7000 Series 7ATB Automatic Transfer & Bypass–Isolation Switches G design 1000 through 4000 amp. sizes
Manual
Refer to the outline and wiring drawings provided with your 7000 Series ATB for all installation and connection details and accessories.
Refer to Group 5 Controller User’s Guide 381333–126 for ATS status display messages, time delays, pickup & dropout settings, and adjustments.
An experienced licensed electrician must install the 7ATB. Rating Label
Each 7000 Series 7ATB contains a rating label to define the loads and fault circuit withstand/closing ratings. Refer to the label on the Transfer Switch for specific values.

Do not exceed the values on the rating label. Exceeding the rating can cause personal injury or serious equipment damage.
Nameplate The Transfer Switch nameplate includes data for each specific 7000 Series ATB. Use the switch only within the limits shown on this nameplate. A typical Catalog Number is shown below with its elements explained:
section-page INSTALLATION Mounting 1-1 Power Connections 1-2 Engine Starting & Auxiliary Circuits 1-2 Functional Test 1-3, 1-4
TESTING & SERVICE Transfer Test 2-1 Preventive Maintenance 2-1 Disconnecting the Controller 2-1 Manual Load Transfer 2-2 Trouble-Shooting 2-2
BYPASSING & ISOLATING Bypassing the ATS 3-1 Isolating the ATS 3-2 Return to Service 3-3, 3-4
4000 amp. size
INDEX back cover
381333–132 F 50 Hanover Road, Florham Park, New Jersey 07932–1591 USA For sales or service call 1 800 800–2726 (ASCO) www.ascopower.com
ASCO POWER TECHNOLOGIES CANADA PO Box 1238, 17 Airport Road, Brantford, Ontario, Canada N3T 5T3



Catalog Number Identification Typical 7000 Series ATB catalog no. for overlapping neutral, 3 pole, 4000 amp., 480 V, in Type 1 enclosure:

G7ATB 4000 A with the lower doors open (transfer switch shown)



The ASCO 7000 Series Automatic Transfer & Bypass–Isolation Switch (ATB) consists of an upper bypass–isolation switch, a lower transfer switch, a monitoring and transfer controller, and door–mounted controls. The ATB is factory wired and tested. Installation requires removal of the shipping skid then securing the enclosure to the supporting foundation.
from the Transfer Switch
Open the lower front door(s). The Transfer Switch carriage is secured to the frame for shipment. Remove the three or four shipping brackets or L–angles (1 upper left, 1 upper right, 1 lower right, or 2 lower on 4000 A).
To prevent serious damage, remove 3 shipping angles from the transfer switch carriage. Do not turn the Isolation Handle until they are removed!
Open the front lower door and remove the two front lag screws securing the enclosure to the wood skid. Next remove the rear lower panel and remove the two rear lag screws securing the enclosure to the wood skid.
The supporting foundation for the enclosure must be level and straight. Allow at least 35 inches in front of the enclosure for draw out of the Transfer Switch. Refer to the enclosure outline drawing included with the ATB for all mounting details including door opening space.
If bottom cable entry is used, the foundation must be prepared so that the conduit stubs are located correctly. Refer to the appropriate enclosure outline drawing for specified cable entrance area and location. Provide cable bending space and clearance to live metal parts. When a concrete floor is poured, use interlocking conduit spacer caps or a wood or metal template to maintain proper conduit alignment.
remove 3 or 4 shipping brackets ( L–angles)
Figure 1-1. On 1000–3000 A remove three shipping
Refer to the enclosure outline drawing furnished with this switch and mount the 7000 Series ATB according to the details and instructions shown on the drawing.
L–angles.
remove 2 upper shipping brackets
remove 2 lower shipping brackets
Figure 1-2. 4000 A remove four shipping L–angles.

