Table of Contents 75 sections Important Safety Instructions · Related Documentation · 1.0 Inspecting the Equipment and Storing for Delayed Installations · 1.1 External Inspections · … ShowHide
Important Safety Instructionsp.7Related Documentationp.91.0 Inspecting the Equipment and Storing for Delayed Installationsp.101.1 External Inspectionsp.101.2 Internal Inspectionsp.101.3 Storing for Delayed Installationp.102.0 Installation Drawings and Recommended Tools and Test Equipmentp.122.1 Installation Drawingsp.122.2 Row-Based Installation Examplep.172.3 Recommended Tools and Test Equipmentp.183.0 Positioning the DC UPS Systemp.193.1 General Requirementsp.193.2 General Guidelines for Positioning the DC UPS Modulesp.193.2.1 Cable Entryp.193.2.2 Environmental Considerationsp.193.2.3 Mechanical Considerationsp.203.3 Floor Installationp.203.4 Considerations in Moving the DC UPS Modulep.213.4.1 Transportingp.213.4.2 Moving a DC UPS Modulep.213.4.3 Final Positioningp.213.5 Overhead Cable Tray Railsp.223.6 Front and Rear Bottom Panel Installationp.233.6.1 Bottom DC Distribution Feed (Bottom Cabled) Modulesp.233.6.2 Top DC Distribution Feed (Top Cabled) Modulesp.234.0 Electrical Connectionsp.254.1 Wiring Information and Guidelinesp.254.1.1 Cable Lengths (Floor or Cabinet Top to Connection Point Inside DC UPS Module)p.254.1.2 Recommended Wire Sizes, Recommended Lugs, and Torque Requirementsp.254.1.3 Wiring Guidelinesp.254.2 Protective Coversp.264.3 Wiring Connections Locationsp.274.4 Making Electrical Connectionsp.294.4.1 Cabinet Grounding Connectionp.294.4.2 DC Distribution Ground/Return Busbar Grounding Connectionp.294.4.3 DC Output Distribution Connectionsp.304.4.4 AC Input Power Connectionsp.314.4.5 Optional Alarm/Control Connections (to Primary Module only)p.334.4.6 ACU + Controller Ethernet Connection (to Primary Module only)p.364.4.7 Optional Emergency Power Off (EPO) Connection (to Primary Module only)p.374.4.8 Battery Connectionsp.384.5 Making Module-to-Module -48VDC and Ground/Return Interconnections (if system consists of multiple DC UPS modules)p.384.5.1 -48Vdc and Ground/Return Busbar Interconnectsp.384.6 Making Alarm/Control Interconnections between Modules (if system consists of multiple DC UPS modules)p.414.6.1 RS-485 Module-to-Module Interconnectp.414.6.2 CAN-Bus Module-to-Module Interconnectp.414.6.3 BLVD Module-to-Module Interconnectp.425.0 Installing PCUsp.486.0 Start-Up Instructionsp.496.1 Generalp.496.2 Final Battery Connectionsp.496.2.1 Introductionp.496.2.2 Safetyp.496.2.3 Connecting Batteriesp.496.3 Initially Starting and Verifying DC UPS System Operationp.606.3.1 Initially Starting the DC UPS System and Verifying System Operationp.616.3.2 Setting Common Controller Parametersp.616.3.3 Changing the Numbering Scheme of the PCUsp.627.0 Specifications and Technical Datap.637.1 Agency Approvalsp.637.2 Environmentalp.637.3 Mechanical Characteristicsp.637.4 Monitoring Capabilityp.647.5 Electrical Characteristicsp.657.5.1 Termination Type, Recommended Wire Size, Recommended Lugsp.657.5.2 Power Ratingsp.677.5.3 AC Input Specificationsp.677.5.4 DC Output Specificationsp.687.5.5 Battery Specificationsp.697.5.6 Advanced Control Unit Plus (ACU+) Controllerp.717.5.7 SM-DU+p.717.5.8 SM-DU (used in Expansion Modules only in place of Controller)p.727.5.9 SM-ACp.727.5.10 SM-BRCp.727.5.11 Standard Featuresp.73
Page 1 of the Emerson 582145500 user manual — Installation Manual, Section 6040 (Issue AB, April 8, 2013)
Page 1 · click to enlarge
Page 1

A Technical Manual from the experts in Business-Critical Continuity™

NetSure™ ITM with eSure™ Technology

Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Specification Number: 582145500 Model: NetSure™ ITM

Emerson 582145500 — Installation Manual, Section 6040 (Issue AB, April 8, 2013) diagram (page 1)
Fig. 1 · Installation Manual, Section 6040 (Issue AB, April 8…
Emerson 582145500 — Installation Manual, Section 6040 (Issue AB, April 8, 2013) diagram (page 1)
Fig. 2 · Installation Manual, Section 6040 (Issue AB, April 8…
Emerson 582145500 — Installation Manual, Section 6040 (Issue AB, April 8, 2013) diagram (page 1)
Fig. 3 · Installation Manual, Section 6040 (Issue AB, April 8…
Page 2 of the Emerson 582145500 user manual
Page 2 · click to enlarge
Page 2

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

This page is intentionally blank.

Page 3 of the Emerson 582145500 user manual — Table of contents
Page 3 · click to enlarge
Page 3

Table of contents

Important Safety Instructionsp.7Related Documentationp.91.0 Inspecting the Equipment and Storing for Delayed Installationsp.101.1 External Inspectionsp.101.2 Internal Inspectionsp.101.3 Storing for Delayed Installationp.102.0 Installation Drawings and Recommended Tools and Test Equipmentp.122.1 Installation Drawingsp.122.2 Row-Based Installation Examplep.172.3 Recommended Tools and Test Equipmentp.183.0 Positioning the DC UPS Systemp.193.1 General Requirementsp.193.2 General Guidelines for Positioning the DC UPS Modulesp.193.2.1 Cable Entryp.193.2.2 Environmental Considerationsp.193.2.3 Mechanical Considerationsp.203.3 Floor Installationp.203.4 Considerations in Moving the DC UPS Modulep.213.4.1 Transportingp.213.4.2 Moving a DC UPS Modulep.213.4.3 Final Positioningp.213.5 Overhead Cable Tray Railsp.223.6 Front and Rear Bottom Panel Installationp.233.6.1 Bottom DC Distribution Feed (Bottom Cabled) Modulesp.233.6.2 Top DC Distribution Feed (Top Cabled) Modulesp.234.0 Electrical Connectionsp.254.1 Wiring Information and Guidelinesp.254.1.1 Cable Lengths (Floor or Cabinet Top to Connection Point Inside DC UPS Module)p.254.1.2 Recommended Wire Sizes, Recommended Lugs, and Torque Requirementsp.254.1.3 Wiring Guidelinesp.254.2 Protective Coversp.264.3 Wiring Connections Locationsp.274.4 Making Electrical Connectionsp.294.4.1 Cabinet Grounding Connectionp.294.4.2 DC Distribution Ground/Return Busbar Grounding Connectionp.294.4.3 DC Output Distribution Connectionsp.304.4.4 AC Input Power Connectionsp.314.4.5 Optional Alarm/Control Connections (to Primary Module only)p.334.4.6 ACU + Controller Ethernet Connection (to Primary Module only)p.364.4.7 Optional Emergency Power Off (EPO) Connection (to Primary Module only)p.374.4.8 Battery Connectionsp.384.5 Making Module-to-Module -48VDC and Ground/Return Interconnections (if system consists of multiple DC UPS modules)p.384.5.1 -48Vdc and Ground/Return Busbar Interconnectsp.384.6 Making Alarm/Control Interconnections between Modules (if system consists of multiple DC UPS modules)p.414.6.1 RS-485 Module-to-Module Interconnectp.414.6.2 CAN-Bus Module-to-Module Interconnectp.414.6.3 BLVD Module-to-Module Interconnectp.425.0 Installing PCUsp.486.0 Start-Up Instructionsp.496.1 Generalp.496.2 Final Battery Connectionsp.496.2.1 Introductionp.496.2.2 Safetyp.496.2.3 Connecting Batteriesp.496.3 Initially Starting and Verifying DC UPS System Operationp.606.3.1 Initially Starting the DC UPS System and Verifying System Operationp.616.3.2 Setting Common Controller Parametersp.616.3.3 Changing the Numbering Scheme of the PCUsp.627.0 Specifications and Technical Datap.637.1 Agency Approvalsp.637.2 Environmentalp.637.3 Mechanical Characteristicsp.637.4 Monitoring Capabilityp.647.5 Electrical Characteristicsp.657.5.1 Termination Type, Recommended Wire Size, Recommended Lugsp.657.5.2 Power Ratingsp.677.5.3 AC Input Specificationsp.677.5.4 DC Output Specificationsp.687.5.5 Battery Specificationsp.697.5.6 Advanced Control Unit Plus (ACU+) Controllerp.717.5.7 SM-DU+p.717.5.8 SM-DU (used in Expansion Modules only in place of Controller)p.727.5.9 SM-ACp.727.5.10 SM-BRCp.727.5.11 Standard Featuresp.73
Page 4 of the Emerson 582145500 user manual
Page 4 · click to enlarge
Page 4

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.5 Making Module-to-Module -48VDC and Ground/Return Interconnections (if system consists of multiple DC UPS modules) 32 4.5.1 -48Vdc and Ground/Return Busbar Interconnects 32 4.6 Making Alarm/Control Interconnections between Modules (if system consists of multiple DC UPS modules) 35 4.6.1 RS-485 Module-to-Module Interconnect 35 4.6.2 CAN-Bus Module-to-Module Interconnect 35 4.6.3 BLVD Module-to-Module Interconnect 36 5.0 INSTALLING PCUS 42

6.0 START-UP INSTRUCTIONS 43 6.1 General 43 6.2 Final Battery Connections 43 6.2.1 Introduction 43 6.2.2 Safety 43 6.2.3 Connecting Batteries 43 6.3 Initially Starting and Verifying DC UPS System Operation 54 6.3.1 Initially Starting the DC UPS System and Verifying System Operation 55 6.3.2 Setting Common Controller Parameters 55 6.3.3 Changing the Numbering Scheme of the PCUs 56 7.0 SPECIFICATIONS AND TECHNICAL DATA 57 7.1 Agency Approvals 57 7.2 Environmental 57 7.3 Mechanical Characteristics 57 7.4 Monitoring Capability 58 7.5 Electrical Characteristics 59 7.5.1 Termination Type, Recommended Wire Size, Recommended Lugs 59 7.5.2 Power Ratings 61 7.5.3 AC Input Specifications 61 7.5.4 DC Output Specifications 62 7.5.5 Battery Specifications 63 7.5.6 Advanced Control Unit Plus (ACU+) Controller 65 7.5.7 SM-DU+ 65 7.5.8 SM-DU (used in Expansion Modules only in place of Controller) 66 7.5.9 SM-AC 66 7.5.10 SM-BRC 66 7.5.11 Standard Features 67

Spec. No582145500 ii Section 6040 Model: NetSure™ ITM Issue AB, April 8, 2013
Page 5 of the Emerson 582145500 user manual — Table of contents
Page 5 · click to enlarge
Page 5

