto the appliance.
Failure to install the appliance indoors could result in severe personal injury, death, or substantial property damage.
The Crest gas manifold and controls met safe lighting and other performance criteria when the boiler underwent tests specified in ANSI Z21.13/CSA 4.9 – latest edition.
This appliance requires a special venting system. Use only the vent materials specified in this manual. Failure to follow all instructions can result in flue gas spillage and carbon monoxide emissions, causing severe personal injury or death.
Before locating the boiler, check:
Provide clearances:
If you do not provide the recommended service clearances shown, it may not be possible to service the boiler without removing it from the space.
Clearances from combustible materials
- Hot water pipes 1/4" - Sides 0" - Rear 0" - Front 0" - Top 0" - Floor Combustible - Vent pipe - Follow special vent system manufacturer’s instructions Recommended clearances for service access
- Sides 24" - Rear 24" - Front 30" - Top 24"
Figure 1-1 Recommended Service Clearances
Failure to keep boiler area clear and free of combustible materials, gasoline, and other flammable liquids and vapors can result in severe personal injury, death, or substantial property damage.

1/4" (6 MM) MINIMUM CLEARANCE AROUND HOT WATER PIPES

Provide air openings to room:
Vent and air piping
The Crest alone in boiler room
The Crest requires a special gas vent system, designed for pressurized venting.
The boiler is to be used for either direct vent installation or for installation using indoor combustion air. When room air is considered, see page 23 of this manual. Note prevention of combustion air contamination below when considering vent/ air termination.
Vent and air must terminate near one another and may be vented vertically through the roof or out a side wall, unless otherwise specified. You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the Crest using any other means.
The Crest in same space with other gas or oil-fired appliances
Be sure to locate the boiler such that the vent and air piping can be routed through the building and properly terminated. The vent/air piping lengths, routing and termination method must all comply with the methods and limits given in this manual.
The space must be provided with combustion/ventilation air openings correctly sized for all other appliances located in the same space as the Crest.
Prevent combustion air contamination
Install air inlet piping for the Crest as described in this manual. Do not terminate vent/air in locations that can allow contamination of combustion air. Refer to Table 1A, page 9 for products and areas which may cause contaminated combustion air.
Failure to comply with the above warnings could result in severe personal injury, death, or substantial property damage.
Ensure that the combustion air will not contain any of the contaminants in Table 1A, page 9. Contaminated combustion air will damage the boiler, resulting in possible severe personal injury, death or substantial property damage. Do not pipe combustion air near a swimming pool, for example. Also, avoid areas subject to exhaust fumes from laundry facilities. These areas will always contain contaminants. WARNING
The Crest is approved for installation on combustible flooring, but must never be installed on carpeting.
Do not install the boiler on carpeting even if foundation is used. Fire can result, causing severe personal injury, death, or substantial property damage.
If flooding is possible, elevate the boiler sufficiently to prevent water from reaching the boiler.
Assure that the floor and structure is sufficient to support the installed weight of the boiler, including the water content in the heat exchanger. If not, structural building failure will result, causing severe personal injury, death, or substantial property damage.
Flooring and foundation · Flooring

When using an existing vent system to install a new boiler:
Products to avoid:
Failure to follow all instructions can result in flue gas spillage and carbon monoxide emissions, causing severe personal injury or death.
Spray cans containing chloro/fluorocarbons
Check the following venting components before installing:
Chlorine-based swimming pool chemicals
Calcium chloride used for thawing
Sodium chloride used for water softening
Paint or varnish removers
Antistatic fabric softeners used in clothes dryers
Chlorine-type bleaches, detergents, and cleaning solvents found in household laundry rooms
Adhesives used to fasten building products and other similar products
Areas likely to have contaminants
Dry cleaning/laundry areas and establishments
With stainless steel vent, seal and connect all pipe and components as specified by the vent manufacturer used.
Furniture refinishing areas and establishments
WARNING If any of these conditions are not met,
the existing system must be updated or replaced for that concern. Failure to follow all instructions can result in flue gas spillage and carbon monoxide emissions, causing severe personal injury or death.

When removing a boiler from existing common vent system:
Do not install the Crest into a common vent with any other appliance except as noted in Section 2 on page 18. This will cause flue gas spillage or appliance malfunction, resulting in possible severe personal injury, death, or substantial property damage.
d. Place in operation the appliance being inspected.
Follow the lighting instructions. Adjust thermostat so appliance will operate continuously.
e. Test for spillage at the draft hood relief opening after
5 minutes of main burner operation. Use the flame of a match or candle, or smoke from a cigarette, cigar, or pipe.
Failure to follow all instructions can result in flue gas spillage and carbon monoxide emissions, causing severe personal injury or death.
f. After it has been determined that each appliance remaining connected to the common venting system properly vents when tested as outlined herein, return doors, windows, exhaust fans, fireplace dampers, and any other gas-burning appliance to their previous conditions of use.
At the time of removal of an existing boiler, the following steps shall be followed with each appliance remaining connected to the common venting system placed in operation, while the other appliances remaining connected to the common venting system are not in operation.
g. Any improper operation of the common venting
system should be corrected so the installation conforms with the National Fuel Gas Code, ANSI Z223.1/NFPA 54 and/or CAN/CSA B149.1, Natural Gas and Propane Installation Code. When re-sizing any portion of the common venting system, the common venting system should be resized to approach the minimum size as determined using the appropriate tables in Part 11 of the National Fuel Gas Code, ANSI Z223.1/NFPA 54 and/or CAN/CSA B149.1, Natural Gas and Propane Installation Code.
a. Seal any unused openings in the common venting
system.
b. Visually inspect the venting system for proper size and
horizontal pitch and determine there is no blockage or restriction, leakage, corrosion, or other deficiencies, which could cause an unsafe condition.
c. Test vent system – Insofar as is practical, close all
building doors and windows and all doors between the space in which the appliances remaining connected to the common venting system are located and other spaces of the building. Turn on clothes dryers and any appliance not connected to the common venting system. Turn on any exhaust fans, such as range hoods and bathroom exhausts, so they will operate at maximum speed. Do not operate a summer exhaust fan. Close fireplace dampers.

Remove boiler from wood pallet
Figure 1-3 Boiler Removed from Shipping Pallet

a. Remove the three (3) shipping bolts located inside the controls compartment securing the boiler to the front of the pallet (see FIG. 1-2).
b. Remove the three (3) shipping bolts that fasten the tie-down brackets securing the legs to the rear of the pallet (FIG. 1-2).
c. The boiler can now be removed from the pallet using a lift truck lifting from the front or rear of the boiler. If lifting from the front, the lift truck forks must extend at least half way under the boiler heat exchanger to assure proper lifting technique with no damage to the boiler.
Maintain minimum specified clearances for adequate operation. All installations must allow sufficient space for servicing the vent connections, water pipe connections, piping and other auxiliary equipment, as well as the appliance. The clearance labels on each appliance note the same service and combustible clearance requirements as shown in this manual.
Failure to assure the truck forks are long enough to extend at least halfway under the boiler heat exchanger will result in the boiler tipping off the lift truck, and potentially falling. This will result in severe personal injury, death, or substantial property damage.
Multiple boilers may be installed side by side with no clearance between adjacent boilers because this boiler is approved for zero clearance from combustible surfaces; however, service access will be limited from the sides.
d. If lifting by crane is desired, remove the top access panels to gain access to the lifting lugs located on the boiler (see FIG. 1-3). It is also recommended that the upper and lower front panels along with both front side panels be removed (no tools required).
Consult the Venting section of this manual for specific installation instructions for the appropriate type of venting system that you will be using.
Do not drop the boiler or bump the jacket on the floor or pallet. Damage to the boiler can result.
Figure 1-2 Boiler Mounted on Shipping Pallet


Combustion and ventilation air requirements for appliances drawing air from the equipment room

Provisions for combustion and ventilation air must be in accordance with Air for Combustion and Ventilation, of the latest edition of the National Fuel Gas Code, NFPA 54 / ANSI Z223.1, in Canada, the latest edition of CGA Standard B149 Installation Code for Gas Burning Appliances and Equipment, or applicable provisions of the local building codes.
The equipment room MUST be provided with properly sized openings and/or be of sufficient volume to assure adequate combustion air and proper ventilation for all gas fired appliances in the equipment room to assure adequate combustion air and proper ventilation.
The requirements shown are for the appliance only; additional gas fired appliances in the equipment room will require an increase in the net free area and/or volume to supply adequate combustion air for all appliances.

No combustion air openings are needed when the appliance is installed in a space with a volume NO LESS than 50 cubic feet per 1,000 Btu/hr of all installed gas fired appliances and the building MUST NOT be of “Tight Construction”3.
A combination of indoor and outdoor combustion air may be utilized by applying a ratio of available volume to required volume times the required outdoor air opening(s) size(s). This must be done in accordance with the National Fuel Gas Code, NFPA 54 / ANSI Z223.1.

3. If air is taken from another interior space combined with the equipment room: (a) Two spaces on same story: Each of the two openings specified above should have a net free area of one square inch for each 1000 Btu/hr (22 cm2 per kW) of input, but not less than 100 square inches (645 cm2) (see FIG. 1-6). (b) Two spaces on different stories: One or more openings should have a net free area of two square inches per 1000 Btu/hr (44 cm2 per kW).