If bus connection is used, use SAE grade 5 hardware to connect bus to appropriate terminal plates on bypass switching device. Wipe off bus surfaces before they are joined. If bus is dirty, gently clean surfaces with a non-flammable solvent. Avoid touching cleaned surfaces.
De–energize the conductors before making any line or auxiliary circuitry connections. Be sure that Normal and Emergency line connections are in proper phase rotation. Place engine gen- erator starting control in the OFF position. Make sure engine generator is not in operation.
Do not connect the power conductors to the ATB until they are tested. Installing power cables in conduit, cable troughs, and ceiling-suspended hangers often requires considerable force. The pulling of cables can damage insulation and stretch or break the conductor’s strands. For this reason, after the cables are pulled into position, and before they are connected they should be tested to verify that they are not defective or have been damaged during installation.
Do not breathe cleaning solvent vapors.
Use SAE grade 5 hardware and tighten the bolted joints to the torque specified in Table 2-1.
The reliability of the connection depends on how clean and how tight the joint is.
Table 2-1. Tightening torque values for bolted joints.
Protect the switch from construction grit and metal chips to prevent malfunction or shortened life of the 7ATB switch.
A Wiring Diagram is furnished with the ATB. All wiring must be made in accordance with the local codes. After the power cables have been tested, connect them to the appropriate terminal lugs on the Bypass Switch as shown on the wiring diagram provided with this ATB. Make sure that the lugs provided are suitable for use with the cables being installed. Standard terminal lugs are solderless screw type and will accept the wire sizes listed on the drawings provided with the ATB. Be careful when stripping insulation from conductors; avoid nicking or ringing the conductor. Remove surface oxides from conductors by cleaning with a wire brush. Follow conductor manufacturer’s instructions when aluminum conductor is used. Apply joint compound to conductor, then carefully wipe away excess compound. Tighten the cable lugs to the torque specified on the rating label.
All internal connections are made at the factory. The bypass switch, transfer switch, and control panel are joined together by an interconnecting wire harness. The disconnect plugs are already engaged on enclosed switches. For open–type switches, the plugs must be engaged after installation is completed. Align harness plugs with sockets in the control and push them together until they are secure.
and Auxiliary Circuits
The engine control contact signal connections and auxiliary circuits are located on terminal block TB as shown on the Wiring Diagram provided with the ATB. Connect the signal wires to the appropriate terminals.
Be sure that the Normal and Emergency power connections are in proper phase rotation.



Test HOLD FOR 15 SECONDS
RED
RED GREEN
Figure 1-2. Standard controls and indicators.

Read all instructions on the Wiring Diagrams and labels affixed to the ATB. Note the control features that are provided and review their operation before proceeding.
After installing the ATB check the following:
– Bypass Handle should be in the NORMAL position. – Isolation Handle should be in the CONN position. – TS transfer switch Normal contacts should be CLOSED
(Emergency contacts should be OPEN)

If handles are not in correct positions, follow instruc- tions for Bypassing and Isolating the automatic transfer switch in Section 3. Do not force the handles. Electrical interlocks prevent a wrong sequence of operation.
First check nameplate on transfer switch; rated voltage must be the same as normal and emergency line voltages.
Use extreme caution when using a meter to measure voltages. Do not touch power terminals; shock, burns, or death could result !
Perform steps 1–6 at the right. Observe the status lights. See Figure 1–2.

Q Black square means light is on. S White square means light is off.
* If necessary, adjust voltage regulator on generator per the manufacturer’s recommendations. The ATB will respond only to rated voltage specified on the nameplate.
Now continue to 2 – Electrical Operation on next page.

Test HOLD FOR 15 SECONDS
RED
RED GREEN
Figure 1-3. Standard controls and indicators.

This procedure checks electrical operation of the ATS.
Be sure to close the enclosure door before proceeding to prevent personal injury in case of electrical system fault.

The ATS should still be bypassed. Both normal and emergency sources must be available and the emergency source generator (if used) must be capable of being started; put engine starting control in automatic position. The Transfer Switch Connected to Normal light and the Normal Source Accepted light should be on.


Q Black square means light is on. S White square means light is off.
This completes the Functional Test of the ATB.