Table of contents

Important Safety Instructionsp.7Related Documentationp.91.0 Inspecting the Equipment and Storing for Delayed Installationsp.101.1 External Inspectionsp.101.2 Internal Inspectionsp.101.3 Storing for Delayed Installationp.102.0 Installation Drawings and Recommended Tools and Test Equipmentp.122.1 Installation Drawingsp.122.2 Row-Based Installation Examplep.172.3 Recommended Tools and Test Equipmentp.183.0 Positioning the DC UPS Systemp.193.1 General Requirementsp.193.2 General Guidelines for Positioning the DC UPS Modulesp.193.2.1 Cable Entryp.193.2.2 Environmental Considerationsp.193.2.3 Mechanical Considerationsp.203.3 Floor Installationp.203.4 Considerations in Moving the DC UPS Modulep.213.4.1 Transportingp.213.4.2 Moving a DC UPS Modulep.213.4.3 Final Positioningp.213.5 Overhead Cable Tray Railsp.223.6 Front and Rear Bottom Panel Installationp.233.6.1 Bottom DC Distribution Feed (Bottom Cabled) Modulesp.233.6.2 Top DC Distribution Feed (Top Cabled) Modulesp.234.0 Electrical Connectionsp.254.1 Wiring Information and Guidelinesp.254.1.1 Cable Lengths (Floor or Cabinet Top to Connection Point Inside DC UPS Module)p.254.1.2 Recommended Wire Sizes, Recommended Lugs, and Torque Requirementsp.254.1.3 Wiring Guidelinesp.254.2 Protective Coversp.264.3 Wiring Connections Locationsp.274.4 Making Electrical Connectionsp.294.4.1 Cabinet Grounding Connectionp.294.4.2 DC Distribution Ground/Return Busbar Grounding Connectionp.294.4.3 DC Output Distribution Connectionsp.304.4.4 AC Input Power Connectionsp.314.4.5 Optional Alarm/Control Connections (to Primary Module only)p.334.4.6 ACU + Controller Ethernet Connection (to Primary Module only)p.364.4.7 Optional Emergency Power Off (EPO) Connection (to Primary Module only)p.374.4.8 Battery Connectionsp.384.5 Making Module-to-Module -48VDC and Ground/Return Interconnections (if system consists of multiple DC UPS modules)p.384.5.1 -48Vdc and Ground/Return Busbar Interconnectsp.384.6 Making Alarm/Control Interconnections between Modules (if system consists of multiple DC UPS modules)p.414.6.1 RS-485 Module-to-Module Interconnectp.414.6.2 CAN-Bus Module-to-Module Interconnectp.414.6.3 BLVD Module-to-Module Interconnectp.425.0 Installing PCUsp.486.0 Start-Up Instructionsp.496.1 Generalp.496.2 Final Battery Connectionsp.496.2.1 Introductionp.496.2.2 Safetyp.496.2.3 Connecting Batteriesp.496.3 Initially Starting and Verifying DC UPS System Operationp.606.3.1 Initially Starting the DC UPS System and Verifying System Operationp.616.3.2 Setting Common Controller Parametersp.616.3.3 Changing the Numbering Scheme of the PCUsp.627.0 Specifications and Technical Datap.637.1 Agency Approvalsp.637.2 Environmentalp.637.3 Mechanical Characteristicsp.637.4 Monitoring Capabilityp.647.5 Electrical Characteristicsp.657.5.1 Termination Type, Recommended Wire Size, Recommended Lugsp.657.5.2 Power Ratingsp.677.5.3 AC Input Specificationsp.677.5.4 DC Output Specificationsp.687.5.5 Battery Specificationsp.697.5.6 Advanced Control Unit Plus (ACU+) Controllerp.717.5.7 SM-DU+p.717.5.8 SM-DU (used in Expansion Modules only in place of Controller)p.727.5.9 SM-ACp.727.5.10 SM-BRCp.727.5.11 Standard Featuresp.73
Page 6 of the Emerson 582145500 user manual — Table of contents
Page 6 · click to enlarge
Page 6

Table of contents

Important Safety Instructionsp.7Related Documentationp.91.0 Inspecting the Equipment and Storing for Delayed Installationsp.101.1 External Inspectionsp.101.2 Internal Inspectionsp.101.3 Storing for Delayed Installationp.102.0 Installation Drawings and Recommended Tools and Test Equipmentp.122.1 Installation Drawingsp.122.2 Row-Based Installation Examplep.172.3 Recommended Tools and Test Equipmentp.183.0 Positioning the DC UPS Systemp.193.1 General Requirementsp.193.2 General Guidelines for Positioning the DC UPS Modulesp.193.2.1 Cable Entryp.193.2.2 Environmental Considerationsp.193.2.3 Mechanical Considerationsp.203.3 Floor Installationp.203.4 Considerations in Moving the DC UPS Modulep.213.4.1 Transportingp.213.4.2 Moving a DC UPS Modulep.213.4.3 Final Positioningp.213.5 Overhead Cable Tray Railsp.223.6 Front and Rear Bottom Panel Installationp.233.6.1 Bottom DC Distribution Feed (Bottom Cabled) Modulesp.233.6.2 Top DC Distribution Feed (Top Cabled) Modulesp.234.0 Electrical Connectionsp.254.1 Wiring Information and Guidelinesp.254.1.1 Cable Lengths (Floor or Cabinet Top to Connection Point Inside DC UPS Module)p.254.1.2 Recommended Wire Sizes, Recommended Lugs, and Torque Requirementsp.254.1.3 Wiring Guidelinesp.254.2 Protective Coversp.264.3 Wiring Connections Locationsp.274.4 Making Electrical Connectionsp.294.4.1 Cabinet Grounding Connectionp.294.4.2 DC Distribution Ground/Return Busbar Grounding Connectionp.294.4.3 DC Output Distribution Connectionsp.304.4.4 AC Input Power Connectionsp.314.4.5 Optional Alarm/Control Connections (to Primary Module only)p.334.4.6 ACU + Controller Ethernet Connection (to Primary Module only)p.364.4.7 Optional Emergency Power Off (EPO) Connection (to Primary Module only)p.374.4.8 Battery Connectionsp.384.5 Making Module-to-Module -48VDC and Ground/Return Interconnections (if system consists of multiple DC UPS modules)p.384.5.1 -48Vdc and Ground/Return Busbar Interconnectsp.384.6 Making Alarm/Control Interconnections between Modules (if system consists of multiple DC UPS modules)p.414.6.1 RS-485 Module-to-Module Interconnectp.414.6.2 CAN-Bus Module-to-Module Interconnectp.414.6.3 BLVD Module-to-Module Interconnectp.425.0 Installing PCUsp.486.0 Start-Up Instructionsp.496.1 Generalp.496.2 Final Battery Connectionsp.496.2.1 Introductionp.496.2.2 Safetyp.496.2.3 Connecting Batteriesp.496.3 Initially Starting and Verifying DC UPS System Operationp.606.3.1 Initially Starting the DC UPS System and Verifying System Operationp.616.3.2 Setting Common Controller Parametersp.616.3.3 Changing the Numbering Scheme of the PCUsp.627.0 Specifications and Technical Datap.637.1 Agency Approvalsp.637.2 Environmentalp.637.3 Mechanical Characteristicsp.637.4 Monitoring Capabilityp.647.5 Electrical Characteristicsp.657.5.1 Termination Type, Recommended Wire Size, Recommended Lugsp.657.5.2 Power Ratingsp.677.5.3 AC Input Specificationsp.677.5.4 DC Output Specificationsp.687.5.5 Battery Specificationsp.697.5.6 Advanced Control Unit Plus (ACU+) Controllerp.717.5.7 SM-DU+p.717.5.8 SM-DU (used in Expansion Modules only in place of Controller)p.727.5.9 SM-ACp.727.5.10 SM-BRCp.727.5.11 Standard Featuresp.73
Page 7 of the Emerson 582145500 user manual — SAVE THESE INSTRUCTIONS
Page 7 · click to enlarge
Page 7

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

I MPORTANT S AFETY I NSTRUCTIONS

SAVE THESE INSTRUCTIONS

This manual contains important instructions that should be followed during installation of your NetSure™ ITM Row-Based DC UPS system.

Read this manual thoroughly before installing the DC UPS system. Retain this manual for use by installing personnel.

! WARNING The DC UPS system should be installed by a qualified technician in accordance with the information contained in this document.

! WARNING Special safety precautions are required for procedures involving handling and installation of the DC UPS system. Observe all safety precautions in this manual before handling or installing the DC UPS system.

! WARNING Exercise extreme care when handling DC UPS modules (cabinets) to avoid equipment damage or injury to personnel. The DC UPS module weighs 3240 lb. (1470 kg), fully loaded.

Be aware of module weight and locate center of gravity symbols before handling the DC UPS module. Test lift and balance the module before transporting. Never tilt module more than 10 degrees from vertical.

! WARNING All power and control wiring should be installed by a qualified electrician. All power and control wiring must comply with the National Electrical Code (NEC) and applicable local codes.

Maximum load must not exceed that shown on the DC UPS module rating label.

Maximum output short circuit current is 7000 amperes.

! WARNING High Ground Leakage Current: Ground connection is essential before connecting the input supply.

This equipment must be grounded in accordance with the NEC and applicable local codes.

! CAUTION Ground leakage current exceeds 3.5 mA and is less than 30 mA.

Transient and steady-state ground leakage currents, which may occur when starting the equipment, should be taken into account when selecting instantaneous residual current circuit breakers (RCCBs) or residual current devices (RCDs).

RCCBs must be selected sensitive to DC unidirectional pulses (Class A) and insensitive to transient current pulses.

Page 8 of the Emerson 582145500 user manual — Battery Compartment Precautions
Page 8 · click to enlarge
Page 8

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

! CAUTION This equipment is fitted with RFI suppression filters.

This unit complies with the limits for a Class A digital device, pursuant to Part 15 Subpart J of the FCC rules. These limits provide reasonable protection against harmful interference in a commercial environment. This unit generates, uses and radiates radio frequency energy and, if not installed and used in accordance with this instruction manual, may cause harmful interference to radio communications. This unit is not designed for use in a residential area. Operation of this unit in a residential area may cause harmful interference that the User must correct at his own expense.

! WARNING In case of fire involving electrical equipment, use only carbon dioxide fire extinguishers or those approved for use in fighting electrical fires.

Battery Compartment Precautions

Batteries are factory installed in the DC UPS module. Final battery connections will be made by Emerson after the DC UPS module is installed. DO NOT MAKE BATTERY CONNECTIONS. The following precautions apply to the battery compartment that is part of the DC UPS module.

! WARNING Special safety precautions are required for procedures involving handling, installing, and servicing batteries. Observe all battery safety precautions presented here and in the battery instruction manual. These precautions should be followed implicitly at all times.

! WARNING A battery can present a risk of electrical shock and high short circuit current. Servicing of batteries should be performed or supervised only by properly trained and qualified personnel knowledgeable about batteries and the required precautions.

The following precautions should be observed when working on batteries:

  • Remove watches, rings and other metal objects.
  • Eye protection should be worn to prevent injury from accidental electrical arcs.
  • Use certified and well maintained insulated tools.
  • Do not lay tools or metal parts on top of batteries.
  • Disconnect charging source prior to connecting or disconnecting battery terminals.
  • Determine if battery is inadvertently grounded. If the battery is inadvertently grounded, remove source from ground. Contact with any parts of a grounded battery can result in electrical shock. The likelihood of such shock can be reduced if such grounds are removed during installation and maintenance (applicable to equipment and remote battery supplies not having a grounded supply circuit).
  • Risk of explosion if battery is replaced with an incorrect type or if polarity is reversed. When replacing batteries, replace with the same manufacturer and type, or equivalent. See your local Emerson representative for a list of approved batteries.
  • Dispose of used batteries according to the instructions provided with the batteries. Do not dispose of batteries in a fire. They may explode. In addition to the hazard of electric shock, gas produced by batteries can be explosive and sulfuric acid can cause severe burns. Do not open or mutilate batteries. Released electrolyte is harmful to the skin and eyes, and is toxic. If electrolyte comes into contact with skin, the affected area should be washed immediately with large amounts of water.
Page 9 of the Emerson 582145500 user manual — R ELATED D OCUMENTATION
Page 9 · click to enlarge
Page 9

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

! WARNING The DC UPS module’s internal batteries are connected and energized even if the DC UPS module is turned OFF. Battery disconnect fuses are provided inside the DC UPS module. To minimize the risk of injury, remove the battery disconnect fuses before any off-line servicing is performed on the unit.