Figure 1-7_Combustion Air from Outside - Single Opening 12

CAUTION Under no circumstances should the equipment room ever be under negative pressure. Particular care should be taken where exhaust fans, attic fans, clothes dryers, compressors, air handling units, etc., may take away air from the unit.
Combustion air requirements are based on the latest edition of the National Fuel Gas Code, NFPA 54 / ANSI Z223.1; in Canada refer to the latest edition of CGA Standard CAN/CSA B149.1. Check all local code requirements for combustion air.
The combustion air supply must be completely free of any flammable vapors that may ignite or chemical fumes which may be corrosive to the appliance. Common corrosive chemical fumes which must be avoided are fluorocarbons and other halogenated compounds, most commonly present as refrigerants or solvents, such as Freon, trichlorethylene, perchlorethylene, chlorine, etc. These chemicals, when burned, form acids which quickly attack the stainless steel heat exchanger, headers, flue collectors, and the vent system.
All dimensions based on net free area in square inches. Metal louvers or screens reduce the free area of a combustion air opening a minimum of approximately 25%. Check with louver manufacturers for exact net free area of louvers.
Where two openings are provided, one must be within 12" (30 cm) of the ceiling and one must be within 12" (30 cm) of the floor of the equipment room. Each opening must have a net free area as specified in Table 1B. Single openings shall commence within 12" (30 cm) of the ceiling. The minimum dimension of air openings shall not be less than 3" (80 mm).
The result is improper combustion and a non-warrantable, premature appliance failure.
EXHAUST FANS: Any fan or equipment which exhausts air from the equipment room may deplete the combustion air supply and/or cause a downdraft in the venting system. Spillage of flue products from the venting system into an occupied living space can cause a very hazardous condition that must be corrected immediately.

Inside Air from 2 Ducts Delivered from Interior Space2 *Outside Air from 1 Opening Directly from Outdoors, in2
*Outside Air from 2 Openings Directly from Outdoors1
*Outside Air from 2 Ducts Delivered from Outdoors1
The above requirements are for the appliance only; additional gas fired appliances in the equipment room will require an increase in the net free area and/or volume to supply adequate combustion air for all appliances. No combustion air openings are needed when the appliance is installed in a space with a volume NO LESS than 50 cubic feet per 1,000 Btu/hr of all installed gas fired appliances. Buildings MUST NOT be of *“Tight Construction”3.
1Outside air openings shall directly communicate with the outdoors.
2Combined interior space must be 50 cubic feet per 1,000 Btu/hr input. Buildings MUST NOT be of *“Tight Construction”.
3”Tight Construction” is defined as a building with less than 0.40 ACH (air changes per hour). For buildings of “Tight Construction”, provide air openings into the building from outside.



DANGER The Crest must be vented and supplied with combustion and ventilation air as described in this section. Ensure the vent and air piping and the combustion air supply comply with these instructions regarding vent system, air system, and combustion air quality. See also Section 1 of this manual.
Sealing of Type “B” double-wall vent material or galvanized vent pipe material used for air inlet piping on a sidewall or vertical rooftop Combustion Air Supply System:
a. Seal all joints and seams of the air inlet pipe using either Aluminum Foil Duct Tape meeting UL Standard 723 or 181A-P or a high quality UL Listed silicone sealant such as those manufactured by Dow Corning or General Electric.
Inspect finished vent and air piping thoroughly to ensure all are airtight and comply with the instructions provided and with all requirements of applicable codes.
b. Do not install seams of vent pipe on the bottom of horizontal runs.
c. Secure all joints with a minimum of three sheet metal screws or pop rivets. Apply Aluminum Foil Duct Tape or silicone sealant to all screws or rivets installed in the vent pipe.
Failure to provide a properly installed vent and air system will cause severe personal injury or death.
d. Ensure that the air inlet pipes are properly supported.
The PVC, CPVC, or ABS air inlet pipe should be cleaned and sealed with the pipe manufacturer’s recommended solvents and standard commercial pipe cement for the material used. The ABS, PVC, CPVC, Dryer Vent or Flex Duct air inlet pipe should use a silicone sealant to ensure a proper seal at the appliance connection and the air inlet cap connection. Dryer vent or flex duct should use a screw type clamp to seal the vent to the appliance air inlet and the air inlet cap. Proper sealing of the air inlet pipe ensures that combustion air will be free of contaminants and supplied in proper volume.
Air inlet pipe materials:
The air inlet pipe(s) must be sealed. Choose acceptable combustion air inlet pipe materials from the following list:
ABS, PVC, or CPVC Dryer Vent or Sealed Flexible Duct (not recommended for rooftop air inlet) Galvanized steel vent pipe with joints and seams sealed as specified in this section. Type “B” double-wall vent with joints and seams sealed as specified in this section. AL29-4C, stainless steel material to be sealed to specification of its manufacturer.
*Plastic pipe may require an adapter (not provided) to transition between the air inlet connection on the appliance and the plastic air inlet pipe.
WARNING Using vent or air intake materials other
than those specified, failure to properly seal all seams and joints or failure to follow vent pipe manufacturer’s instructions can result in personal injury, death or property damage. Mixing of venting materials will void the warranty and certification of the appliance.

When a sidewall or vertical rooftop combustion air supply system is disconnected for any reason, the air inlet pipe must be resealed to ensure that combustion air will be free of contaminants and supplied in proper volume.
DANGER Failure to properly seal all joints and seams as required in the air inlet piping may result in flue gas recirculation, spillage of flue products and carbon monoxide emissions causing severe personal injury or death.
Vent and air piping
This product has been approved for use with stainless steel vent systems.
Use only the materials, vent systems, and terminations listed in Table 2A. DO NOT mix vent systems of different types or manufacturers, unless listed in this manual. Failure to comply could result in severe personal injury, death, or substantial property damage.
Figure 2-1 Combustion Air Adapter

Installations must comply with applicable national, state, and local codes. Stainless steel vent systems must be listed as a UL-1738 approved system for the United States and a ULC-S636 approved system for Canada.
Installation of a stainless steel vent system should adhere to the stainless steel vent manufacturer’s installation instructions supplied with the vent system.
The Crest uses model specific combustion air intake and vent piping sizes as detailed in Tables 2B and 2C on page 17.
Increasing or decreasing combustion air or vent piping to sizes not specified in this manual is not authorized.
Table 2A Approved Stainless Steel Vent Manufacturers

Approved Stainless Steel Vent Manufacturers Make Model ProTech Systems (Simpson Dura-Vent Co.) FasNSeal Vent Z-Flex (Nova Flex Group) Z-Vent Heat Fab (Selkirk Corporation) Saf-T Vent Metal Fab Corr/Guard Securities Chimneys International Secure Seal SS Schebler Chimney Systems eVent
Air intake/vent connections

Table 2B Direct Vent Minimum / Maximum Allowable Air / Vent Lengths

AIR INLET VENT Input De-Rate per 25 feet of Vent Air Intake
FB 1500 7" 12' 100' 7" 12' 100' 2% FB 2000 8" 12' 100' 8" 12' 100' 2%
FB 2500 8" 12' 100' 9" 12' 100' 2%
FB 3000 10" 12' 100' 10" 12' 100' 2%
FB 3500 10" 12' 100' 10" 12' 100' 2%
Table 2C Room Air Minimum / Maximum Allowable Air / Vent Lengths

25 feet of Vent FB 1500 7" 12' 100' 1% FB 2000 8" 12' 100' 1%
When determining equivalent combustion air and vent length, add 5 feet (1.5m) for each 90° elbow and 3 feet (.9 m) for each 45° elbow.
Vent, air piping and termination:
The Crest vent and air piping can be installed through the roof or through a sidewall. Follow the procedures in this manual for the method chosen. Refer to the information in this manual to determine acceptable vent and air piping length.
EXAMPLE: 20 feet (6 m) of pipe + (4) 90° elbows + (3) 45° elbows = 49 equivalent feet (15 m) of piping.
Removing from existing vent
Pool and laundry products and common household and hobby products often contain fluorine or chlorine compounds. When these chemicals pass through the boiler, they can form strong acids. The acid can eat through the boiler wall, causing serious damage and presenting a possible threat of flue gas spillage or boiler water leakage into the building.
Follow the instructions in Section 1, page 10 of this manual when removing a boiler from an existing vent system.
Vent and air piping
Vent and air system:
Installation must comply with local requirements and with the National Fuel Gas Code, NFPA 54 / ANSI Z223.1 for U.S. installations or CSA B149.1 for Canadian installations.
Please read the information given in Table 1A, page 9, listing contaminants and areas likely to contain them. If contaminating chemicals will be present near the location of the boiler combustion air inlet, have your installer pipe the boiler combustion air and vent to another location, per this manual.
If the boiler combustion air inlet is located in a laundry room or pool facility, for example, these areas will always contain hazardous contaminants.
You must also install air piping from outside to the boiler air intake adapter. The resultant installation is direct vent (sealed combustion).
You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the Crest using any other means.
To prevent the potential of severe personal injury or death, check for areas and products listed in Table 1A, page 9 before installing the boiler or air inlet piping.
DO NOT mix components from different systems. The vent system could fail, causing leakage of flue products into the living space. Use only approved stainless steel pipe and fittings.
If contaminants are found, you MUST:
Air contamination

Table 2D Flue Damper Kits
Crest boilers may be common vented; however, the following criteria MUST BE followed:
FB1500 7" DRH30000
FB2500 9" DRH30002
FB3500 10" DRH30003
For approved common vent sizing, contact the factory.
WARNING When Crest boilers are common vented,
the criteria above MUST BE followed. Failure to follow all these requirements will result in severe personal injury, death, or substantial property damage.
Common venting

Follow instructions below when determining vent location to avoid possibility of severe personal injury, death or substantial property damage.
Figure 3-2 Vertical Termination of Air and Vent w/Rain Cap