REPLACEMENT PARTS
Test the Automatic Transfer Switch portion of the 7000 Series ATB at least once a month. This procedure checks the electrical operation of the Transfer Switch and Controller. Put the engine–generator starting con- trol (at the engine–generator set) in automatic mode. In the following test the generator will start, the load will be transferred to the Emergency source, then back to the Normal source. An interruption to the load will occur, unless the the Transfer Switch contacts are by- passed before the test. See pages 3–1 and 3–2 for by- passing & isolating instructions if no interruption of load is required.
Replacement parts are available in kit form. When ordering parts provide the Serial No., Bill of Material No. (BOM), and Catalog No. from the transfer switch nameplate. For service call ASCO Services at 1–800–800–2726.
The harness disconnect plugs are furnished for repair purposes only and should not have to be unplugged. If the controller must be isolated, follow these steps:
Bypass–Isolation Switch is energized! Do not touch isolation contact fingers; shock, burns, or death could result!
Be sure to close the enclosure door before proceeding to prevent personal injury in case of electrical system fault.
Perform the five–step Electrical Operation – Transfer Test procedure on page 1–4.
PREVENTIVE MAINTENANCE Reasonable care in preventive maintenance will insure high reliability and long life for the 7000 Series ATB. An annual preventive maintenance program is recom- mended.
ASCO Services, Inc. (ASI) is ASCO Power Technologies’ national service organization. ASI can be contacted at 1–800–800–2726 for informa- tion on preventive maintenance agreements.
Checklist for Yearly Inspection
Hazardous voltage capable of causing shock, burns, or death is used in this switch. Deenergize both Normal – Emergency power sources before performing inspections!
S Clean the ATB enclosure. Brush and vacuum
away any excessive dust accumulation. Remove any moisture with a clean cloth. S Check the transfer switch contacts. Remove
transfer switch barriers and check the condition of the contacts. Replace contacts when pitted or worn excessively. Reinstall the barriers carefully. S Maintain transfer switch lubrication. If switch is
subjected to severe dust or abnormal operating conditions, renew factory lubrication on all move- ments and linkages. Relubricate solenoid operator if TS coil is replaced. Don’t use oil; order lubrica- tion kit 75-100. S Check all cable connections & retighten them.
Disconnecting the Plugs · Reconnecting the Plugs

Hazardous voltage capable of causing shock, burns, or death is used in this switch. Do not touch the power or load terminals of the bypass switch or transfer switch!
Table 2-1. Trouble-Shooting Checks.
* These are factory settings. Refer to Controller’s User’s Guide. If the problem is isolated to circuits on the controller or the transfer switch, call your local ASCO Power Technolo- gies sales office or ASI: in the United States, call 1–800–800–2726. Furnish the Serial No., Catalog No., and Bill of Material (BOM) No. from the transfer switch nameplate.
MAINTENANCE HANDLE
This procedure manually transfers load to other source if the Transfer Switch or Controller are out of service.
Bypass and isolate the Transfer Switch before using the maintenance handle! See pages 3–1 and 3–2. Remove the maintenance handle after using it and store it on the frame.
Close enclosure doors to prevent personal injury in case of electrical system fault.
Turn counterclockwise to Emergency.
Turn clockwise to Normal.
slide hub onto shaft
insert handle into hole
Grasp handle firmly

This procedure explains how to Bypass the closed automatic transfer switch contacts. Bypassing is required before the ATS can be tested or isolated. The Bypass Handle must be in the OPEN position (green indicator) and the Isolation Handle must be in the CLOSED position (window). See Figures 3–1, 3–2, and 3–3.
You can only bypass to the same source that the Transfer Switch is connected. Solenoid interlock prevents incorrect operation.

yellow O EMERGENCY CLOSED when ATS is bypassed to Emergency or
yellow O NORMAL CLOSED when ATS is bypassed to Normal Source.
green O OPEN when the ATS is not bypassed.
To Bypass Normal push in handle all the way & turn it clockwise.*
To Bypass Emergency pull out han- dle all the way & turn it clockwise.*
Figure 3–1. Bypass Handle and position indicators.
To Bypass Emergency Source*
(Load connected to Normal Source) The Transfer Switch Connected To Normal light is on and Transfer Switch Connected To Emergency light is off.
(Load connected to Emergency Source) The Transfer Switch Connected To Emergency light is on
and Transfer Switch Connected To Normal light is off.
Push in* the Bypass Handle all the way, then turn it clockwise until Bypass Switch Position shows CLOSED on NORMAL (yellow indicator). The red light Unit Not In Automatic will flash.
Pull out* the Bypass Handle all the way, then turn it clockwise until Bypass Switch Position shows CLOSED on EMERGENCY (yellow indicator). The red light Unit Not In Automatic will flash.
Push in Bypass Handle