! WARNING DO NOT REMOVE BATTERY STRAPS. If a battery cell is replaced, ensure the battery strap is replaced and appropriately tighten.

  • Battery compartments contain non-spillable batteries.
  • Keep units upright.
  • Do not stack.
  • Do not tilt. Failure to heed this warning could result in smoke, fire, or electric hazard.

Call Emerson before moving DC UPS modules (after initial installation).

R ELATED D OCUMENTATION

  • System Operation Document (Section 6047).
  • Site Planning Data and System Drawings Document (Section 6037).
  • Emerson Excellence Range VRLA Battery (31020591)
Page 10 of the Emerson 582145500 user manual — 1.3 Storing for Delayed Installation
Page 10 · click to enlarge
Page 10

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

1.0 INSPECTING THE EQUIPMENT AND STORING FOR DELAYED INSTALLATIONS

1.1 External Inspections 1. While the DC UPS system is still on the truck, inspect the equipment and shipping container(s) for any signs of damage or mishandling. Do not attempt to install the system if damage is apparent. If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact Emerson Network Power (number located on last pages of this document) to inform them of the damage claim and the condition of the equipment. 2. Compare the contents of the shipment with the bill of lading. Report any missing items to the carrier and your local Emerson representative immediately.

1.2 Internal Inspections 1. Remove any packaging material, then visually examine the DC UPS system for transit damage, both internally and externally. Report any such damage to the shipper and to Emerson immediately. 2. Check the nameplate inside the DC UPS module (located on the front top right side with front door open) to verify that the "base configuration part number" and the "configured system spec. number" correspond to the units ordered. Record the DC UPS module identification numbers and serial number in the front of this manual. This information is necessary should service be required. See Table 1.

3. Check for loose connections or unsecured components in the module. 4. Check for shipping damage to internal components.

1.3 Storing for Delayed Installation

If the equipment will not be installed immediately, it must be stored indoors where the humidity is no higher than 95%. The storage area must protect the DC UPS system from excessive moisture.

For optimal battery life, store at a temperature between -4°F to +77°F (-20°C to +25°C) (see 7.2 - Environmental).

! CAUTION If the batteries must remain disconnected from the DC UPS module for more than six (6) months, the batteries must be recharged before use. To charge the batteries, the batteries must be connected to the DC UPS module and the DC UPS module must be connected to utility power and started up by qualified personnel.

Page 11 of the Emerson 582145500 user manual — 1.0 Inspecting the Equipment and Storing for Delayed Installations
Page 11 · click to enlarge
Page 11

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Table 1 DC UPS Module "Base Configuration Part Numbers" and "Configured System Spec. Numbers"

Base Configuration Part Numbers Part NumberModuleDistribution FeedDistributionNo. of AC Inputs FAB8010542/2PrimaryTop(22) Circuit Breaker1 FAB8010542/1PrimaryTop(22) Circuit Breaker2 FAB8010542/4PrimaryTop(6) Fuse1 FAB8010542/3PrimaryTop(6) Fuse2 FAB8010540/2PrimaryBottom(22) Circuit Breaker1 FAB8010540/1PrimaryBottom(22) Circuit Breaker2 FAB8010540/4PrimaryBottom(6) Fuse1 FAB8010540/3PrimaryBottom(6) Fuse2 FAB8010543/2ExpansionTop(22) Circuit Breaker1 FAB8010543/1ExpansionTop(22) Circuit Breaker2 FAB8010543/4ExpansionTop(6) Fuse1 FAB8010543/3ExpansionTop(6) Fuse2 FAB8010541/2ExpansionBottom(22) Circuit Breaker1 FAB8010541/1ExpansionBottom(22) Circuit Breaker2 FAB8010541/4ExpansionBottom(6) Fuse1 FAB8010541/3ExpansionBottom(6) Fuse2 Configured System Spec. Numbers Spec. NumberDescription 582145500-M1Primary Module 582145500-M21st Expansion Module 582145500-M32nd Expansion Module 582145500-M43rd Expansion Module
Page 12 of the Emerson 582145500 user manual — 2.1 Installation Drawings
Page 12 · click to enlarge
Page 12

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

2.0 INSTALLATION DRAWINGS AND RECOMMENDED TOOLS AND TEST EQUIPMENT

2.1 Installation Drawings

The diagrams in this section illustrate the key mechanical and electrical characteristics of the NetSure ITM DC UPS system.

General Notes Applicable to All Illustrations 1. All dimensions are in inches (millimeters). 2. Minimum clearance above unit required for air exhaust is 8 in. (203mm). 3. Keep module within 10 degrees of vertical while handling. 4. Top and bottom cable entry options available. 5. Color - black. 6. Unit bottom is structurally adequate for forklift handling. 7. M12 mounting holes used for seismic anchoring or floor stand.

8. The Primary Module includes side panels. For installations consisting of Expansion Module(s), one side panel on the Primary Module must be removed and be placed on the end Expansion Module. 9. Leveling feet are not designed to carry the full weight of the module. 10. Finger-tighten leveler against the floor, then tighten with a wrench less than 2 turns for friction fit against floor. 11. Control wiring, output cabling, and input cabling must be run separately. 12. Aluminum and copper-clad aluminum cables are not recommended. 13. All wiring is to be in accordance with the NEC and applicable local codes.

Page 13 of the Emerson 582145500 user manual — 2.0 Installation Drawings and Recommended Tools and Test Equipment
Page 13 · click to enlarge
Page 13

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 1 Outline Drawing

Emerson 582145500 — 2.0 Installation Drawings and Recommended Tools and Test Equipment diagram (page 13)
Fig. 4 · 2.0 Installation Drawings and Recommended Tools and…

DC UPS MODULE WITH TOP FEED DC DISTRIBUTION DC UPS MODULE WITH BOTTOM FEED DC DISTRIBUTION

Top Cabled Version X = 11.81 (300) Y = 26.38 (670) Z = 36.61 (930)

Bottom Cabled Version X = 11.81 (300) Y = 26.38 (670) Z = 40.55 (1030)

Page 14 of the Emerson 582145500 user manual — 2.0 Installation Drawings and Recommended Tools and Test Equipment
Page 14 · click to enlarge
Page 14

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 1, Detail A

Emerson 582145500 — 2.0 Installation Drawings and Recommended Tools and Test Equipment diagram (page 14)
Fig. 5 · 2.0 Installation Drawings and Recommended Tools and…

M12 x 1.75 x 70 Metric Socket Head Cap Screw. Plain Finish with Allen Drive (hex drive) / Coarse thread. Grade 12.9.

M12 X 1.75 Metric Hex Nuts - Grade 10.9 / Coarse Thread / Zinc Plated.

M12 Metric Flat Washer. Grade 10.9 / Zinc. D=28mm or 11/8".

Hole through foot (4x) for anchoring on raised floor

Page 15 of the Emerson 582145500 user manual — 2.0 Installation Drawings and Recommended Tools and Test Equipment
Page 15 · click to enlarge
Page 15

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 2 Bottom DC Distribution Feed Modules

Emerson 582145500 — 2.0 Installation Drawings and Recommended Tools and Test Equipment diagram (page 15)
Fig. 6 · 2.0 Installation Drawings and Recommended Tools and…
Page 16 of the Emerson 582145500 user manual — 2.0 Installation Drawings and Recommended Tools and Test Equipment
Page 16 · click to enlarge
Page 16

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 3 Top DC Distribution Feed Modules

Emerson 582145500 — 2.0 Installation Drawings and Recommended Tools and Test Equipment diagram (page 16)
Fig. 7 · 2.0 Installation Drawings and Recommended Tools and…

Front Cable Tray Supports if Mounted on Top of Module

Page 17 of the Emerson 582145500 user manual — 2.2 Row-Based Installation Example
Page 17 · click to enlarge
Page 17

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

2.2 Row-Based Installation Example

The NetSure ITM DC UPS system provides the flexibility to meet the needs of any data center.

The NetSure ITM DC UPS system is delivered fully configured for quick and easy field installation. Multiple DC UPS modules can easily be connected on site in order to increase capacity. Each module takes only 24" (w) x 41" (d) of floor space, including batteries and primary distribution. The NetSure ITM DC UPS system is typically installed in the middle or at the end of a row of server racks. This makes the system uniquely flexible and scalable. Deploy only the capacity that is initially needed; modules can be added at any time to existing units on the data center floor.

Figure 4 depicts a top distribution feed installation powering IT racks. Depending on your site and budget requirements, the NetSure ITM DC UPS solution can either be installed as a single deployment, or incrementally by row. In either scenario, DC distribution cabling to each rack is reduced by placing the NetSure ITM DC UPS in-the-row.

Whatever the physical layout of your data center, the NetSure ITM DC UPS allows for maximum space for IT equipment. With DC UPS building block modules, you can mix and match configurations and standard layouts to fit your available space.

Figure 4 NetSure™ ITM Row-Based DC UPS System Installation Example

Emerson 582145500 — 2.2 Row-Based Installation Example diagram (page 17)
Fig. 8 · 2.2 Row-Based Installation Example
Page 18 of the Emerson 582145500 user manual — 2.3 Recommended Tools and Test Equipment
Page 18 · click to enlarge
Page 18

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

2.3 Recommended Tools and Test Equipment

The following tools and test equipment are recommended to install the DC UPS modules.

  • Non-Contact Voltage Detector
  • Digital Multimeter (DMM), 0 to 60 V dc, 0 to 600 V ac
  • NO-OX-ID-A or Approved Equivalent
  • Lineman's Scissors
  • Lineman's Strippers
  • Lineman's Cutters
  • Electrician's Insulated Screwdrivers, Phillips, No. 1 and 2
  • Electrician's Insulated Screwdrivers, Flat-Blade, Small and Large
  • Adjustable Torque Wrench, 1/2" Drive, 0 in-lb to 800 in-lb
  • Ratchet, 1/2" Drive
  • Insulated Nut Driver Set
  • Crimping Tool with Dies from 350 kcmil to 2 AWG
  • Torx Screwdrivers or Bits: TX10 and TX20
  • 17 mm Wrench or Socket for M10 Bolts and Nuts (for circuit breaker distribution)
  • 19 mm Wrench or Socket for M12 Bolts and Nuts (for fuse distribution)
  • 24 mm Wrench for Pallet.
  • Hexagonal mm Bit for the Air Duct.
  • Hexagonal Bit for the AC Input Breaker.

Contact Emerson for full turn key installation quote.

Page 19 of the Emerson 582145500 user manual — 3.2.2 Environmental Considerations
Page 19 · click to enlarge
Page 19

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

3.0 P OSITIONING THE DC UPS S YSTEM

This section describes the environmental and mechanical considerations that must be taken into account when planning the positioning and cabling of the DC UPS system. This section also provides procedures for physical installation of the DC UPS cabinet.

Because every site is unique, some subsections present a guide to general procedures and practices that should be observed by the installing engineer, rather than step-by-step installation instructions.

3.1 General Requirements

  • The installer should be familiar with the installation requirements and techniques to be used in securing the DC UPS module (cabinet) to the floor. It is up to the customer to determine the requirements for anchoring the cabinet to the specific type of floor at the site, select proper anchors, and to investigate the proper use of the anchor.
  • This product is intended only for installation in a Restricted Access Location on or above a noncombustible surface.
  • Front and rear access is required for installation and operation (see Clearances in this section).