WARNING Do not connect any other appliance to the
vent pipe or multiple boilers to a common vent pipe except as noted in Section 2 on page 18. Failure to comply could result in severe personal injury, death, or substantial property damage.
VENT OUTLET 36" [914 MM] MINIMUM ABOVE AIR INLET
Installation must comply with local requirements and with the National Fuel Gas Code, NFPA 54 / ANSI Z223.1 - latest edition for U.S. installations or CSA B149.1 Installation Code for Canadian installations.
12" [305 MM] MINIMUM ABOVE ROOF / SNOW LINE
Determine location Locate the vent/air terminations using the following guidelines:
1. The total length of piping for vent or air must not exceed the limits given in the General Venting Section on page 17 of this manual. 2. The vent must terminate at least 3 feet above the highest place in which the vent penetrates the roof and at least 2 feet above any part of a building within 10 horizontal feet. 3. The air piping must terminate in a down-turned 180° return pipe no further than 2 feet (.6 m) from the center of the vent pipe. This placement avoids recirculation of flue products into the combustion air stream. 4. The vent piping must terminate in an up-turned coupling as shown in FIG. 3-1. The top of the coupling or the rain cap must be at least 36" (914 mm) above the air intake. The air inlet pipe and vent pipe can be located in any desired position on the roof, but must always be no further than 2 feet (.6 m) apart and with the vent termination at least 36" (914 mm) above the air intake.
Rooftop vent and air inlet terminations must terminate in the same pressure zone, unless vertical vent sidewall air is set up as shown in the General Venting - Vertical Vent, Sidewall Air Section.
Figure 3-1 Vertical Termination of Air and Vent

12" [305 MM] MINIMUM ABOVE ROOF / SNOW LINE
Prepare roof penetrations · Termination and fittings

Figure 3-4 Alternate Vertical Terminations with Multiple Boilers

Terminate all vent pipes at the same height and all air pipes at the same height to avoid recirculation of flue products and the possibility of severe personal injury, death, or substantial property damage.
Figure 3-3 Vertical Terminations with Multiple Boilers

12” (305 MM) 12” (305 MM) 12” (305 MM)
12” (305 MM) 12” (305 MM) 12” (305 MM)
Multiple vent/air terminations

Follow instructions below when determining vent location to avoid possibility of severe personal injury, death, or substantial property damage.
WARNING Sidewall vent and air inlet terminations must terminate in the same pressure zone.
f. Do not terminate above any door or above or below any window. Condensate can freeze, causing ice formations. g. Locate or guard vent to prevent condensate damage to exterior finishes.
A gas vent extending through an exterior wall shall not terminate adjacent to a wall or below building extensions such as eaves, parapets, balconies, or decks. Failure to comply could result in severe personal injury, death, or substantial property damage.
Figure 4-1 Sidewall Termination of Air and Vent

PVC/CPVC or ABS is acceptable air inlet pipe material. NOTICE
WARNING Do not connect any other appliance to the
vent pipe or multiple boilers to a common vent pipe except as noted in Section 2 on page 18. Failure to comply could result in severe personal injury, death, or substantial property damage.
CAUTION Sidewall venting commercial products will result in large exhaust plumes in cold climates. Consideration should be taken when locating in proximity to windows, doors, walkways, etc.
Installation must comply with local requirements and with the National Fuel Gas Code, NFPA 54 / ANSI Z223.1 for U.S. installations or CSA B149.1 for Canadian installations.
Locate the vent/air terminations using the following guidelines:
2. You must consider the surroundings when terminating the vent and air: a. Position the vent termination where vapors will not damage nearby shrubs, plants or air conditioning equipment or be objectionable. b. The flue products will form a noticeable plume as they condense in cold air. Avoid areas where the plume could obstruct window views. c. Prevailing winds could cause freezing of condensate and water/ice buildup where flue products impinge on building surfaces or plants. d. Avoid possibility of accidental contact of flue products with people or pets. e. Do not locate the terminations where wind eddies could affect performance or cause recirculation, such as inside building corners, near adjacent buildings or surfaces, window wells, stairwells, alcoves, courtyards, or other recessed areas.
Determine location

Figure 4-2 Clearance to Doors and Windows

Vent pipe penetration: a. Cut a hole for the vent pipe. For either combustible or noncombustible construction, size the vent pipe hole per the vent manufacturer’s instructions.
Figure 4-3 Clearance to Forced Air Inlets

All vent pipes and air inlets must terminate at the same height to avoid possibility of severe personal injury, death, or substantial property damage.
CAUTION Sidewall venting commercial products will result in large exhaust plumes in cold climates. Consideration should be taken when locating in proximity to windows, doors, walkways, etc.
Prepare wall penetrations · Termination and fittings · Multiple vent/air terminations

Figure 4-6 Room Air (Direct Exhaust Terminations)

Figure 4-4 Multiple Vent Terminations (must also comply with Figure 4-1)

The Crest boiler may be installed with a single pipe carrying the flue products to the outside while using combustion air from the equipment room.
Follow the requirements in the General Venting, Sidewall Direct Venting, and Vertical Direct Venting sections for vent material specifications, vent length requirements, and vent termination requirements.
Install the air inlet cover (shipped loose with the boiler) per FIG. 4-7. Combustion and ventilation air must be supplied to the equipment room per the requirements on pages 12 and 13 of this manual for proper operation of the Crest boiler when utilizing the single pipe method.
Figure 4-5 Direct Vent Terminations


System water piping methods
The Crest is designed to function in a closed loop pressurized system not less than 12 psi (83 kPa). A temperature and pressure gauge is included to monitor system pressure and outlet temperature and should be located on the boiler outlet.
Basic steps are listed below along with illustrations on the following pages, which will guide you through the installation of the Crest (5-2 thru 5-5).
It is important to note that the boiler has a pressure drop which must be figured in when sizing the circulators. Each boiler installation must have an air elimination device, which will remove air from the system.
Install the boiler so the gas ignition system components are protected from water (dripping, spraying, etc.) during appliance operation or basic service of circulator replacement, valves, and others.
Observe a minimum of 1/4 inch (6 mm) clearance around all uninsulated hot water pipes when openings around the pipes are not protected by non-combustible materials.
Low water cutoff device
An electronic low water cutoff is provided as standard equipment on all models. The low water cutoff should be inspected every 6 months.
If the boiler supplies hot water to heating coils in air handler units, flow control valves or other devices must be installed to prevent gravity circulation of heater water in the coils during the cooling cycle. A chilled water medium must be piped in parallel with the heater.
9. This appliance is supplied with a relief valve sized in accordance with ASME Boiler and Pressure Vessel Code, Section IV (“Heating Boilers”). The safety relief valve is installed at the factory and is located on the rear of the boiler. Pipe the discharge of the safety relief valve to prevent injury in the event of pressure relief. Pipe the discharge to a drain. Provide piping that is the same size as the safety relief valve outlet. Never block the outlet of the safety relief valve.
Freeze protection for new or existing systems must use glycol that is specially formulated for this purpose. This includes inhibitors, which prevent the glycol from attacking the metallic system components. Make certain to check that the system fluid is correct for the glycol concentration and inhibitor level. The system should be tested at least once a year and as recommended by the producer of the glycol solution. Allowance should be made for the expansion of the glycol solution in the system piping.
Use only inhibited propylene glycol solutions, which are specifically formulated for hydronic systems. Ethylene glycol is toxic and can attack gaskets and seals used in hydronic systems.
See the piping illustrations included in this section, FIG.’s 5-2 thru 5-5 for suggested guidelines in piping the Crest.
Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes.
General piping information · Chilled water system · Freeze protection

The Crest heat exchanger does have a pressure drop, which must be considered in your system design. Refer to the graph in FIG. 5-1 for pressure drop through the Crest heat exchanger.
Figure 5-1 Pressure Drop vs. Flow

Table 5A Sizing Information for Temperature Rise Applications_20°F, 40°F and 60°F

FB 1500 4" 138 3.4 69 1.5 46 1.0
FB 2000 4" 184 4.1 92 1.6 61 1.0
FB 2500 4" 230 4.6 115 1.3 77 0.7
FB 3000 4" 277 5.6 138 1.2 92 0.7
FB 3500 4" 323 7.5 161 1.2 108 0.7
It is required that boiler piping systems utilize Primary/Secondary or Fixed or Variable Flow Primary configurations as shown in FIG.’s 5-2 thru 5-5. The use of other boiler piping configurations could result in improper building and system flow rates leading to inadvertent boiler high limit shutdowns and poor system performance.
Circulator sizing

Near boiler piping components
CAUTION The maximum allowable water flow rate through a single Crest boiler is 350 GPM. Exceeding this flow rate will result in damage to the heat exchanger and/or piping.
Table 5B1 Minimum Flow Rate with the Boiler at Full Fire
MODEL FLOW RATE (GPM)
FB(N,L)1500 35
FB(N,L)2500 58
FB(N,L)3000 70
[Based on 80°F Temperature Rise]
Table 5B2 Absolute Minimum Flow Rate
MODEL FLOW RATE (GPM)
FB(N,L)2000 25
FB(N,L)2500 25
FB(N,L)3000 25
FB(N,L)3500 45

Figure 5-2 Single Boiler - Recommended - Primary / Secondary Piping with a Hot Water Generator

System flow should always remain higher than the required flow for the boiler(s) when the boiler(s) is in operation to prevent short cycling and high limit issues. NOTICE
Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes. NOTICE

Table 5C Multiple Boilers - Common Header - Primary / Secondary Flow

Number of Units 2 3 4 5 6 7 8 Recommended Common Header Pipe Sizes in Inches FB 1500 4 4 5 5 6 6 7 FB 2000 4 5 5 6 7 7 8 FB 2500 5 5 6 7 7 8 10 FB 3000 5 6 7 7 8 10 10 FB 3500 5 6 7 8 10 10 10
Figure 5-3 Multiple Boilers - Common Header - Recommended - Primary / Secondary Flow

System flow should always remain higher than the required flow for the boiler(s) when the boiler(s) is in operation to prevent short cycling and high limit issues. NOTICE
Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes. NOTICE

Figure 5-4 Single Boiler - Alternate - Fixed or Variable Flow Primary System Piping

Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes. NOTICE

Figure 5-5 Multiple Boilers - Alternate - Common Header - Fixed or Variable Flow Primary

Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes. NOTICE
When installing multiple Crest boilers in fixed or variable flow primary applications, utilize a reverse-return or other piping method to ensure balanced flow through each boiler. NOTICE

For dual fuel models, reference the Crest Dual Fuel Supplemental Manual. NOTICE
b. The appliance must be isolated from the gas supply piping system by closing a manual shutoff valve during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 PSIG (3.5 kPa).
Figure 6-1 Gas Supply Piping

c. The appliance and its gas connection must be leak tested before placing it in operation.
Do not check for gas leaks with an open flame – use the bubble test. Failure to use the bubble test or check for gas leaks can cause severe personal injury, death, or substantial property damage.
MANUAL SHUTOFF
VALVE (FACTORY SUPPLIED)
Failure to apply pipe sealing compound as detailed in this manual can result in severe personal injury, death, or substantial property damage.
SEDIMENT TRAP / DRIP LEG CLEAN OUT (FACTORY SUPPLIED)
Table 6A Gas Inlet Size
Model Gas Inlet Size
The gas valve and blower will not support the weight of the piping. Do not attempt to support the weight of the piping with the boiler or its accessories. Failure to comply could result in severe personal injury, death, or substantial property damage.
FB3000 2"
FB3500 2"

Use two wrenches when tightening gas piping at boiler (FIG. 6-2), using one wrench to prevent the boiler gas line connection from turning. Failure to support the boiler gas connection pipe to prevent it from turning could damage gas line components.
Natural gas supply pressure requirements
Figure 6-2 Inlet Pipe with Backup Wrench

WARNING Ensure that the high gas pressure regulator is at least 10 feet (3 m) upstream of the appliance.
Check boiler rating plate to determine which fuel the boiler is set for. Crest boilers CAN NOT be field converted. Failure to comply could result in severe personal injury, death, or substantial property damage.
Pipe sizing for propane gas
Propane Supply Pressure Requirements
USE BACK UP WRENCH TO PREVENT PIPE FROM ROTATING
Maximum inlet gas pressure must not exceed the value specified. Minimum value listed is for the purposes of input adjustment.
WARNING Check boiler rating plate to determine
WARNING Ensure that the high gas pressure regulator is at least 10 feet (3 m) upstream of the appliance (FIG. 6-3).
which fuel the boiler is set for. Crest boilers CANNOT be field converted. Failure to comply could result in severe personal injury, death, or substantial property damage.
Figure 6-3 Gas Supply Piping to Regulator

Pipe sizing for natural gas
* REQUIRED FOR INSTALLATION IN THE COMMONWEALTH OF MASSACHUSETTS

Table 6B Natural Gas Pipe Size Chart

of Btu/hr for gas pressures of 14 Inches Water Column (0.5 PSIG) or less and
10 20 30 40 50 60 70 80 90 100 125 150 175 200
1½ 2,150 1,500 N/A
2 4,100 2,820 2,260 1,950 1,720 1,560 N/A
2½ 6,460 4,460 3,610 3,100 2,720 2,460 2,310 2,100 2,000 1,900 1,700 1,540 N/A N/A
on NAT GAS, 1025 Btu/hr per Cubic Foot of
3 11,200 7,900 6,400 5,400 4,870 4,410 4,000 3,800 3,540 3,300 3,000 2,720 2,500 2,340
4 23,500 16,100 13,100 11,100 10,000 9,000 8,300 7,690 7,380 6,870 6,150 5,640 5,130 4,720
DO NOT adjust or attempt to measure gas valve outlet pressure. Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death, or substantial property damage.
The gas piping must be sized for the proper flow and length of pipe, to avoid excessive pressure drop. Both the gas meter and the gas regulator must be properly sized for the total gas load.
If you experience a pressure drop greater than 1 inch w.c. (249 Pa), the meter, regulator, or gas line is undersized or in need of service. Perform the steps below when checking inlet gas supply:

WARNING Do not check for gas leaks with an open
flame -- use the bubble test. Failure to use the bubble test or check for gas leaks can cause severe personal injury, death, or substantial property damage.
The gas pressure must remain between 4 inches w.c. (.99 kPa) minimum and 14 inches w.c. (3.5 kPa) maximum for Natural gas and between 4 inches w.c. (.99 kPa) minimum and 14 inches w.c. (3.5 kPa) maximum for LP gas during standby (static) mode and while in operating (dynamic) mode. If an in-line regulator is used, it must be a minimum of 10 feet (3 m) from the Crest boiler. It is very important that the gas line is properly purged by the gas supplier or utility company. Failure to properly purge the lines or improper line sizing, will result in ignition failure.
Ignition problems are especially noticeable in NEW LP installations and also in empty tank situations. This can also occur when a utility company shuts off service to an area to provide maintenance to their lines.
Figure 6-4 Inlet Gas Supply Check

The gas valve MUST NOT be replaced with a conventional gas valve under any circumstances. As an additional safety feature, the gas valves have flanged connections to the venturis and blowers.
Failure to follow all precautions could result in fire, explosion, or death!
DO NOT adjust or attempt to measure gas valve outlet pressure. Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death, or substantial property damage.
Gas Pressure · Gas valve replacement

ELECTRICAL SHOCK HAZARD – For your safety, turn off electrical power supply before making any electrical connections to avoid possible electric shock hazard. Failure to do so can cause severe personal injury or death.
Wiring must be N.E.C. Class 1.
Line voltage connections
If original wiring as supplied with boiler must be replaced, use only type 105°C wire or equivalent.
Boiler must be electrically grounded as required by National Electrical Code ANSI/NFPA 70 – latest edition.
Label all wires prior to disconnection when servicing controls. Wiring errors can cause improper and dangerous operation.
Figure 7-1 Boiler Line Voltage Field Wiring Connections


ModBus
The RS-485 ModBus cable is connected to the ModBus terminals. Use shielded, 2-wire twisted pair cable. If desired, the shield can be connected to ground by installing a jumper wire between terminals 1 and 3 on connector X5 on the ModBus interface module. Hot Water Generator (HWG) thermostat
Figure 7-2 Routing Field Wiring

If louvers need to operate before the boiler fires, they can be controlled by this output. Connect these terminals to a 24V relay coil, which is wired to operate the louvers (FIG. 7-3).
Louvers are used to provide combustion air for the room air option. A louver proving switch should be connected to the appropriate terminals and are verified prior to operation (see FIG. 7-3).
This 0 - 10V output is available to control the speed of a variable speed boiler pump. The SMART TOUCH control will vary the speed of this pump in order to maintain a minimum T (set by the installer, see the Crest Service Manual) across the heat exchanger, as well as prevent high limit lockouts when the flow in the primary loop is extremely low. Connect this output to the 0 - 10V input on the boiler pump speed control.
If a variable speed pump is used in the primary loop, and a 0-10V signal is available from the pump speed control, this signal can be used by the SMART TOUCH control to anticipate changes in the building heat load. By connecting this 0 - 10V signal to the 0 - 10V SYS PUMP IN terminals, the boiler (or cascade) can modulate up and down as the primary flow increases and decreases.
This output provides a 0 - 10V signal that is proportional to the firing rate of the boiler. This may be used by a BMS system to monitor the actual rate of the boiler.

Wiring of the cascade
Additional field supplied limit controls may be connected to the auxiliary switch inputs. If additional limit controls fail or open, it will result in a manual reset lockout. System supply sensor
When wiring the boilers for Cascade operation, select one boiler as the Leader boiler. The remaining boilers will be designated as Members. See page 45 “Configuration of the Cascade” for a detailed explanation of this procedure.
Connect the system supply sensor, system return sensor and outdoor air sensor (if used) to the Leader boiler.
The location of the system supply sensor should be downstream of the boiler connections in the main system loop (FIG.’s 5-5 and 5-6). The system supply sensor should be wired to the Low Voltage Connection Board at the terminals marked for the system supply sensor (see FIG. 7-3). The Leader control will use the water temperature at the system supply sensor to control the operation of the Cascade.
If outdoor air reset is desired, the outdoor air sensor should be wired to the Low Voltage Connection Board at the terminals marked for the outdoor air sensor on the Leader boiler (FIG. 7-3). If the outdoor air sensor is connected, the Leader control will calculate the water temperature set point based on the programmed reset curve parameters. If the outdoor air sensor is not connected, the Leader control will maintain the fixed water temperature set point that is programmed into the control.
If a Thermostat enable output is available, it should be wired to the Low Voltage Connection Board on the Leader boiler at the terminals marked Enable (FIG. 7-3). If the boilers are to run continuously, connect a jumper wire between the 7 and 8 terminals at the Enable input. This will initiate a call for heat on the Cascade. If the SMART TOUCH control is being controlled by a Boiler Management System (BMS), a call for heat may be initiated by the voltage applied to the BMS 0 - 10 VDC input instead.
The SMART TOUCH control closes a set of dry contacts whenever the burner is running. This is typically used by Building Management Systems to verify that the boiler is responding to a call for heat.
Communication between the Leader boiler and the Member boilers is accomplished by using shielded, 2-wire twisted pair communication cable. Connect one of the twisted pair wires to Cascade terminal A on each of the Low Voltage Connection boards, and the other wire of the twisted pair to Cascade terminal B on each of the Low Voltage Connection Boards. Connect the shield wires to one of the Cascade shield ground terminals on the Low Voltage Connection Boards (FIG. 7-3). If more than two boilers are on the Cascade, daisy chain the wiring from the Cascade terminals on the second boiler to the Cascade terminals on the third boiler, then from the third to the forth, and so on. The connections between boilers can be made in any order, regardless of the addresses of the boilers. Try to keep each cable as short as possible.
The SMART TOUCH control closes another set of contacts whenever the boiler is locked out or the power is turned off. This can be used to turn on an alarm, or signal a Building Management System that the boiler is down.