& turn it clockwise.
& turn it clockwise.
Figure 3–2. Bypass to Normal.
Figure 3–3. Bypass to Emergency.
The automatic transfer switch can now be put in the TEST or OPEN position. See ISOLATING on page 3–2.
* NOTE: When Accessory 66A (reversed Normal & Emergency connections) is specified, the handle push–pull operation is reversed. Follow instructions on the door.


Isolating is required before any service work can be performed on the automatic transfer switch (ATS). Refer to Figures 3–4, 3–5, 3–6, and 3–7.
Align position indicator. Do not leave the handle in an intermediate position.
Figure 3–6. Isolation Handle. NOTE: In the TEST position the transfer switching device solenoid operator circuit is energized through secondary disconnects.

Turn crank counter- clockwise until window shows TEST.
Hazardous voltage capable of causing electrical shock, burns, or death; do not touch any control circuit terminals.
Figure 3–4. CONNECTED to TEST position. 3. Continue turning Isolation Handle counterclock- wise (approx. 7 turns, approx. 8 turns for 4000 A) until the window shows ISOLATE.

Figure 3–7a. 1000–3000 A transfer switch
Turn crank counter- clockwise until window shows ISOLATE.
isolated and pulled out for inspection. See page 2–2 for maintenance handle use. For 1000–3000 A lifting yoke kit 607064 is available to facilitate lifting by using an overhead crane or similar equipment. For 4000 A use lifting yoke 835745–001.

1000–3000 A switches weighs 350–450 lbs; use lifting yoke 607064. 4000 A switches weigh approx. 600 lb; use lifting yoke 835745--001 or other device capable of lifting this weight to avoid personal injury or equipment damage.
Figure 3–5. TEST to ISOLATE position. 4. Open the lower enclosure door(s). Pull out the side rail carriage. On 4000 A extend two support legs; see Figure 3–7b. Then roll out the transfer switch. It can be safely inspected in this position. The transfer switch can also be removed for easier maintenance operations.
To avoid personal injury and equipment damage on 4000 A switches, two support legs must be extended as shown in Figure 3–7b. Substantial initial force is required to pull out the transfer switch (there are detents on rails).


locking pin with clevis pin
locking pin with clevis pin
adjust length to touch floor
adjust length to touch floor Drawout procedure
Figure 3–7b. 4000 amp transfer switch isolated and pulled out for inspection.
To avoid personal injury and equipment damage on 4000 A switches, two support legs must be extended as shown in Figure 3–8. Substantial initial force is required to pull out the transfer switch (there are detents on rails).
The 4000 A transfer switch weighs 600 lb. Use lifting yoke 835745–001 or other device capable of lifting this weight to avoid personal injury or equipment damage.

This procedure explains how to return the automatic transfer switch (ATS) to service after inspection and maintenance. Observe the Bypass Switch Position indicator and lights). Refer to Figures 3–7a, 3–7b, 3–8, 3–9, and 3–10.
Solenoid interlock prevents you from closing the isolation contacts until the ATS is in the same position as the Bypass Switch.

Close the enclosure door to prevent personal injury in case of electrical system fault.

Operate to NORMAL OperatetoEMERGENCY Turn Transfer Control switch to Retransfer Delay Bypass.
Turn Transfer Control switch to Transfer Test (hold 15 seconds).*
Align position indicator. Do not leave the handle in an intermediate position.
* If Feature 2B time delay is used, there will be a delay before transfer to Emergency.