3.2 General Guidelines for Positioning the DC UPS Modules

Choose a location for the DC UPS system that offers:

  • Easy connection to inputs, outputs, and alarms.
  • Air circulation sufficient to expel heat produced by the DC UPS system.
  • Protection against moisture and excessive humidity.
  • Protection against dust and other particulate matter.
  • Enough space to service the DC UPS system (see Clearances in this section).
  • Compliance with fire prevention regulations and practices.

3.2.1 Cable Entry

DC distribution and alarm cables enter the DC UPS module from the top or bottom, depending on module configuration (top distribution feed or bottom distribution feed).

AC input cables can enter either at the top or bottom. Conduit openings are provided in both locations.

3.2.2 Environmental Considerations

Before installing the DC UPS system, verify that the room satisfies the environmental conditions stipulated in 7.2 - Environmental, paying particular attention to the ambient temperature and air exchange system. Also refer to 7.2 - Environmental for details on heat dissipation.

The DC UPS system should be installed in a cool, dry, clean-air environment with adequate ventilation to keep the ambient temperature within the specified operating range +23°F to +95°F (-5°C to +35°C).

  • Batteries are installed in the DC UPS module’s battery compartment. Temperature is a major factor in determining battery life and capacity. Battery manufacturers recommend an operating temperature of 77°F (25°C). Ambient temperatures higher than this reduce battery life; temperatures lower than this reduce battery capacity. For optimal battery performance and service life, inlet air temperature to the battery compartment (from the front of the system) should be maintained between +68°F to +77°F (+20°C to +25°C) .

The DC UPS module is cooled by internal fans. Cooling air enters the system through the front of the unit and is exhausted out the top. To permit proper air flow and prevent overheating, do NOT block or cover the ventilation openings or blow air down onto the unit. Ventilation clearance above the unit must be a minimum of 8 in. (203mm).

Page 20 of the Emerson 582145500 user manual — 3.3 Floor Installation
Page 20 · click to enlarge
Page 20

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

3.2.3 Mechanical Considerations

The DC UPS system can be comprised of up to four (4) modules (cabinets), depending upon your power requirements. All modules used are the same size and are designed to be positioned side-by- side to form an aesthetically appealing equipment suite. The system always contains one (1) Primary Module. For increased power demands, up to three (3) Expansion Modules may be added. Locate the Primary Module at the far left or far right of the row. Remove the side panel from the Primary Module from the side that will face adjacent Expansion Modules. Place the first Expansion Module next to the Primary Module. Place additional Expansion Modules (if required) next to each other. Install the side panel removed from the Primary Module to the open side of the last Expansion Module in the row.

NOTE When the DC UPS system consists of multiple modules, the switches inside the modules are pre-set at the factory to identify the module as the Primary Module, 1st Expansion Module, 2nd Expansion Module, or 3rd Expansion Module. When placing modules, refer to the nameplate identification number (see Table 1) to ensure the Primary Module is placed on the end, and Expansion Modules are place in sequential order.

Clearances

There are no ventilation grilles on the sides of the DC UPS module. The DC UPS modules may be placed with the sides touching or against a wall.

To enable routine tightening of power terminations within the DC UPS module, make sure there is sufficient clearance in front and rear of the DC UPS module to permit free passage of personnel and that the front door can be fully opened.

Leave a minimum of 8 in. (203mm) between the top of the DC UPS module and the ceiling to permit adequate air circulation above the unit. Emerson recommends against using air conditioning or other systems that blow air onto the top of the unit.

Leave a minimum of 36 in. (914 mm) between the back of the DC UPS module and a wall to permit adequate air circulation for the battery compartment fans and facilitate maintenance access.

3.3 Floor Installation

Refer also to 3.1 - General Requirements.

The diagrams in 2.0 - Installation Drawings and Recommended Tools and Test Equipment show the location of holes in the base plate for bolting the DC UPS module to the floor.

If the module is to be placed on a raised floor, it should be mounted on a floor stand that will support the equipment point loading. Refer to the cabinet-bottom views in 2.0 - Installation Drawings and Recommended Tools and Test Equipment to design this pedestal. Contact your Emerson Sales Representative for a floor stand designed for this system (see Figure 5).

Figure 5 Emerson Floor Stands

Emerson 582145500 — 3.3 Floor Installation diagram (page 20)
Fig. 9 · 3.3 Floor Installation

P/N 547823 36” Tall Floor Stand P/N 547822 24” Tall Floor Stand

Page 21 of the Emerson 582145500 user manual — 3.4.3 Final Positioning
Page 21 · click to enlarge
Page 21

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

3.4 Considerations in Moving the DC UPS Module

3.4.1 Transporting

Ensure that the DC UPS module weight is within the designated surface weight loading (lb./ft2 or kg/ cm2) of any handling equipment. The DC UPS module weighs 3240 lb. (1470 kg), fully loaded.

! WARNING Ensure that any equipment that will be used to move the DC UPS module has sufficient lifting capacity. Ensure adequate personnel and lifting equipment are available when taking the module off its shipping pallet. The module presents a tipping hazard. Do not tilt the module further than 10 degrees from vertical.

The DC UPS module is fitted with casters. Take care to prevent movement when unbolting the module from its shipping pallet. The casters are strong enough for movement across even surfaces only. Casters may fail if they are subjected to shock loading, such as being dropped or rolled over holes in the floor or obstructions. Such failure may cause the unit to tip over, injuring personnel and damaging the equipment.

! WARNING Batteries are factory installed in the DC UPS module’s battery compartment. Care must be taken when maneuvering modules with batteries. Keep such moves to a minimum. See Battery Compartment Precautions on page 2.

3.4.2 Moving a DC UPS Module

Cabinet Preparation 1. Inspect the cabinet as described in 1.1 - External Inspections and 1.2 - Internal Inspections. 2. Remove the front and rear bottom panels to gain access to the bolts securing the cabinet to the pallet.

Moving DC UPS Module from Shipping Pallet

Use lifting equipment, such as a forklift or similar equipment, appropriately rated for the weight of the load to move the DC UPS cabinet from its shipping pallet.

When moving a DC UPS cabinet with a forklift or similar equipment, make sure that the fork is of sufficient length for the pallet size and capable of lifting the cabinet. Also use a forklift with adjustable forks or a narrow type.

1. Close the front door. 2. Slide the forklift into place. 3. Unbolt the cabinet from the pallet. 4. Lift the cabinet. The pallet should drop off from its own weight. 5. Carefully move the DC UPS module to its installation location or set the DC UPS module down on its casters if it is to be rolled into position.

Moving DC UPS Module to Installation Location

The DC UPS module may be rolled on its casters when moving the unit a short distance. For longer distances, move the DC UPS module with a forklift or similar equipment to ease the relocation and to reduce vibration.

3.4.3 Final Positioning

Page 22 of the Emerson 582145500 user manual — 3.5 Overhead Cable Tray Rails
Page 22 · click to enlarge
Page 22

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

3.5 Overhead Cable Tray Rails

Refer to Figure 6 for mounting locations for overhead cable tray rails.

Figure 6 Mounting Locations for Overhead Cable Tray Rails

Emerson 582145500 — 3.5 Overhead Cable Tray Rails diagram (page 22)
Fig. 10 · 3.5 Overhead Cable Tray Rails

Brackets can be used to secure rails for overhead cable trays, drill as required.

Holes for 1/4” thread-forming screws to secure rails for overhead cable trays.

Page 23 of the Emerson 582145500 user manual — 3.6.2 Top DC Distribution Feed (Top Cabled) Modules
Page 23 · click to enlarge
Page 23

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

3.6 Front and Rear Bottom Panel Installation

3.6.1 Bottom DC Distribution Feed (Bottom Cabled) Modules

Refer to Figure 7 and install the front and rear bottom panels.

Figure 7 Installing Front and Rear Bottom Panels

Emerson 582145500 — 3.6 Front and Rear Bottom Panel Installation diagram (page 23)
Fig. 11 · 3.6 Front and Rear Bottom Panel Installation

3.6.2 Top DC Distribution Feed (Top Cabled) Modules

Installing the Supplied Air Duct Assembly: The Air Duct Assembly must be installed in DC UPS modules configured for top DC distribution feed (top cabled). The Air Duct Assembly allows air to be drawn from the bottom front of the DC UPS module and up into the battery compartment for cooling. Refer to Figure 8 and install the supplied Air Duct Assembly.

Page 24 of the Emerson 582145500 user manual — 3.6 Front and Rear Bottom Panel Installation
Page 24 · click to enlarge
Page 24

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 8 Installing Air Duct Assembly

Procedure: 1) Partially slide the half of the air duct assembly with vents into the front bottom compartment of the DC UPS module (power compartment bottom). 2) Install and secure the supplied bracket with the supplied screws. 3) Slide the half of the air duct assembly with vents completely into the DC UPS module, and secure with the supplied screws.

Install supplied bracket after partially sliding assembly in.

Secure with supplied screws.

4. Slide the remaining half of the air duct assembly into the rear bottom compartment of the DC UPS module (battery compartment bottom). 5) Secure the air duct half just installed with the supplied screws.

Secure with supplied screws.

Show 6 more labels / short text on this page
Power Compartment Half · Battery Compartment Half · Air Duct Assembly · Battery Compartment Half · Power Compartment Half · Installed View
Page 25 of the Emerson 582145500 user manual — 4.1.3 Wiring Guidelines
Page 25 · click to enlarge
Page 25

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.0 E LECTRICAL C ONNECTIONS

The DC UPS system requires grounding, DC output distribution, AC input power, alarm/control, and battery wiring once it has been mechanically installed.

If the system consists of multiple DC UPS modules, battery and ground/return busbars must be interconnected and alarm/control interconnect wiring between modules must be made.

4.1 Wiring Information and Guidelines

4.1.1 Cable Lengths (Floor or Cabinet Top to Connection Point Inside DC UPS Module)

To help calculate the total cable length required, refer to Table 2 for the distance from the floor or cabinet top to selected connection points inside the DC UPS module. Determine the cable length required to reach the DC UPS module, then add the appropriate length from the table and adequate slack for repair and maintenance.

Table 2 Distance to Connection Points inside the DC UPS Module

Distance - Bottom DC Distribution Feed Module

Distance - Top DC Distribution Feed Module

From Top of Module

From Top of Module

in. (mm)

in. (mm)

in. (mm)

in. (mm)

AC Input 79 (2000) 138 (3500) 157 (4000) 59 (1500)

DC Output 28 (700) N/A N/A 28 (700)

Grounding 79 (2000) 138 (3500) 157 (4000) 59 (1500)

Alarm/Control 59 (1500) N/A N/A 47 (1200)

4.1.2 Recommended Wire Sizes, Recommended Lugs, and Torque Requirements

The main factors affecting the choice and size of wires are voltage, current (also taking into account overcurrent), room temperature, and installation conditions.

The power cables of the system must be sized with respect to the following:

  • AC Input Cables - The AC input cables must be sized for the module’s maximum input current.
  • DC Output Distribution Cables - The DC output distribution cables must be sized for the module’s output breakers or fuses.
  • Battery Cables - The DC UPS module contains a battery compartment. Battery cables are factory supplied and sized accordingly.

Refer to Termination Type, Recommended Wire Size, Recommended Lugs on page 59 for recommended wire sizes and recommended lugs. Refer to the illustrations in this section for torque requirements.

4.1.3 Wiring Guidelines

The following are guidelines only and are superseded by the NEC and applicable local codes where applicable.

  • The grounding cable connecting the DC UPS module to the main ground system must follow the most direct route possible.
  • Consider using paralleled smaller cables for heavy currents—this can ease installation.
Show 5 more labels / short text on this page
Connection Point · inside DC UPS · Module · From Floor · From Floor
Page 26 of the Emerson 582145500 user manual — 4.2 Protective Covers
Page 26 · click to enlarge
Page 26

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

  • When laying power cables, do not form coils; this will help avoid increasing formation of electromagnetic interference. Positive and negative cables should be run together.
  • Alarm/control wiring and power wiring must be run separately. Output and input cables must be run separately.