Figure 7-3 Low Voltage Field Wiring Connections

40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1. The Crest is a high efficiency appliance that produces condensate. 2. The rear of the boiler has a 1 inch (25.4 mm) stainless steel drain fitting and a 3/8 inch (9.8 mm) stainless steel vent line for connection to the condensate trap. 3. Connect the 1 inch (25.4 mm) fitting to the 1 inch (25.4 mm) fitting on the condensate trap with the factory supplied silicone hose. Secure the hose to the condensate trap and the boiler using the factory supplied hose clamps. 4. Connect the 3/8 inch (9.8 mm) fitting to the 3/8 inch (9.8 mm) fitting on the condensate trap (shipped loose) with the factory supplied silicone hose. Secure the hose to the condensate trap and the boiler using the factory supplied hose clamps. 5. The condensate trap must be installed at the same level or below the boiler base. 6. The condensate trap is sized for a 1" PVC outlet connection pipe. 7. Plug the wiring connection from the condensate trap into the connector located on the back of the unit. 8. Slope condensate tubing down and away from the boiler into a drain or condensate neutralizing filter. Condensate from the Crest will be slightly acidic (typically with a pH from 3 to 5). Install a neutralizing filter if required by local codes. A neutralizer kit (FIG. 8-1) is available from the factory (KIT30097). The neutralizer kit must be placed on a surface that is a minimum of 3 inches lower than the condensate trap with field supplied piping (vacuum break) installed between the condensate trap and the neutralizer kit.
Use materials approved by the authority having jurisdiction. In the absence of other authority, PVC and CPVC pipe must comply with ASTM D1785 or D2845. Cement and primer must comply with ASME D2564 or F493. For Canada use CSA or ULC certified PVC or CPVC pipe, fittings, and cement.
The condensate line must remain unobstructed, allowing free flow of condensate. If condensate is allowed to freeze in the line or if the line is obstructed in any other manner, condensate can exit from the boiler tee, resulting in potential water damage to property.
Figure 8-1 Condensate Disposal


Fill and test water system
Do not use petroleum-based cleaning or sealing compounds in the boiler system. Damage to elastomer seals and gaskets in the system could occur, resulting in substantial property damage.
Hardness less than 7 grains
Chlorine concentration less than 200 ppm
b. Pressure will rise when boiler is turned on and system water temperature increases.
Eliminate all system leaks. Continual fresh makeup water will reduce boiler life. Minerals can build up in the heat exchanger, reducing heat transfer, overheating the heat exchanger, and causing heat exchanger failure.
Test/replace freeze protection fluid
Purge air from water system
Freeze protection (when used)
a. Starting on the lowest floor, open air vents one at a time until water squirts out.
b. Repeat with remaining vents.
Check/control water chemistry

Check for gas leaks
Propane boilers only – Your propane supplier mixes an odorant with the propane to make its presence detectable. In some instances, the odorant can fade, and the gas may no longer have an odor. Before startup (and periodically thereafter), have the propane supplier verify the correct odorant level in the gas.
Before starting the boiler, and during initial operation, smell near the floor and around the boiler for gas odorant or any unusual odor. Remove the top access panel and smell the interior of the boiler enclosure. Do not proceed with startup if there is any indication of a gas leak. Use an approved leak detection solution. Repair any leaks at once.
DO NOT adjust or attempt to measure gas valve outlet pressure. The gas valve is factory set for the correct outlet pressure. This setting is suitable for natural gas and propane, requiring no field adjustment. Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death, or substantial property damage.
Figure 9-1 Condensate Trap

FROM CONDENSATE DRAIN ON BOILER TO FLOOR DRAIN OR NEUTRALIZER KIT 1” PVC / CPVC CONNECTION
Inspect/check condensate lines and fittings
Check thermostat circuit(s) · Inspect condensate system

Final checks before starting the boiler
Check vent piping and air piping
Read the Crest Service Manual to familiarize yourself
with SMART TOUCH control module operation. Read this manual, page 43 for proper steps to start boiler.
Venting system must be sealed gastight to prevent flue gas spillage and carbon monoxide emissions, which will result in severe personal injury or death.
Verify the boiler and system are full of water and all
system components are correctly set for operation.
Verify the preparation procedures of Section 9, pages 40
and 41 have been completed.
Verify electrical connections are correct and securely
attached.
Inspect vent piping and air piping for signs of deterioration
If you discover evidence of any gas leak, shut down the boiler at once. Find the leak source with a bubble test and repair immediately. Do not start the boiler again until corrected. Failure to comply could result in severe personal injury, death, or substantial property damage.
from corrosion, physical damage or sagging. Verify air piping and vent piping are intact and correctly installed per this manual.
Check flame and combustion
If boiler does not start correctly
For dual fuel models, reference the Crest Dual Fuel Supplemental Manual. NOTICE
If none of the above corrects the problem, refer to the Troubleshooting Section of the Crest Service Manual.
Check system and boiler
Check gas piping · Start the boiler · Check water piping

A. This appliance does not have a pilot. It is
equipped with an ignition device which automatically lights the burner. Do not try to light the burner by hand. B. BEFORE OPERATING smell all around
the appliance area for gas. Be sure to smell next to the floor because some gas is heavier than air and will settle on the floor.
Never use tools. If the handle will not turn by hand, don’t try to repair it, call a qualified service technician. Force or attempted repair may result in a fire or explosion.
D. Do not use this appliance if any part has been
under water. Immediately call a qualified service technician to inspect the appliance and to replace any part of the control system and any gas control which has been under water.


Check flame and combustion (continued)
Set space heating operation
Verify space heat circulator mode
The system pump output can be programmed to never run (OFF), run only when a space heating demand is present (ON), or run continuously except during warm weather shutdown (WWSD). If the boiler is not heating an indirect HW (Hot Water) tank, it also turns on the boiler pump. After the space heating call for heat ends, and the system pump is programmed as ON, the system pump continues to run for a short period of time. If the boiler pump was running, it continues to run for a short period of time as well. These pump delays are factory set to 30 seconds. If different delays are desired, the appropriate parameters in the control must be changed. See the Crest Service Manual for a detailed explanation of this procedure.
Set space heating set point temperature
Table 9A Flue Products Chart
During normal operation, space heating set point temperatures can be adjusted from the Set Points Menu. Press the following buttons to navigate to the Set Points Menu from the Home Screen:
After pressing SETUP, the Password Screen will appear. Entering the correct password will allow access to all Installer Level adjustable parameters. Press ENTER without a password to access the User Level parameters.
You must replace the flue gas temperature sensor to prevent flue gas spillage into the room. Failure to comply could result in severe personal injury, death, or substantial property damage.

Set Hot Water Generator (HWG) operation
Verify HWG circulator mode
The HWG Mode is programmed to heat an indirect hot water tank. When a tank thermostat or a tank sensor initiates a call for heat, the SMART TOUCH control will turn on the HW pump and turn off the boiler pump (if running). If the system pump is running, it will remain on. When the HW call for heat ends, and there is no space heating call for heat, the HW pump will continue to run for a period of time. This pump delay is set at the factory to 60 seconds. If a shorter or longer delay is desired, the appropriate parameter in the control must be changed. See the Crest Service Manual for a detailed explanation of this procedure. If there is an active space heating call for heat, then the boiler pump will be turned on and the HW pump will be turned off.
Configuration of the cascade
When installed in a Cascade system, the individual controls must be programmed for cascade operation. To program the cascade parameters, access the Cascade Menu found in the Setup Menu by pressing the following buttons:
Set HWG target temperature
After pressing SETUP, the correct installer password MUST BE entered.
When in the HWG Mode, the control will modulate to maintain the outlet temperature to a set point. This set point is set at the factory to 180°F. If a different set point is desired, the appropriate parameter in the control must be changed. See the Crest Service manual for a detailed explanation of this procedure.
If a tank sensor is installed, the HWG heat demand will start when the tank temperature drops 6°F below the tank set point, and stop when the tank temperature reaches the tank set point. The tank set point is set at the factory to 120°F (49°C).
Press the following buttons to program the clock:
After pressing SETUP, the Password Screen will appear. Entering the correct password will allow access to all Installer Level adjustable parameters. Press ENTER without a password to access the User Level parameters.
The SMART TOUCH control has a built-in clock that it uses for its night setback feature and for logging events. This clock must be set when the boiler is installed, and anytime the boiler has been powered off for more than one day. Use the following procedure to set the clock:

How the boiler operates
The SMART TOUCH control module allows connection of a HW thermostat or sensor to the low voltage connection board. When the HW thermostat or sensor calls for heat, the control module activates the HW pump, shuts down the boiler pump, and immediately sets the target outlet water temperature to 180°F (82.2°C).
The Crest uses an advanced stainless steel heat exchanger and electronic control module that allows fully condensing operation. The blowers pull in air and push flue products out of the boiler through the heat exchanger and flue piping. The control module regulates blower speeds to control the boiler firing rate. The gas valves sense the amount of air flowing into the boiler and allow only the right amount of gas to flow.
This provides automatic priority heat allocation to the HW Generator for maximum response and recovery. The HW pump continues for 60 seconds after the heating cycle to deliver the most possible heat. The control module can be programmed to limit the firing rate of the boiler during a HW call for heat.
How the control modules operate
The Crest boiler is equipped with a SMART TOUCH control module. The SMART TOUCH control module receives inputs from boiler sensors and external devices. The control module activates and controls the blowers and gas valves to regulate heat input and switches the boiler, Hot Water Generator (HWG), and system pumps on and off as needed. The user programs the control module to meet system needs by adjusting control parameters. These parameters set operating temperatures and boiler operating modes.
The control module is programmed to use the outlet sensor as the control sensor by default. If a system supply sensor is connected, the control automatically uses it as the control sensor. The control module may be programmed to use the inlet sensor as the control sensor instead. In this case, the control will use the system return sensor if it is connected.
Control inputs and outputs
After a space heating demand has been satisfied, the control will delay the next space heating call for a set time period (time is adjustable by the installer). The time delay will be bypassed if the inlet water temperature drops too far during the delay.
This input tells the boiler to provide water for space heating.
Hot Water Generator (HWG) tank thermostat
Boiler, system, and HW pump control
When a space heating call for heat starts and no HWG call is on, the boiler pump is turned on. The system pump will turn on also if it is programmed to do so. If a HWG call for heat is on, the boiler pump will wait to turn on until just before the HWG pump turns off. After the space heating call for heat ends, the boiler pump will run for an additional period of time.
This input tells the boiler to provide water for heating an indirect HW tank.
The Crest can be controlled by a Building Management System (BMS) using a 0 - 10 VDC signal. The control can be configured by the installer to use this signal to either control set point or firing rate.
When a HWG call for heat starts, the HWG pump is turned on. If a space heating call for heat is on, the boiler pump will turn off a few seconds after the HWG pump turns on.
When a variable speed system pump is used, and there is a 0 - 10V signal available from the pump speed control, this signal may be connected to the boiler. Doing so will allow the boiler to anticipate changes in the BTU’s needed by the system as the system flow changes, and therefore, help the boiler to maintain the desired system temperature. Connect the - input terminal to the COM or - output terminal on the pump speed control, and the + input terminal to the 0 - 10V or + output terminal on the pump speed control. Note that the voltage on these inputs must never go below ground.
When the boiler needs to control combustion air louvers, connect a 24 VAC louver relay to the two (2) Louver Relay terminals. Connect the Louver End Switch to the Louver Proving Switch input on the Low Voltage Connection Board.
The Crest is capable of modulating its firing rate from a minimum of 4 - 6% (model specific) to a maximum of 100%. The firing rate is dictated by the call for heat (i.e., space heating or hot water generation), the heating load, ramp delay (if enabled), and various other temperature limitations.

If during operation of the boiler the outlet water temperature is rising too quickly, the control will reduce the firing rate to its lowest setting.
For systems with lower flow, the SMART TOUCH can limit the firing rate (when enabled) when a space heating call for heat starts, or when switching from a DHW call for heat to a space heating call for heat. There are six (6) limits that can be programmed, as well as six (6) time intervals corresponding to each limit. The sixth limit will also limit the firing rate for the rest of the call for heat.
If an outdoor air sensor is connected, the control module will calculate the set point based on the programmed reset curve. The installer can change the slope of the reset curve by several adjustable parameters. The user can limit the maximum set point for the system using the space heating set point.
Outlet temperature, flue temperature, and temperature rise limiting
If outdoor air reset is active, the boost temperature is not 0, a space heating demand has been active continuously for a set period of time (time adjustable by installer) and there has been no HWG demands, the control will increase the set point by a fixed number of degrees (adjustable by installer). This process will continue until the space heating demand ends, the set point reaches the programmed set point or a maximum of 20 increases has occurred. Once the system heat demand is satisfied, the set point will revert to the value determined by the reset curve.
The outlet water temperature is monitored by the boiler outlet temperature sensor. When the outlet temperature exceeds 185°F, the unit will reduce the fan speed. If the outlet water temperature exceeds 195°F (90°C) the control will shut the unit down until the minimum off time has expired and the outlet drops 10°F (5.5°C).
The control module monitors the flue temperature by a sensor located in the flue exhaust. If the flue temperature exceeds 350°F (176°C) the control will reduce the maximum fan speed. If the flue temperature exceeds 400°F (204°C) the control will shut the unit down. The unit will restart automatically once the flue temperature drops 50°F (27°C) and the minimum off time has expired.
The controller may be programmed to reduce the space heating set point and/or Hot Water Generator set point for each demand during a certain time each day. A start and stop time for each demand can be programmed for each day of the week. The controller can be programmed to reduce the tank set point as well. A different set of start and stop times can be programmed each day of the week.
The control monitors the temperature difference between the inlet and the outlet sensor. If this difference exceeds 80°F (27°C) the control will reduce the fan speed. If the temperature difference exceeds 90°F (32°C) the control will shut the unit down. The unit will restart automatically once the temperature difference has dropped below 50°F (28°C) and the minimum off time has expired.
To prevent nuisance shutdowns when the boiler is firing at minimum rates, the control will increase the firing rate when the flame signal drops too low.
DO NOT install the boiler in a room likely to freeze.
The following integral feature of the SMART TOUCH control module provides some protection for the boiler only -- not for the system.
The Crest boiler can be connected to and controlled by a Building Automation System through the ModBus interface. Connect the A and B wires to the A and B terminals. If connecting another cable (in a daisy chain), connect the shield wire of the first cable to one of the shield terminals, and the shield wire of the second cable to the other shield terminal. If it is desired to ground the cable shield at the heater, connect the shield wire to one of the shield terminals, and install a jumper across the two (2) terminals in connector X5 on the ModBus interface board.
This feature of the SMART TOUCH control module does not eliminate the possibility of freezing. The installation must still use recognized design, installation and maintenance practice to prevent freeze potential for the boiler and system.
A 0-10V signal which indicates the firing rate of the heater is available. This output may be connected to a Building Management System (BMS) to allow it to monitor the actual firing rate. Connect the - terminal to the COM or - terminal on the BMS, and connect the + terminal to the 0 - 10V or + terminal on the BMS.

Connections are provided on the connection board for external limits such as an additional high limit. The SMART TOUCH control will shut off the burner and inhibit relighting whenever any of these external limits open.
The Crest SMART TOUCH control has two (2) integral limits, one auto reset and one manual reset. The Crest also has one auxiliary manual reset high limit. The integral and auxiliary high limits are UL353 certified.
When the outlet temperature exceeds 195°F (90.6°C) (Installer Adjustable Parameter), integral auto reset high limit action occurs. The boiler will shut down until the outlet water cools down and the timer expires.
Run-time and alarm outputs
The boiler provides dry contacts for indicating when the boiler is running, and when it is unable to operate.
If the outlet temperature exceeds 200°F (93.3°C) (User Adjustable Dial), auxiliary manual reset high limit action occurs. The boiler will shut down until the outlet water cools down and the boiler is reset through the user interface.
Run-time and cycle counting
The control uses four timers to monitor the total hours of burner operation: 75 - 100% 50 - 75% 25 - 50%
If the outlet temperature exceeds 205°F (93.3°C) (Installer Adjustable Parameter), integral manual reset high limit action occurs. The boiler will shut down until the outlet water cools down and the boiler is reset through the user interface.
The control uses four (4) ignition counters to monitor the amount of boiler cycles. The first counter counts all ignitions of the control. The second counter counts only ignition attempts that have failed. The third and fourth counters are the same as the first and second respectively, but can be reset by the installer.
Low water cutoff protection
A low water cutoff device with test and reset functionality is provided in the boiler as standard equipment.
The control can be programmed for service reminder notification. This notification will become active when either a set amount of time has expired, or a set amount of running hours or cycles has expired (all adjustable by the installer). The service reminder notification can be reset by the installer. The service company’s name and phone number can be programmed to display when service is due.
The SMART TOUCH control module uses temperature sensing of both supply and return temperatures of the heat exchanger. If the flow rate is too low or the outlet temperatures too high, the control module modulates down and will shut the boiler off. This ensures boiler shutdown in the event of low flow conditions.
The control will hold in memory the last 10 blocking faults as well as the last 10 lockout faults. The date and time of the occurrence will be recorded as well. Only the 10 most recent occurrences will be held in memory.
Outdoor reset operation, if used
Target temperature with outdoor reset
This feature improves the system’s efficiency as the outdoor temperature warms up.
The SMART TOUCH control module senses water temperature and regulates boiler firing and firing rate to achieve a target temperature. The target temperature can be set between 32°F (0°C) and 185°F (85°C).
See the Crest Service Manual to change the settings.
The reset curve looks at outdoor air temperature and adjusts the set point.

Sequence of the cascade
When multiple boilers are installed, they can be wired together in a cascade sequence. A maximum of eight boilers can be controlled from a single control. In this application one boiler would be designated as the Leader control and all others would be designated as Member controls.
To equalize the run time of all boilers on the Cascade, the firing sequence will automatically be changed at set intervals.
For the first 24 hours after initializing the Cascade, the sequence will be changed every hour. After that the sequence will be changed once every 24 hours.
Once the Leader boiler receives a call for heat from the Enable input, the 0 - 10 VDC input, or ModBus, the control will determine what the set point will be. If outdoor air reset is desired, connect the outdoor air sensor to the terminals on the Low Voltage Connection Board on the Leader boiler. The set point will be calculated based on the programmed reset curve parameters. See the Crest Service Manual to program the reset curve. If outdoor air reset is not desired, do not connect the outdoor air sensor. A fixed temperature set point can be programmed into the control, or provided through the ModBus interface.
HW operation with cascade
For HW operation any boiler(s) in the Cascade can be selected to provide heat for a HW call. Select a boiler to be designated as the HW boiler. Connect the HW thermostat or sensor to the terminals on the Low Voltage Connection Board marked for the HW Thermostat or sensor. When the boiler receives a HW call, the Leader control will take that boiler out of the Cascade sequence. If another boiler is available, the Leader will start it up to take its place.
If the water temperature at the controlling sensor is less than the set point + the turn-off offset - the off-on differential, the control will initiate a call for heat on the Cascade (see the Crest Service Manual for an explanation of the offset and differential). The Leader will energize the lead boiler on the Cascade. For a new startup this will be the Leader boiler.
The HW boiler will adjust its set point to the programmed HW set point and will adjust its firing rate to maintain this. Once the HW call has been satisfied, the Leader control will place that boiler back into the Cascade sequence.
Night Setback and Ramp Delay operations with cascade
The two (2) types of Cascade control are listed below:
Night Setback and Ramp Delay operation of the boilers within the Cascade are available. Programming will be done through the Leader boiler. Refer to the Crest Service Manual for information regarding Night Setback and Ramp Delay.
Efficiency optimization is chosen when the application is such that overall heating efficiency is most important. The Cascade will fire the boilers in a way that is the most efficient. This allows more boilers to fire at one time, at a lower rate, thus more efficient. This Cascade is also required when cascading boilers in a common vent application.
The Lead/Lag method is chosen when the application requires firing as few boilers at a time as possible. This method will not bring on another boiler until the current number of boilers cannot meet the demand. This Cascade is NOT allowed in a common vent application.
The parameters for both types of Cascade are adjustable. Reference the Crest Service Manual for a more detailed description of these adjustments.
Cascade · Efficiency optimization · Lead/Lag

If the first combustion system in the boiler is unable to maintain the desired set point temperature, the second combustion system in the boiler will be started. Both blowers will modulate to a set speed, and the second gas valve will be energized. The second combustion system will light from the first combustion system. The second flame will be monitored much like the first. Once both combustion systems are firing, the control will work in synchronization to maintain the desired set point temperature. If the heat load should decrease sufficiently, the second combustion system will be shut down.