Do not close the isolation contacts unless the Transfer Switch (ATS) and Bypass Switch are in the same position!
Figure 3–8. Isolation Handle. 2. Turn the Isolation Handle clockwise (approx. 7 turns, approx. 8 turns for 4000 A) until the window shows TEST. The ATS can be tested now without load interruption (see page 2–1).


Turn crank clockwise until window shows TEST.
Turn crank clockwise until window shows CONN (connected). ATS
Figure 3–10. TEST to CONNECTED position.
Figure 3–9. ISOLATE to TEST position.
Now continue to the next page for instructions on how to return the Bypass Handle to the OPEN postition.

RETURN TO SERVICE continued*
This procedure explains how to return the Bypass Switch Handle to the OPEN position. The Bypass Handle must be in the CLOSED position (yellow indicator on NORMAL or EMERGENCY) and the Isolation Handle must be in the TEST position (window). If the handles are not in these positions, refer to Return to Service on page 3–3. See Figures 3–11, 3–12, and 3–13.
You can only bypass to the same source that the ATS is connected. Solenoid interlock prevents incorrect operation.
1 Observe which Bypass Switch Position indicator is yellow (NORMAL or EMERGENCY) at the Bypass Switch Handle. This indicates the source connected to the load. 2 Un–Bypass to same source as the Bypass Switch Position as follows (select Normal or Emergency).

yellow O EMERGENCY CLOSED when ATS is bypassed to Emergency or
yellow O NORMAL when ATS is bypassed to Normal Source.
green O OPEN when the ATS is not bypassed.
To un–Bypass Normal push in handle all the way & turn it counterclockwise.*
Figure 3–11. Bypass Handle and position indicators.
To Un–Bypass Emergency Source*
(Load connected to Normal Source) The Transfer Switch Connected To Normal light is on and Transfer Switch Connected To Emergency light is off.
(Load connected to Emergency Source) The Transfer Switch Connected To Emergency light is on
and Transfer Switch Connected To Normal light is off.
Push in* the Bypass Handle then turn it counterclock- wise until Bypass Switch Position shows OPEN (green indicator). The Unit Not in Automatic light should be off.
Pull out* the Bypass Handle then turn it counterclock- wise until Bypass Switch Position shows OPEN (green indicator). The Unit Not in Automatic light should be off.


Push in Bypass Handle
& turn it counter- clockwise.
& turn it counter- clockwise.
Figure 3–12. Un–Bypass Normal.
Figure 3–13. Un–Bypass Emergency.
The Automatic Transfer & Bypass–Isolation Switch should be left in this position.
* NOTE: When Accessory 66A (reversed Normal & Emergency connections) is specified, the handle push–pull operation is reversed. Follow instructions on the door.

A
R
removal of shipping angles, 1–1
removal of shipping skid, 1–1
isolating the ATS, 3–2
bypassing the ATS, 3–1
return to service, 3–4, 3–5
load connected to emergency, 1–4
catalog number, inside cover
ASCO Services, Inc. (ASI), 2–1
load connected to normal, 1–4
see Controller User’s Guide
disconnecting, 2–1 see Controller User’s Guide
support legs on 4000 A, 3–3
drawout, transfer switch, 3–2, 3–3
manual load transfer, 2–2
test, functional, 1–3, 1–4
testing power cables, 1–2
see Controller User’s Guide
Emergency Source Accepted light,
Transfer Control selector switch
Normal Source Accepted light, 1–3
Retransfer Delay Bypass, 1–4 Transfer Test, 1–4
Engine Control selector switch
Transfer Switch Connected To
engine starting contacts, 1–2
Transfer Switch Connected To
electrical, 1–4 manual, 2–2
transfer test, 1–3, 2–1
transfer to emergency, 1–4, 2–1
functional test, 1–3, 1–4
transfer to normal, 1–4, 2–1
H
phase rotation check, 1–3
customercare@asco.com 800–800–ASCO
voltage, pickup and dropout settings
see Controller User’s Guide
Printed in U.S.A. E ASCO Power Technologies, L.P. 2009
Pages referenced in this manual — manufacturer, support and downloads.
Owners and our team usually reply within a day — and your question helps the next person too.
Be the first to ask — other owners or our team will answer.