4.2 Protective Covers

Wiring connection access requires removing protective covers from the DC UPS module. When making electrical connections, remove the appropriate protective cover, as shown in Figure 9.

Replace all protective covers after all electrical connections have been made and checked.

Figure 9 Protective Covers

Emerson 582145500 — 4.2 Protective Covers diagram (page 26)
Fig. 12 · 4.2 Protective Covers

SU ITABLE FOR MOU NTIN G ON CON CRET E

Dual AC Input Circuit Breaker Option Protective Cover View (Top cabled configuration shown, bottom cabled configuration similar.) AC Input Protective Cover

Page 27 of the Emerson 582145500 user manual — 4.3 Wiring Connections Locations
Page 27 · click to enlarge
Page 27

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.3 Wiring Connections Locations

The DC UPS module input and output cable connections are easily accessible from the front of the unit for installation. Refer to Figure 10, Figure 11, Figure 12, Figure 13, Figure 14, Figure 16, Figure 17, Figure 18, and Figure 19 for connection locations. The DC UPS module contains a battery compartment. Battery cables are factory supplied and connected to the DC UPS module. Final connections to the batteries are made in the procedure in 6.2 - Final Battery Connections. Battery connections are done from the rear of the DC UPS module.

Figure 10 Wiring Connections Locations (DC UPS Module with Bottom Feed DC Distribution)

Emerson 582145500 — 4.3 Wiring Connections Locations diagram (page 27)
Fig. 13 · 4.3 Wiring Connections Locations

(AC input cables may also enter at bottom of cabinet.)

Recommended CouplingRaco Type 2628 (Grainger 3LV08) or Thomas Betts Type TK126US

Alarm/Control Connections (to ACU+ IB2 Interface Board) (Primary Module only)

Battery Fuses (3) (Battery leads factory connected and routed to Battery Compartment.)

Load Distribution Devices DCCB01 - DCCB11 (Top Row) DCCB12 - DCCB22 (Bottom Row) (DC distribution breakers shown, large fuses available.)

Battery Compartment and Base Removed in Illustrations for Clarity

Battery Return and Load Return (Battery return leads factory connected and routed to Battery Compartment.)

Page 28 of the Emerson 582145500 user manual — 4.3 Wiring Connections Locations
Page 28 · click to enlarge
Page 28

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 11 Wiring Connections Locations (DC UPS Module with Top Feed DC Distribution)

Emerson 582145500 — 4.3 Wiring Connections Locations diagram (page 28)
Fig. 14 · 4.3 Wiring Connections Locations

AC Input Conduit Openings (AC input cables may also enter

Battery Return and Load Return (Battery return leads factory connected and routed to Battery Compartment.)

Load Distribution Devices DCCB01 - DCCB11 (Top Row) DCCB12 - DCCB22 (Bottom Row) (DC distribution breakers shown, large fuses available.)

Alarm/Control Connections (to ACU+ IB2 Interface Board) (Primary Module only)

Recommended CouplingRaco Type 2628 (Grainger 3LV08) or Thomas Betts Type TK126US

Battery Fuses (3) (Battery leads factory connected and routed to Battery Compartment.)

Battery Compartment and Base Removed in Illustrations for Clarity

Page 29 of the Emerson 582145500 user manual — 4.4.2 DC Distribution Ground/Return Busbar Grounding Connection
Page 29 · click to enlarge
Page 29

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.4 Making Electrical Connections

! CAUTION The electrical connections described in this section must be performed by authorized electricians or qualified technical personnel. Follow the NEC and applicable local codes. If you have any difficulties, contact your local Emerson representative or Emerson Services.

Before making electrical connections, do the following for each DC UPS module (see Figure 10 and Figure 11 for circuit breaker and fuse locations).

  • Open the front door. For bottom cable installations, remove the lower front panel. For all installations, remove protective panels as required (see 4.2 - Protective Covers ).
  • Ensure the main AC input circuit breaker(s) is in the OFF position.
  • Ensure all PCU AC input circuit breakers are in the OFF position.
  • Ensure the three (3) battery disconnect fuses are removed.
  • Ensure all distribution circuit breakers are in the OFF position or distribution fuses are removed.

4.4.1 Cabinet Grounding Connection

The cabinet grounding connection is made to a stud located on the top of the DC UPS module, as shown in Figure 12. A cabinet grounding cable must be connected to this stud, per site requirements. Tighten the connection to the torque indicated in Figure 12.

Each module also contains a separate stud located on each side to connect the supplied grounding strap between DC UPS modules, if desired.

All modules and cable conduit should be grounded in accordance with the NEC and all applicable local codes.

! WARNING Failure to follow proper grounding procedures can result in electric shock hazard to personnel or the risk of fire, should a ground fault occur.

Figure 12 Cabinet Grounding Connection

Emerson 582145500 — 4.4.1 Cabinet Grounding Connection diagram (page 29)
Fig. 15 · 4.4.1 Cabinet Grounding Connection

Grounding Strap between Modules 3/8” (M10) Stud. Recommended Torque is 407-434 in-lbs (46-49 Nm). 5/16” (M8) Studs. Recommended Torque is 204-221 in-lbs (23-25 Nm).

4.4.2 DC Distribution Ground/Return Busbar Grounding Connection

The DC distribution ground/return busbar must be connected via a solidly grounded lead to the main building ground. Three extra positions are provided on the ground/return busbar for customer connection to site ground. Refer to Figure 10 and Figure 11 for location of the DC distribution ground/return busbar. Refer to Table 250-122 in the American National Standards Institute (ANSI) approved National Fire Protection Association's (NFPA) National Electrical Code (NEC) for grounding conductor size. Typically use equivalent or minimum of 1/0 AWG.

Page 30 of the Emerson 582145500 user manual — 4.4.3 DC Output Distribution Connections
Page 30 · click to enlarge
Page 30

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.4.3 DC Output Distribution Connections

Connect the DC output distribution cables between the DC UPS module and the loads as required. These connections are made to the output circuit breaker or fuse busbars and the ground/return busbar, as shown in Figure 10 or Figure 11. Refer to Figure 13 for a view of the busbar terminations. Tighten the connections to the torque indicated in Figure 13.

! WARNING If the load equipment will not be ready to accept power on the arrival of the commissioning engineer, then ensure that the system output cables are safely isolated.

Figure 13 DC Output Connections

Emerson 582145500 — 4.4.3 DC Output Distribution Connections diagram (page 30)
Fig. 16 · 4.4.3 DC Output Distribution Connections

DC Output (-48Vdc) (per distribution position) to distribution device busbar

Terminals are 3/8” (M10) studs. Recommended Torque is 407-434 in-lbs (46-49 Nm).

DC Output Return (per distribution position) to ground/return busbars

DC Output (-48Vdc) (per distribution position) to distribution device busbar

Terminals are 1/2” (M12) studs. Recommended Torque is 690-743 in-lbs (78-84 Nm).

DC Output Return (per distribution position) to ground/return busbars

Page 31 of the Emerson 582145500 user manual — AC Input Connections
Page 31 · click to enlarge
Page 31

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.4.4 AC Input Power Connections

! WARNING AC input power connections must be performed by a qualified electrician.

Before connecting AC input cables to the DC UPS module, ensure that you are aware of the location and operation of the overcurrent protection devices that connect these cables to the power distribution panel. Before connecting AC input cables, de-energize and lockout or tagout these overcurrent protection devices.

Do not apply AC input power to the DC UPS module before the arrival of the commissioning engineer.

AC Input Overcurrent Protective Device

! CAUTION To reduce the risk of fire, connect AC input only to a circuit provided with correct amperes maximum branch circuit overcurrent protection in accordance with the NEC, ANSI/NFPA 70.

External overcurrent protection for the AC input circuit is to be provided by the customer. Refer to AC Input Specifications on page 61 for maximum input current ratings. Each DC UPS module is provided with one or two internal 150A AC input circuit breaker.

AC Input Connections

AC input leads can enter the DC UPS module from the top or from the bottom. Refer to Figure 14 for an AC input routing diagram. Figure 15 provides a diagram for installing conduit fittings when AC is fed from the top.

One or two AC input breakers are provided (depending on module configuration). Refer to Figure 16 for an AC input connections diagram. Tighten the connections to the torque indicated in Figure 16. Note that a cover needs to be removed to access the circuit breakers as shown in Figure 9.

  • Connect Feed A AC input supply cables between the power distribution panel and the DC UPS module’s internal Feed A input circuit breaker (Feed A: L1, L2, L3 terminals).
  • If the DC UPS module is configured for two AC input feeds, connect the optional Feed B AC input supply cables between the power distribution panel and the DC UPS module’s internal Feed B input circuit breaker (Feed B: L1, L2, L3 terminals).
Page 32 of the Emerson 582145500 user manual — 4.4.4 AC Input Power Connections
Page 32 · click to enlarge
Page 32

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 14 AC Input Power Connection Routing Options

Emerson 582145500 — 4.4.4 AC Input Power Connections diagram (page 32)
Fig. 17 · 4.4.4 AC Input Power Connections

Figure 15 Installing Conduit Fittings when AC is Fed from the Top

Emerson 582145500 — 4.4.4 AC Input Power Connections diagram (page 32)
Fig. 18 · 4.4.4 AC Input Power Connections
2. Install one or two customer provided conduit fittings to supplied conduit plate.
3. Secure conduit plate with conduit fittings installed to top of cabinet. Note: If only one conduit being installed, re-install plate that was cut in half.

Figure 16 AC Input Power Connections

Emerson 582145500 — 4.4.4 AC Input Power Connections diagram (page 32)
Fig. 19 · 4.4.4 AC Input Power Connections

One or two AC input circuit breakers are provided (depending on module configuration).

Two ground studs (5/16” [M8]) are provided attached to the sides of the enclosure surrounding the AC input circuit breaker(s).

Recommended torque is 124 in-lbs (14 Nm) for AC input circuit breaker connection.

Recommended torque is 204-221 in-lbs (23-25 Nm) to grounding studs.

Page 33 of the Emerson 582145500 user manual — Digital Input Connections
Page 33 · click to enlarge
Page 33

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.4.5 Optional Alarm/Control Connections (to Primary Module only)

Alarm/control connections are made to the ACU+ Controller Customer Interface Board (IB2). The IB2 board provides connection points for digital inputs and relay outputs. System required connections are factory wired to the IB2 board. The customer may wire to un-used digital input and relay outputs, if desired. The IB2 board is located in an enclosure above the ACU+ Controller (see Figure 10 or Figure 11). To access these connections, loosen the captive fastener on the front of the enclosure and slide the IB2 board partially out of the shelf. Note that a wireway is provided to route the wires to the IB2 board, as shown in Figure 10 or Figure 11. Connect external alarm/control wiring to terminal blocks J3-J9 of the IB2 board, as required. Refer to Figure 17.

Figure 17 Alarm and Control Connections

Emerson 582145500 — 4.4.5 Optional Alarm/Control Connections (to Primary Module only) diagram (page 33)
Fig. 20 · 4.4.5 Optional Alarm/Control Connections (to Primary…

NC = Norm ally Closed COM = Com mon NO = Normally Open

NO C NC NO C NC NO C NC

5 3 1 5 3 1 5 3 1

5 3 1 5 3 1 5 3 1

All relay contacts are shown with the relay deenergized.