The Home Screen displays status, modulation rate, outlet water temperature, inlet water temperature, flue temperature, system supply temperature, system return temperature, outdoor air temperature, and domestic hot water tank temperature.
The boiler can be started and stopped by pressing the ON/OFF button. The Boiler Status Screen and Main Menu Screen can be accessed by pressing the appropriate button.
Figure 10-1 Home Screen

When the ON/OFF switch is turned to the ON position, the first screen visible on the LCD display will be the Home Screen. This screen displays the current status of the Crest boiler. The following items can be viewed or interacted with on the Home Screen:
DHW Temperature - This is the temperature as measured by the tank sensor in the hot water storage tank (if connected).
Flue Temperature - Temperature measured by the flue sensor.
Time - The time is displayed in the lower left-hand corner of the display. Reference the Crest Service Manual for Night Setback parameters and more information regarding adjusting the date and time.
On/Off button - Pressing this button allows the boiler to be placed in either Manual Shutdown Mode or Standby Mode.
Status - This line shows the current operating status of the Crest boiler and the current set point.
Boiler Status button - Pressing this button brings up the Boiler Status Screen. This screen shows the status of the various safeties, inputs, and outputs to the control module. Reference the Boiler Status Screen section in the Crest Service Manual for more information regarding this screen.
Outlet Water Temperature - This is the boiler outlet temperature.
Inlet Water Temperature - This is the boiler inlet temperature.
Main Menu button - Pressing this button brings up the Main Menu Screen. From this screen navigation to nine (9) other screens is possible. Reference the Main Menu Screen section on page 52 of this manual for more information regarding this screen.
System Supply Temperature - This is the water temperature as measured by the system supply sensor located in the downstream piping (if connected).
System Return Temperature - This is the water temperature measured by the system return sensor located in the upstream piping (if connected).
Modulation button - Pressing this button brings up the Modulation Screen. This screen shows overall boiler modulation, individual fan speeds, and flame currents.
Outside Air Temperature - This is the outdoor air temperature (if connected).
Modulation Percentage - Displays the current boiler firing rate.

Use the Main Menu Screen (FIG. 10-2) to access the screens necessary to set temperatures, operating conditions, and monitor boiler operation.
The Crest is equipped with a SMART TOUCH control system. All menu options are accessed by touching the screen with your finger or a stylus from a PDA.
Figure 10-2 Main Menu Screen

The Main Menu Screen allows navigation to nine (9) additional screens which are used to set temperatures, operating conditions, and monitor boiler operation. These screens are as follows:
Reference the Crest Service Manual for more information regarding the nine (9) accessible screens.

Maintenance and annual startup
Table 11A Service and Maintenance Schedules
Owner maintenance (see the Crest User’s Information Manual for
months
instructions)

Follow the service and maintenance procedures given throughout this manual and in component literature shipped with the boiler. Failure to perform the service and maintenance could result in damage to the boiler or system. Failure to follow the directions in this manual and component literature could result in severe personal injury, death, or substantial property damage.
The boiler should be inspected annually only by a qualified service technician. In addition, the maintenance and care of the boiler designated in Table 11A and explained on the following pages must be performed to assure maximum boiler efficiency and reliability. Failure to service and maintain the boiler and system could result in equipment failure.
Electrical shock hazard – Turn off power to the boiler before any service operation on the boiler except as noted otherwise in this instruction manual. Failure to turn off electrical power could result in electrical shock, causing severe personal injury or death.
Figure 11-1 Condensate Trap

FROM CONDENSATE DRAIN ON BOILER TO FLOOR DRAIN OR NEUTRALIZER KIT 1” PVC / CPVC CONNECTION
Eliminate all system or boiler leaks. Continual fresh makeup water will reduce boiler life. Minerals can build up, reducing heat transfer, overheating heat exchanger, and causing heat exchanger failure. Leaking water may also cause severe property damage.
Flush condensate trap with water

Safety relief valves should be re-inspected AT LEAST ONCE EVERY THREE YEARS, by a licensed plumbing contractor or authorized inspection agency, to ensure that the product has not been affected by corrosive water conditions and to ensure that the valve and discharge line have not been altered or tampered with illegally. Certain naturally occurring conditions may corrode the valve or its components over time, rendering the valve inoperative. Such conditions are not detectable unless the valve and its components are physically removed and inspected. This inspection must only be conducted by a plumbing contractor or authorized inspection agency – not by the owner. Failure to re-inspect the boiler relief valve as directed could result in unsafe pressure buildup, which can result in severe personal injury, death, or substantial property damage.
Failure to inspect for the above conditions and have them repaired can result in severe personal injury or death.
Following installation, the valve lever must be operated AT LEAST ONCE A YEAR to ensure that waterways are clear. Certain naturally occurring mineral deposits may adhere to the valve, rendering it inoperative. When manually operating the lever, water will discharge and precautions must be taken to avoid contact with hot water and to avoid water damage. Before operating lever, check to see that a discharge line is connected to this valve directing the flow of hot water from the valve to a proper place of disposal. Otherwise severe personal injury may result. If no water flows, valve is inoperative. Shut down the boiler until a new relief valve has been installed.

Figure 11-2 Burner Assembly

Check burner flame

Review with owner 1. Review the Crest User’s Information Manual with the owner. 2. Emphasize the need to perform the maintenance schedule specified in the Crest User’s Information Manual (and in this manual as well). 3. Remind the owner of the need to call a licensed contractor should the boiler or system exhibit any unusual behavior. 4. Remind the owner to follow the proper shutdown procedure and to schedule an annual start-up at the beginning of the next heating season.
The combustion chamber insulation in this appliance contains ceramic fiber material. Ceramic fibers can be converted to cristobalite in very high temperature applications. The International Agency for Research on Cancer (IARC) has concluded, “Crystalline silica in the form of quartz or cristobalite from occupational sources is carcinogenic to humans (Group 1).” Normal operating temperatures in this appliance are below the level to convert ceramic fibers to cristobalite. Abnormal operating conditions would have to be created to convert the ceramic fibers in this appliance to cristobalite.
The ceramic fiber material used in this appliance is an irritant; when handling or replacing the ceramic materials it is advisable that the installer follow these safety guidelines. Avoid breathing dust and contact with skin
The boiler contains ceramic fiber materials. Use care when handling these materials per instructions on this page. Failure to comply could result in severe personal injury.
6. Use a vacuum cleaner to remove any accumulation on the tube sheet surfaces. Do not use any solvent. 7. Brush the heat exchanger (tube sheet, combustion chamber walls, and tube entry) while dry using a nylon bristle brush. Caution: DO NOT use a metal brush. Re-vacuum the heat exchanger. 8. Finish cleaning using a clean cloth dampened with warm water. 9. Temporarily remove the condensate drain line from the condensate trap and route directly to a drain. 10. Rinse out debris with a low pressure water supply. The water will drain through the condensate connection. 11. Allow the heat exchanger to thoroughly dry. 12. Reconnect the condensate drain line to the condensate trap. 13. Close isolation valves on piping to isolate boiler from system. Attach a hose to the boiler drain and flush boiler thoroughly with clean water by using purging valves to allow water to flow through the water make-up line to the boiler. 14. When securing the burner, be sure to tighten the nuts, but DO NOT over-tighten. Tighten the nuts to a torque setting of no more than 6.2 ft.-lbs. When securing the burner mounting plate be sure to tighten the nuts, but DO NOT over-tighten. Tighten the nuts to a torque setting of no more than 15.5 ft.-lbs.
chamber lining to prevent airborne dust. Remove the combustion chamber lining
from the boiler and place it in a plastic bag for disposal. Wash potentially contaminated clothes
separately from other clothing. Rinse clothes washer thoroughly.
NIOSH stated First Aid.
Eye: Irrigate immediately. Breathing: Fresh air.