6 4 2 6 4 2 6 4 2 6 4 2

6 4 2 6 4 2 6 4 2

NO C NC NO C NC NO C NC NO C NC

Terminals are M2 screws. Recommended Torque is 1.92-2.16 in-lbs (0.22-0.25 Nm). Wire size range is 26 AWG to 16 AWG (0.14 mm^2 to 1.0 mm^2).

Digital Input Connections

Up to eight (8) digital inputs may be connected to the IB2 board. Digital inputs that have factory connections are listed in Table 3. A blank column in Table 3 is also provided if you want to document custom connections to un-used digital inputs.

  • Observe proper polarity per Table 3 . Note that you must supply both paths for the digital input (either a positive or negative signal and the opposite polarity return path).
  • The digital inputs can be configured to provide an alarm when the signal is applied (HIGH) or removed (LOW) (Local menu "Settings / System Dashboard / General"). Refer to Appendix A in the NetSure ITM Operation Manual (Section 6047).

Connecting a NetSure RDB Rack PDU (Power Distribution Unit) to the NetSure ITM: The following applies to all PDUs listed in the NetSure RDB Installation and Operation Manual (Section 6041).

Perform the following after installing and making the DC input and output connections to the PDU per Section 6041.

  • Connect a 22 AWG lead from the circuit breaker alarm connector located on the last PDU to the (-) input of one of the unused digital inputs on the IB2 board. Connect a second 22 AWG lead from the NetSure ITM System Ground/Return (+) to the (+) input of the same digital input on the IB2
Page 34 of the Emerson 582145500 user manual — J5-5
Page 34 · click to enlarge
Page 34

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

board. Assign a unique signal name to this digital input (Web interface "Signal Information Modification Submenu"). Refer to Appendix A in the NetSure ITM Operation Manual (Section 6047).

Table 3 Programmable Digital Inputs

Digital Input Pin No. Dedicated to... Customer Custom Digital Input

1 J3-1 – Available for Customer

Custom Digital Input J3-2 +

2 J3-3 – Available for Customer

Custom Digital Input J3-4 +

3 J3-5 – Available for Customer

Custom Digital Input J3-6 +

4 J4-1 –

PCU EPO factory wired J4-2 +

5 J4-3 –

Fan Supply Alarm factory wired J4-4 +

6 J4-5 –

Fan Alarm factory wired J4-6 +

7 J5-1 – Available for Customer

Custom Digital Input J5-2 +

8 J5-3 – Available for Customer

Custom Digital Input J5-4 +

J5-5

Relay Output Connections

The IB2 board provides eight (8) programmable alarm relays with Form-C contacts. Default relay assignments are documented in Table 4. A blank column in Table 4 is also provided if you want to document a custom configuration. Alarm relay contacts are rated for 2A @ 30VDC and 0.5A @ 125VAC (60W maximum power consumption).

  • Each relay can be individually configured to activate for any system alarm condition.
  • Refer to the NetSure ITM Operation Manual (Section 6047) for programming instructions.

Programmable · internal connections J5-6

Page 35 of the Emerson 582145500 user manual — J9-2 NC
Page 35 · click to enlarge
Page 35

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Table 4 Programmable Relay Outputs

Relay Output Pin No. Alarms Assigned to this Relay (Default)

Alarms Assigned to this Relay (Custom)

J6-5 NO All alarms programmed

with alarm severity of

J6-3 COM

"critical alarm". Relay de-energizes during an alarm condition.

J6-1 NC

(See Note 1.)

J6-6 NO All alarms programmed

with alarm severity of

J6-4 COM

"warning alarm". Relay energizes during an alarm condition.

J6-2 NC

(See Note 1.)

J7-5 NO All alarms programmed

with alarm severity of

J7-3 COM

"information alarm".

Relay energizes during an alarm condition.

J7-1 NC

(See Note 1.)

J7-6 NO

Custom Setting J7-4 COM

J7-2 NC

J8-5 NO

Custom Setting J8-3 COM

J8-1 NC

J8-6 NO

Custom Setting J8-4 COM

J8-2 NC

J9-5 NO

Custom Setting J9-3 COM

J9-1 NC

J9-6 NO

Custom Setting J9-4 COM

J9-2 NC

Show 6 more labels / short text on this page
Programmable · Available for Customer · Available for Customer · Available for Customer · Available for Customer · Available for Customer
Page 36 of the Emerson 582145500 user manual — ESC ENT
Page 36 · click to enlarge
Page 36

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

IB2 Board DIP Switch Settings (for reference only)

Dip Switch SW1 on the IB2 board is used to set the communications address for this board (Table 5). In this system, both switches of SW1 are to be set in the OFF position. Refer to Figure 17 for SW1 location.

Table 5 IB2 Board Communications Address Settings

Emerson 582145500 — IB2 Board DIP Switch Settings (for reference only) diagram (page 36)
Fig. 21 · IB2 Board DIP Switch Settings (for reference only)

IB2 Board LED Indicators (for reference only)

The IB2 board has a green LED indicator which is lit in normal operation and flashes when the IB2 board is communicating with the Controller.

4.4.6 ACU + Controller Ethernet Connection (to Primary Module only)

The ACU+ Controller provides a Web Interface via an Ethernet connection to a TCP/IP network. An RJ-45 10BaseT jack is provided on the front of the ACU+ Controller for connection into a customer's network running TCP/IP. This jack has a standard Ethernet pin configuration scheme, twisted pair. Refer to Figure 10 or Figure 11 for location of the ACU+. Refer to Figure 18 for location and Table 6 for pinouts of the Ethernet port. Use shielded Ethernet cable (grounded at both ends). Note that the ACU+ Controller’s RJ-45 jack is connected to chassis ground.

You can access the Web pages of the power system locally by using a "crossover" or "straight" cable connected directly between your PC and the ACU+.

Figure 18 ACU+ Controller RJ-45 Ethernet Port

ESC ENT

Table 6 ACU+ Controller RJ-45 Ethernet Port

Emerson 582145500 — ESC ENT diagram (page 36)
Fig. 22

Ethernet Port (RJ-45)

Page 37 of the Emerson 582145500 user manual — 4.4.7 Optional Emergency Power Off (EPO) Connection (to Primary Module only)
Page 37 · click to enlarge
Page 37

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.4.7 Optional Emergency Power Off (EPO) Connection (to Primary Module only)

The DC UPS module has an Emergency Power Off (EPO) function operated by a remote contact provided by the User.

! WARNING The EPO circuit operates with -48Vdc. There is -48Vdc present on the terminals the EPO jumper connects to. There is -48Vdc present on these same terminals that an external EPO switch will be connected to.

If the EPO function is desired, locate the EPO jumper in the Primary Module (see Figure 19). Remove the EPO jumper (the jumper connects from the bottom terminal of the EPO terminal block and the bottom of EPO Fuse F11). Connect a customer provided external normally closed switch between the bottom terminal of the EPO terminal block and the bottom of the EPO Fuse.

The following occurs when the EPO switch is opened.

  • The battery LVD contactor in each DC UPS module opens, disconnecting the battery from each module.
  • If the ACU+ "EPO Enabled" option is set to YES, the PCUs in each DC UPS module shut down after 5 seconds. If the ACU+ "EPO Enabled" option is set to NO, PCUs remain running.

It does not internally disconnect the input power supply. To disconnect ALL power to the DC UPS module, open the upstream feeder breaker(s) when the remote EPO is activated.

It does not disconnect the SM-BRC. The SM-BRC will still be powered by the batteries.

Page 38 of the Emerson 582145500 user manual — 4.4.8 Battery Connections
Page 38 · click to enlarge
Page 38

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 19 EPO Jumper Location

Emerson 582145500 — 4.4.8 Battery Connections diagram (page 38)
Fig. 23 · 4.4.8 Battery Connections

Top DC Distribution Feed Shown, Bottom DC Distribution Feed Similar

4.4.8 Battery Connections

Batteries are factory installed and connected. Final connections to the batteries are made in the procedure presented in 6.2 - Final Battery Connections.

4.5 Making Module-to-Module -48VDC and Ground/Return Interconnections (if system consists of multiple DC UPS modules)

4.5.1 -48Vdc and Ground/Return Busbar Interconnects 1. Install the provided -48Vdc Interconnect Busbar(s) between the -48Vdc busbars located in each adjacent DC UPS module. Refer to Figure 20 (DC UPS module with bottom feed DC distribution) and Figure 21 (DC UPS module with top feed DC distribution). Torque to the values listed in the illustrations. 2. Install the provided Ground/Return Interconnect Busbar(s) between the ground/return busbars located in each adjacent DC UPS module. Refer to Figure 20 (DC UPS module with bottom feed DC distribution) and Figure 21 (DC UPS module with top feed DC distribution). Torque to the values listed in the illustrations.

Page 39 of the Emerson 582145500 user manual — 4.4.8 Battery Connections
Page 39 · click to enlarge
Page 39

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 20 Module-Module Interconnect Busbars (DC UPS Module with Bottom Feed DC Distribution)

Emerson 582145500 — 4.4.8 Battery Connections diagram (page 39)
Fig. 24 · 4.4.8 Battery Connections

Hardware Build-Up M10 Nut (electro zinc treatment with bright chromate)

M10 Belleville Lock Washer DIN 6796-10.5 STEEL (electro zinc treatment with bright chromate)

Hardware Build-Up M10 x 30mm Bolt (electro zinc treatment with bright chromate)

M10 Belleville Lock Washer DIN 6796-10.5 STEEL (electro zinc treatment with bright chromate)

Battery Compartment and Base Removed in Illustrations for Clarity

-48Vdc Interconnect Busbar (can be installed on left and/or

Page 40 of the Emerson 582145500 user manual — 4.4.8 Battery Connections
Page 40 · click to enlarge
Page 40

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 21 Module-Module Interconnect Busbars (DC UPS Module with Top Feed DC Distribution)

Emerson 582145500 — 4.4.8 Battery Connections diagram (page 40)
Fig. 25 · 4.4.8 Battery Connections

Hardware Build-Up M10 Nut (electro zinc treatment with bright chromate)

M10 Belleville Lock Washer DIN 6796-10.5 STEEL (electro zinc treatment with bright chromate)

Hardware Build-Up M10 x 30mm Bolt (electro zinc treatment with bright chromate)

M10 Belleville Lock Washer DIN 6796-10.5 STEEL (electro zinc treatment with bright chromate)

Battery Compartment and Base Removed in Illustrations for Clarity

Ground/Return Interconnect Busbar (can be installed on left and/or right side of module)

-48Vdc Interconnect Busbar (can be installed on left and/or right side of module)

Page 41 of the Emerson 582145500 user manual — 4.6.2 CAN-Bus Module-to-Module Interconnect
Page 41 · click to enlarge
Page 41

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4.6 Making Alarm/Control Interconnections between Modules (if system consists of multiple DC UPS modules)

Make the following module-to-module alarm/control interconnections as required. Refer to Figure 23 for an interconnect diagram. See also the Cabinet Interconnections illustration in Figure 24, Figure 25, and Figure 26.

4.6.1 RS-485 Module-to-Module Interconnect

Primary Module to 1st Expansion Module (Skip if No 1st Expansion Module) 1. Locate the long RS-485 interconnect cable (RPM 628 415/2) (yellow/white wire twisted pair) coiled up on the right side of the Primary Module. 2. Route this cable through the openings in the sides of the cabinets to the 1st Expansion Module. 3. Connect this cable to the mating RS-485 interconnect cable connected to the SM-AC located in the 1st Expansion Module (yellow/white wire twisted pair).

1st Expansion Module to 2nd Expansion Module (Skip if No Additional Expansion Module) 1. Locate the long RS-485 interconnect cable (RPM 628 415/2) (yellow/white wire twisted pair) coiled up on the right side of the 1st Expansion Module. 2. Route this cable through the openings in the sides of the cabinets to the 2nd Expansion Module. 3. Connect this cable to the mating RS-485 interconnect cable connected to the SM-AC located in the 2nd Expansion Module (yellow/white wire twisted pair).

Additional Expansion Modules (Skip if No Additional Expansion Module) 1. Make similar connections between each adjacent Expansion Module.

SM-BRC RS-485 Termination Resistor Setting in Last DC UPS Module 1. A jumper on the SM-BRC circuit board is used for selecting a termination resistor for the RS-485 connection. RS-485 termination is disabled when the jumper is across pins 1 and 2 (default). It is enabled when the jumper is across pins 2 and 3. See Figure 22 for the location of the jumper.

In most cases, RS-485 termination is not necessary because maximum baud rate is 19200 bps (default is 9600). RS-485 termination is recommended when intermittent communications occur.

If there are intermittent communications errors, it is recommended to set the termination resistor on the SM-BRC in the last module to the enabled position (jumper between pins 2 and 3) instead of the factory disabled position (jumper between pins 1 and 2).

Figure 22 SM-BRC RS-485 Jumper Locations

Emerson 582145500 — 4.6.1 RS-485 Module-to-Module Interconnect diagram (page 41)
Fig. 26 · 4.6.1 RS-485 Module-to-Module Interconnect

4.6.2 CAN-Bus Module-to-Module Interconnect

CAN-Bus End Resistor (move only if more than one DC UPS module) 1. Locate the short CAN-Bus interconnect cable jumper connected to the SM-DU+ in the Primary Module (black/white wire twisted pair located behind the SM-DU+ sheetmetal enclosure and

Page 42 of the Emerson 582145500 user manual — 4.6.3 BLVD Module-to-Module Interconnect
Page 42 · click to enlarge
Page 42

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

exiting the top of the SM-DU+). Remove the CAN-Bus End Resistor plugged into this cable only if there are Expansion Modules. 2. Locate the short CAN-Bus interconnect cable jumper connected to the SM-DU in the last (end) Expansion Module (black/white wire twisted pair located behind the SM-DU sheetmetal enclosure). Plug the CAN-Bus End Resistor into this cable.

1st Expansion Module to Primary Module 1. Locate the long CAN-Bus interconnect cable (RPM 628 351/1) coiled up on the right side of the 1st Expansion Module (black/white wire twisted pair). 2. Route this cable through the openings in the sides of the cabinets to the Primary Module. 3. Route this cable through the top lip of the Primary Module’s SM-DU+ sheetmetal enclosure. 4. Connect this cable to the mating CAN-Bus interconnect cable connected to the SM-DU+ in the Primary Module (black/white wire twisted pair located behind the SM-DU+ sheetmetal enclosure and exiting the top of the SM-DU+).

2nd Expansion Module to 1st Expansion Module 1. Locate the long CAN-Bus interconnect cable (RPM 628 351/1) coiled up on the right side of the 2nd Expansion Module (black/white wire twisted pair). 2. Route this cable through the openings in the sides of the cabinets to the 1st Expansion Module. 3. Connect this cable to the mating CAN-Bus interconnect cable connected to the SM-DU in the 1st Expansion Module (black/white wire twisted pair located behind the SM-DU sheetmetal enclosure).

Additional Expansion Modules 1. Make similar connections between each remaining Expansion Module.

4.6.3 BLVD Module-to-Module Interconnect

1st Expansion Module to Primary Module 1. Locate the BLVD control interconnect cable (RPM 628 466/3) coiled up on the right side of the 1st Expansion Module (the Expansion Module’s BLVD cable is factory connected to the bottom connector on the LVD Relay Board, and exits at the back of the LVD Relay Board’s sheetmetal enclosure). 2. Route this cable through the openings in the sides of the cabinets to the Primary Module. 3. Route the cable through the back of the Primary Module’s LVD Relay Board sheetmetal enclosure. 4. Connect this cable to the mating BLVD control interconnect cable (RPM 628 465/3) in the Primary Module (the Primary Module’s BLVD cable is factory connected to the bottom connector located on the LVD Relay Board).

2nd Expansion Module to 1st Expansion Module 1. Locate the BLVD control interconnect cable (RPM 628 466/3) coiled up on the right side of the 2nd Expansion Module (the Expansion Module’s BLVD cable is factory connected to the bottom connector on the LVD Relay Board, and exits at the back of the LVD Relay Board’s sheetmetal enclosure). 2. Route this cable through the openings in the sides of the cabinets to the 1st Expansion Module. 3. Route the cable through the back of the 1st Expansion Module’s LVD Relay Board sheetmetal enclosure. 4. Connect this cable to the mating BLVD control interconnect cable (RPM 628 465/3) in the 1st Expansion Module (the 1st Expansion Module’s BLVD cable is factory connected to the bottom connector located on the LVD Relay Board).

Additional Expansion Modules 1. Make similar connections between each remaining Expansion Module.

Page 43 of the Emerson 582145500 user manual — 4.6.3 BLVD Module-to-Module Interconnect
Page 43 · click to enlarge
Page 43

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 23 Alarm/Control Cable Interconnects (cont’d on next page)

Emerson 582145500 — 4.6.3 BLVD Module-to-Module Interconnect diagram (page 43)
Fig. 27 · 4.6.3 BLVD Module-to-Module Interconnect

(RPM 628 351/1) located coiled up on right side of Expansion Module cabinet (mating connector located behind Detail A cover)

(RPM 628 415/2) located coiled up on right side of

BLVD Control Cable (RPM 628 466/3) located coiled up on right side of Expansion Module cabinets

LVD Relay Board Can-Bus End Resistor (if no Expansion Module)

Page 44 of the Emerson 582145500 user manual — 4.6.3 BLVD Module-to-Module Interconnect
Page 44 · click to enlarge
Page 44

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 23 Alarm/Control Cable Interconnects (cont’d from previous page)

Emerson 582145500 — 4.6.3 BLVD Module-to-Module Interconnect diagram (page 44)
Fig. 28 · 4.6.3 BLVD Module-to-Module Interconnect

(RPM 628 351/1) located coiled up on right side of 2nd Expansion Module cabinet (mating connector located on SM-DU)

(RPM 628 415/2) located coiled up on right side of 1st Expansion Module cabinet (mating connector located on SM-AC)

BLVD Control Cable (RPM 628 466/3) located coiled up on right side of Expansion Module cabinets

Can-Bus End Resistor (moved from Primary Module to last Expansion Module)

Page 45 of the Emerson 582145500 user manual — 4.6.3 BLVD Module-to-Module Interconnect
Page 45 · click to enlarge
Page 45

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 24 System Configuration and Communications Connections

Emerson 582145500 — 4.6.3 BLVD Module-to-Module Interconnect diagram (page 45)
Fig. 29 · 4.6.3 BLVD Module-to-Module Interconnect
Page 46 of the Emerson 582145500 user manual — 4.6.3 BLVD Module-to-Module Interconnect
Page 46 · click to enlarge
Page 46

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 25 Cabinet Interconnections

Emerson 582145500 — 4.6.3 BLVD Module-to-Module Interconnect diagram (page 46)
Fig. 30 · 4.6.3 BLVD Module-to-Module Interconnect
Page 47 of the Emerson 582145500 user manual — 4.6.3 BLVD Module-to-Module Interconnect
Page 47 · click to enlarge
Page 47

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 26 Signal Cabling and Switch Settings

Emerson 582145500 — 4.6.3 BLVD Module-to-Module Interconnect diagram (page 47)
Fig. 31 · 4.6.3 BLVD Module-to-Module Interconnect
Page 48 of the Emerson 582145500 user manual — 5.0 I NSTALLING PCU S
Page 48 · click to enlarge
Page 48

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

5.0 I NSTALLING PCU S

Emerson 582145500 — 5.0 I NSTALLING PCU S diagram (page 48)
Fig. 32

! WARNING In order to prevent damage to the latching mechanism, do not use excessive force on the PCU handle when pushing the PCU into the cabinet.

PCUs are hot swappable. They can be installed with the system operating.

Procedure 1. Place the PCU into an unoccupied mounting position without sliding it in completely. 2. Push the “Safety Latch Release” located on the front of the PCU "UP". Refer to Figure 27 for an illustration. 3. Gently push the PCU into the mounting location until it stops. 4. Note that the PCU will NOT be completely seated in the mounting location until the next step is performed. 5. Push the “Safety Latch Release” located on the front of the PCU "DOWN". Gently push the PCU into the mounting location until it is completely seated. 6. Push the PCU’s handle in and secure the PCU to the cabinet by tightening the captive fastener located on the handle. 7. Repeat the above steps for each PCU being installed in the DC UPS module. 8. After the PCUs are physically installed, they are ready for operation immediately after power is supplied to them.

Figure 27 PCU Handle and Safety Latch

Emerson 582145500 — 5.0 I NSTALLING PCU S diagram (page 48)
Fig. 33
Page 49 of the Emerson 582145500 user manual — 6.2.3 Connecting Batteries
Page 49 · click to enlarge
Page 49

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

6.0 S TART -U P I NSTRUCTIONS

6.1 General

The NetSure ITM DC UPS system must be fully installed and commissioned before startup. The start-up procedure consists of making final battery connections, initially starting the system, and verifying system operation. Emerson Network Power will perform ALL start-up procedures, including making final battery connections.

THE FOLLOWING ARE GENERAL GUIDELINES FOR EMERSON TECHNICIANS.

6.2 Final Battery Connections

6.2.1 Introduction

Each DC UPS module contains a battery compartment. The battery compartment consists of six battery shelves that house (4) 6V batteries, each. Batteries are factory installed and wired for (3) -48VDC battery strings. Also provided is a 800A battery disconnect fuse for each string.

6.2.2 Safety

Special care should be taken when working with the batteries associated with the DC UPS module. See the precautions in the battery instruction manual and in Battery Compartment Precautions at the beginning of these instructions.

6.2.3 Connecting Batteries

Battery Leads The batteries are factory installed and most battery interconnections are factory made. The following interconnections need to made during installation to complete the battery electrical path to the DC UPS module. Refer to Figure 28 for the battery connections torque value for the Emerson EB4 6V200 battery. 1. Refer to Figure 28 and connect the supplied Battery Interconnect Links between the indicated Battery Shelves. For each connection: a. Install the faston lugs on top of the battery links as shown in Figure 28. Note that battery monitoring leads are factory connected to the faston lugs and each faston lug is insulated for shipping. Observe proper polarity when attaching the faston lugs with factory wiring to the battery posts. b. Tighten the connections to the torque indicated in Figure 28. c. Place the plastic cover over the battery terminals and interconnect link. 2. On all remaining battery terminals (factory connections); remove the plastic covers, check the torque, then reinstall the plastic covers. Torque to value indicated in Figure 28.

DO NOT INSTALL THE BATTERY FUSES BEFORE THE EQUIPMENT HAS BEEN COMMISSIONED AND THE PROCEDURE IN "6.3.1 - Initially Starting the DC UPS System and Verifying System Operation" IS PERFORMED.

Page 50 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 50 · click to enlarge
Page 50

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Figure 28 Making Final Battery Shelf Battery Interconnect Link Connections

Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 50)
Fig. 34 · 6.0 Start-Up Instructions

Lead Labeled 1.5+ (Battery One Link) 2.5+ (Battery Two Link) 3.5+ (Battery Three Link)

1. Connect supplied Battery Interconnect Links between these points.
2. Place faston lugs with factory wired battery monitoring leads on top of interconnect link as shown in illustration. DO NOT PLACE BETWEEN LINK AND BATTERY TERMINALS.
4. Place plastic cover over battery terminals and interconnect links.
6. On all remaining battery terminals (factory connections); remove the plastic covers, check the torque, then reinstall the plastic covers.
Page 51 of the Emerson 582145500 user manual — Perform InterCell Resistance Calibration
Page 51 · click to enlarge
Page 51

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Perform InterCell Resistance Calibration

Use the Alber software to run an Intercell Resistance test.