Figure 12-1 Ladder Diagram
JUNCTION BOX
TERMINAL STRIP 120V SUPPLY "L" TERMINAL STRIP 120V SUPPLY "N"
BOX DEPICTS DUAL SENSOR SINGLE HOUSING
INTEGRATED CONTROL
ON/OFF SWITCH
1.5A EACH MAX
LOW VOLTAGE 120 VAC
TERMINAL STRIP
GROUND
F2
F4
HIGH VOLTAGE
3.15 A
5.0 A SYSTEM PUMP
SYSTEM PUMP
RELAY
CONTACTOR
INTEGRATED
CONTROL
LARGE CONNECTION BOARD
BOILER PUMP
BOLIER PUMP
RELAY
CONTACTOR
CN6-3
CN6-2
DHW PUMP
DHW PUMP CONTACTOR
MODBUS
BOARD
RELAY
CN6-1
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
A
MODBUS OPTION
SMALL BLOWER
RELAY
CN3-6
B
CN3-7
SHIELD
X10-1 X10-2
RELAY SMALL GAS VALVE RELAY
LARGE BLOWER
RATE OUT
CN3-14
BOILER PUMP OUT
LARGE GAS VALVE RELAY
CN3-13
SYSTEM RETURN SENSOR
LARGE GAS VALVE RELAY X10-6
GAS VALVE (LARGE) GAS VALVE (SMALL)
CN3-12
SYSTEM SUPPLY SENSOR
SMALL GAS VALVE RELAY
CN3-11
TANK SENSOR
CN3-10
OUTDOOR SENSOR
FLAME SENSE 2
CN3-4 X8-15
CN3-9
BMS IN
CN3-8
SYSTEM PUMP IN
SPARK
SPARK GENERATOR
ROD
CN3-1
SHIELD
FLAME SENSE 1
CN3-2
A
B CASCADE
SHIELD
CN3-3
CN3-4
USB INTERFACE
-T
INLET SENSOR
-T
SMALL BLOWER
OUTLET SENSOR (S9)
SMALL BLOWER
RELAY
-T
OUTLET SENSOR (S1)
LARGE BLOWER
-T
LARGE BLOWER
FLUE SENSOR
RELAY
-T
FLUE SENSOR (S10)
-T
MODBUS X1-1 X1-2
PRE-MIX SENSOR 1 (S11)
-T
PRE-MIX SENSOR 1 (S13)
FLUE DAMPER TRANSFORMER
-T
PRE-MIX SENSOR 2 (S12)
-T
PRE-MIX SENSOR 2 (S14)
FLUE DAMPER
M 1 2
SMALL BLOWER
24V TRANSFORMER
LARGE BLOWER
J3-6
J3-5
TEST SWITCH LWCO PROBE
J3-3
J3-2
LWCO RESET
J2-1
LWCO BOARD
J3-4
J2-2
RIBBON CABLE
INTEGRATED
CN3 CN1
LCD DISPLAY
CONTROL
GPS1 GPS2 GPS3
SMALL CONNECTION BOARD
DU941
BLOWER PROVING
CN1-4
SWITCH (LARGE)
CN1-5
BLOWER PROVING
SWITCH (SMALL)
CN1-6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
BLOCKED FLUE
SWITCH
CN1-12
RUN-TIME CONTACTS
CN1-10
BLOCKED DRAIN
SWITCH
TANK THERMOSTAT
CN1-11
ENABLE R
W
CN1-9
LOUVER PROVING
CN1-8
24 VAC LOUVER RELAY COIL
CN1-7
AUX SWITCH 1
"X5" BLOCK WIRING
CN1-1
AUX SWITCH 2
IS MODEL DEPENDANT
HIGH LIMIT
CN1-2
SWITCH
CN1-3
Notes: 1. All wiring must be installed in accordance with: local, state, provincial and national code requirements per either N.E.C. in USA or C.S.A. in Canada. 2. If any original equipment wire as supplied with the appliance must be replaced, it must be replaced with wire having same wire gauge (AWG) and rated for a minimum of 105°C. Exceptions : Replacement high voltage spark lead and ribbon cables must be purchased from the factory. Use of a non-approved spark lead or ribbon cables can lead to operational problems which could result in non-repairable damage to the integrated controller or other components. 3. Actual connector block locations may vary from those shown on diagrams. Refer to actual components for proper connector block locations when using diagrams to troubleshoot unit.
LBL20281 REV A

Figure 12-2 Wiring Diagram
BOX DEPICTS DUAL SENSOR SINGLE HOUSING
MODBUS
BOARD
LARGE CONNECTION BOARD
X1-2 X1-3
LOW VOLTAGE 120 VAC
SHIELD
CN6-3 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
B MODBUS
A
CN6-2
R
X6-1 X6-2
INTEGRATED CONTROL
HIGH VOLTAGE
OPTION
CN6-1
R P
SHIELD
X4-1 X4-2 X4-3
K B
X8-20 X8-10
RATE
OUT
T
BOILER PUMP OUT
CN3-4
CN3-7 CN3-14
CN3-6
L B
R
X7-8 X7-7
SYSTEM RETURN
L B
X8-14 X8-13
SENSOR
CN3-13 CN3-12 CN3-11 CN3-10
R
SYSTEM SUPPLY
SENSOR
R B
X8-12 X8-11
TANK SENSOR
W
CN3-9 CN3-8
R O OR/W P
X8-15 X8-5
1.5A EACH MAX
OUTDOOR
X8-6 X8-16 X8-7 X8-17 X8-18 X8-1
SYSTEM PUMP CONTACTOR
SENSOR
CN3-1 CN3-2
W
120V SUPPLY
BMS
IN
L B
BOILER PUMP CONTACTOR
SYSTEM PUMP IN
CN3-5 CN3-3
K B
GND
DHW PUMP CONTACTOR
Y/BK
L N
SHIELD
-T
L B
JUNCTION
B CASCADE
A
INLET SENSOR
BOX
SHIELD
-T
W / R
OUTLET SENSOR (S9)
-T
OUTLET SENSOR (S1)
R
BK
-T
W
ON/OFF SWITCH
FLUE SENSOR
-T
Y G
K B
FLUE SENSOR (S10)
W
LCD DISPLAY
-T
Y G
G
PRE-MIX SENSOR 1 (S11)
-T
R B
R P
PRE-MIX SENSOR 1 (S13)
X1-2 X1-4 X10-2
T
-T
K B
R O
PRE-MIX SENSOR 2 (S12)
R O
GAS VALVE (SMALL)
-T
PRE-MIX SENSOR 2 (S14)
T
X10-5 X10-3
L B
R
CN3
GAS VALVE (LARGE)
DU941
L B X6-18
CN1
R
X6-8 X1-8
K B Y G
K B
SMALL BLOWER
SMALL CONNECTION BOARD
RELAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
ALARM CONTACTS
(SMALL)
RUN-TIME CONTACTS
CN1-4
R
1 2 4 5 3
R
X6-9 X6-17
W
TANK THERMOSTAT
CN1-6
R O
T
R
CN1-12
CN1-10 CN1-11
R O
L B
X6-1 X6-11
ENABLE
W
K B
T
LOUVER PROVING
CN1-9 CN1-8 CN1-7 CN1-1 CN1-2 CN1-3
R B
X6-2 X6-14 X6-10 X6-13
BK/W W / G
R
LARGE BLOWER
24 VAC LOUVER RELAY COIL
Y
RELAY
R/W
AUX SWITCH 1
R O HIGH LIMIT
BLOWER
SWITCH R
L B
(LARGE)
AUX SWITCH 2
R
BK/W
1 2 4 5 3
K B / W
T
LWCO BOARD
J3-6
X2-3 X1-7 X1-10
R
FLAME SENSE 2
TEST SWITCH LWCO PROBE
J3-5 J3-4
R
SPARK GENERATOR SPARK ROD
X6-3 R O OR/BK OR/BK
R
P
FLAME SENSE 1
J3-3 J3-2 J2-1 J2-2
LWCO RESET
R O
FLUE DAMPER TRANSFORMER
R O
K B
X6-5 GPS1 GPS2 GPS3
R B R O R O
FLUE DAMPER
GND
L B
M
X6-15 BLOWER PROVING
R O
Y
SWITCH (LARGE)
R O
X6-12 BLOWER PROVING
T
SWITCH (SMALL)
X13-1 BLOCKED FLUE
R P
SWITCH
24V TRANSFORMER
K B
BLOCKED DRAIN
SWITCH
BL
Y
"X5" BLOCK WIRING
X5-3 X5-9
USB INTERFACE
IS MODEL DEPENDANT
X5-4 X5-10 X5-5 X5-41 X5-6 X5-12
Notes: 1. All wiring must be installed in accordance with: local, state, provincial and national code requirements per either N.E.C. in USA or C.S.A. in Canada. 2. If any original equipment wire as supplied with the appliance must be replaced, it must be replaced with wire having same wire gauge (AWG) and rated for a minimum of 105°C. Exceptions: Replacement high vo ltage spark lead and ribbon cables must be purchased from the factory. Use of a non-approved spark lead or ribbon cables can lead to operational problems which could result in non-repairable damage to the integrated controller or other components. 3. Actual connector block locations may vary from those shown on diagrams. Refer to actual components for proper connector block locations when using diagrams to troubleshoot unit. WIRING DIAGRAM

Revision Notes: Revision A (ECO #C07970) initial release.
Revision B (ECO #C08023) reflects changes made to FIG. 6-3 on page 32 for Mass approval and changes made to FIG. 5-3 on page 28.
Revision C (ECO #C08179) reflects the addition of three (3) new vent manufacturers (pg. 16 - Table 2A).
Revision D (ECO #C08585) reflects edits made to FIG. 4-4 and the addition of Fixed or Variable Flow Primary in place of Full Flow.
Revision E (ECO #C08841) reflects changes made to #3 on page 42 additional information added to the humidity warning on page 7, along with references to the Dual Fuel Supplemental Manual.
Revision F (ECO C09629) reflects the update of the AHRI and ASME logos on page 6 and the update of condensate disposal information and Figure 8-1 on page 39.
Revision G (ECO C10325) reflects a kit number correction (Neutralizer kit) and the addition of version 4, software update (pg. 49).
Revision H (ECO C10391) reflects the change in Label and Wiring diagrams on pages 58 and 59.
Revision I (ECO C11129) reflects changes made to the Ratings (page 6), the Common Venting section, page 18 and (ECR 05455) the addition of #7 in the Before Locating the Boiler section on page 7.
FB-I-O Rev I · 08/12
Owners and our team usually reply within a day — and your question helps the next person too.
Be the first to ask — other owners or our team will answer.