1. After making final battery connections and before installing battery fuses, perform the following: a. Disconnect the RS-485 cable from the back of the SM-BRC. b. Connect the USB cable from the SM-BRC to your computer. c. Start the ALBER Configurator. 2. Click on the "Connect to Monitor" button at the top of the screen.
Emerson 582145500 — Perform InterCell Resistance Calibration diagram (page 51)
Fig. 35 · Perform InterCell Resistance Calibration
Page 52 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 52 · click to enlarge
Page 52

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

3. Select "USB" as the Connection Type and click on "Connect to Monitor" at lower right.
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 52)
Fig. 36 · 6.0 Start-Up Instructions
Page 53 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 53 · click to enlarge
Page 53

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

4. Click "Setup" on the menu tree found at the left of the window.
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 53)
Fig. 37 · 6.0 Start-Up Instructions
Page 54 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 54 · click to enlarge
Page 54

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

5. Select the "General Tab" and fill in the following: a. System Configuration (String x Cells x Voltages): 3x8x6V. (note that this is a pull down selection) b. RS-485/Module Address (1-254). For ITM Module 1, set to 120. For ITM Module 2, set to 121. For ITM Module 3, set to 122. For ITM Module 4, set to 123. c. RS-485 Baud Rate: 19200 bps. (note that this is a pull down selection) 6. Press "Apply".
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 54)
Fig. 38 · 6.0 Start-Up Instructions
Page 55 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 55 · click to enlarge
Page 55

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7. Click"OK" in the pop-up window.
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 55)
Fig. 39 · 6.0 Start-Up Instructions
Page 56 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 56 · click to enlarge
Page 56

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

8. Select "Real-Time Data" in the menu tree at the left. 9. Click on the "Internal R" tab at top of screen. 10. Check the box "Set baseline" and click on the "Start" button.
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 56)
Fig. 40 · 6.0 Start-Up Instructions
Page 57 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 57 · click to enlarge
Page 57

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

11. Click on "Yes" in the pop-up window.
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 57)
Fig. 41 · 6.0 Start-Up Instructions
Page 58 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 58 · click to enlarge
Page 58

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

12. The unit will start calibration. One at a time each green bar will appear for each battery block.
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 58)
Fig. 42 · 6.0 Start-Up Instructions
Page 59 of the Emerson 582145500 user manual — 6.0 Start-Up Instructions
Page 59 · click to enlarge
Page 59

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

13. When the last green bar appears, a pop-up will appear indicating that the test is done. Click "OK".
Emerson 582145500 — 6.0 Start-Up Instructions diagram (page 59)
Fig. 43 · 6.0 Start-Up Instructions
14. Select "Disconnect from Monitor" at the top of the screen. 15. Remove the USB cable from your computer and re-install the RS-485 cable into the SM-BRC.
Page 60 of the Emerson 582145500 user manual — 6.3 Initially Starting and Verifying DC UPS System Operation
Page 60 · click to enlarge
Page 60

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Field Battery Monitoring Lead Connections to the SM-BRC Unit

Battery monitoring leads are factory connected to the mating halves of the SM-BRC unit’s Load Inputs terminal blocks labeled 1, 3, 5, 7 and 2, 4, 6, 8. The DC UPS module is factory shipped with the mating halves of the SM-BRC’s Load Inputs terminal blocks labeled 1, 3, 5, 7 and 2, 4, 6, 8 disconnected. This is to prevent the batteries from discharging when the system is not powered.

When the DC UPS module is to be placed into service, open the battery compartment’s top rear access panel. Locate the disconnected connectors labeled "Load Inputs 1, 3, 5, 7" and "Load Inputs 2, 4, 6, 8". Plug these connectors into the back of the SM-BRC, as shown in Figure 29. Repeat this procedure for each DC UPS module in the system.

Figure 29 Field Battery Monitoring Lead Connections to the SM-BRC Unit

Emerson 582145500 — Field Battery Monitoring Lead Connections to the SM-BRC Unit diagram (page 60)
Fig. 44 · Field Battery Monitoring Lead Connections to the SM-…

The DC UPS module is factory shipped with the mating halves of the SM-BRC’s Load Inputs terminal blocks 1, 3, 5, 7 and 2, 4, 6, 8 disconnected. When ready to place the module into service, locate and plug the mating halves of the SM-BRC’s Load Inputs terminal blocks 1, 3, 5, 7 and 2, 4, 6, 8 here.

6.3 Initially Starting and Verifying DC UPS System Operation

! WARNING During this procedure the output terminals will become live.

If any load equipment is connected to the DC UPS module output terminals, please check with the load user and ascertain whether it is safe to apply power to the load. If the load is not ready to receive power, then ensure that it is safely isolated from the DC UPS module output terminals.

Page 61 of the Emerson 582145500 user manual — 6.3.2 Setting Common Controller Parameters
Page 61 · click to enlarge
Page 61

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

6.3.1 Initially Starting the DC UPS System and Verifying System Operation

The NetSure ITM DC UPS must be fully installed and commissioned before startup.

Procedure 1. Open the front door on each DC UPS module. 2. Apply AC input power to each DC UPS module by closing the external AC disconnect(s) or protective device(s) that supplies power to each DC UPS module. If the dual AC input feed option is furnished, there will be two (2) devices per DC UPS module. 3. On each DC UPS module, close the main AC input circuit breaker. If the dual AC input feed option is furnished, a safety latch is provided on the circuit breakers to prevent both circuit breakers from being placed in the ON position. Slide the latch over to allow the desired circuit breaker to be turned ON. 4. On each DC UPS module, close all PCU AC input circuit breakers. Note that each circuit breaker feeds two (2) PCUs. 5. In the Primary DC UPS module, once the ACU+ Controller is powered on, a starting... screen appears followed by a language screen.

Press “” or “” to select the desired language. Press ENT to confirm the selection. If no key is pressed within 30 seconds, the ACU+ Controller automatically selects the displayed language. Refer to the NetSure ITM Operation Manual (Section 6047) for ACU+ Controller local menu operating instructions. Once initialized, the ACU+ Main Screen displays.

Main Screen Main Menu

09:20:20 Float

ENT

MAIN MENU

Press or to browse through MAIN MENU.

Status Settings Energy Saving Manual CustomizeMenu

53.4V 404A

ESC

Press ENT to enter Sub-Menu.

6. With an external meter, measure battery voltage. 7. Adjust the system’s float voltage to within approximately 0.5V of battery voltage. 8. In each DC UPS module, install the three battery disconnect fuses. 9. Adjust the system’s float voltage to 54.5Vdc. 10. In each DC UPS module, place each distribution circuit breaker to the ON position or install all distribution fuses. 11. In the Primary DC UPS module, verify that there are no alarms present on the ACU+ local display.

6.3.2 Setting Common Controller Parameters

Navigate through the controller menus and submenus to set common controller parameters (time, date, IP address, etc.). Refer to Section 3.5 of the NetSure ITM Operation Manual (Section 6047) for common tasks performed locally.

English · Auto NoAlarm

Page 62 of the Emerson 582145500 user manual — 6.3.3 Changing the Numbering Scheme of the PCUs
Page 62 · click to enlarge
Page 62

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

6.3.3 Changing the Numbering Scheme of the PCUs

Follow these procedures to change how the ACU+ identifies (numbers) the PCUs installed in the system. These procedures are performed from the ACU+ Controller’s local display and keypad.

Initial Installation (numbering the PCUs per their Physical Location in the System) 1. Go to Main Menu / Settings / PCU. 2. Press Enter. 3. Navigate down to PCU 1 (001). 4. Press Enter. 5. Look for the PCU installed in the system with a flashing LED. 6. Press Enter. 7. Press the Up or Down Arrow until the number displayed is the same as the physical position of the PCU with the flashing LED. 8. Press Enter. 9. Press ESC. 10. Navigate down to the next PCU and repeat steps 4 thru 10. 11. After all PCUs are renumbered, go to Main Menu / Control / PCU / All PCU Ctrl. 12. Press Enter. 13. Navigate down to Confirm Posi/PH. 14. Select Yes, then press Enter. 15. Verify that the ACU+ now numbers the PCUs via their physical position in the system by going to Main Menu / Status / PCU and scrolling down to each PCU listed in the display. Compare the PCU number highlighted in the display with the physical position of the PCU with the flashing LED.

Swapping PCUs Physical Positions without Adding or Removing the Number of PCUs 1. If you swap PCUs, the ACU+ numbering stays with the PCUs. For example, if PCU in physical position 1 is swapped with PCU in physical position 2, the ACU+ numbers the PCU now installed in physical position 1 as 2 and the PCU now installed in physical position 2 as 1. To correct this, repeat the steps shown in the "Initial Installation" procedure for ONLY the two PCUs that were swapped.

Removing a PCU without Replacing It 1. Remove the PCU. 2. Go to Main Menu / Control / PCU / All PCU Ctrl. 3. Press Enter. 4. Navigate down to Confirm Posi/PH. 5. Select Yes, then press Enter. 6. Now, when you view the voltage and current for the removed PCU, the fields will be highlighted in BLACK to indicate this PCU is not present. Also, the WEB interface shows that PCU information GREYED out. 7. If you now re-install that same PCU in it's previous physical position, it will retain its previous slot number.

Replacing a Previously Installed PCU with a New PCU 1. Remove a previously installed PCU. 2. Clear the PCU Lost Alarm. 3. Install the new PCU. 4. The new PCU is automatically assigned the same numbering as the original PCU it replaced.

Page 63 of the Emerson 582145500 user manual — 7.3 Mechanical Characteristics
Page 63 · click to enlarge
Page 63

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.0 S PECIFICATIONS AND T ECHNICAL D ATA

7.1 Agency Approvals

The NetSure ITM DC UPS system has the following agency approval ratings:

  • EN 60 950-1:2006
  • UL 60 950-1
  • UL 1801 (This unit is UL Listed ["c UL"] as a DC Power Distribution Center. This unit meets the requirements of CSA 22.2, No. 225 and is tested and Certified by UL ["c UL"] as a Custom Built Power Distribution Center.)

7.2 Environmental

The NetSure ITM DC UPS system is designed to operate under the following environmental conditions without damage or degradation in electrical operating characteristics:

Table 7 DC UPS System Environmental Characteristics

+23°F to +95°F (-5°C to +35°C) Recommended Operation with Battery (Air Inlet): +68°F to +77°F (+20°C to +25°C)

System Storage Temperature (optimal) -4°F to +77°F (-20°C to +25°C)

Relative Humidity 0 to 95%, non-condensing

Operating Elevation 6562 ft (2000m) at full power

Audible Noise < 60dB

Heat Rejection at Full Load 18,096 BTU/hr. (5.3kW) per module

EMI FCC Class A

7.3 Mechanical Characteristics

Table 8 DC UPS System Mechanical Characteristics (per module)

Unit Dimensions Inches83H x 24W x 41D (Millimeters: 2100H x 600W x 1040D)

Unit Weight 3240 lb (1470 kg)

Airflow 560 CFM (950 m3/h)

Cable Entry Bottom or Top

Protection Grade (with open/closed front doors) IP 20

System Operating Temperature · Form Factor Rack · Color Black (Z-0350)

Page 64 of the Emerson 582145500 user manual — 7.4 Monitoring Capability
Page 64 · click to enlarge
Page 64

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Table 9 Shipping Dimensions and Weights

Size 70KW 140KW 210KW 280KW

(1) Module:

(2) Modules, per module: Inches: 92H x 29W x 47D Millimeters: 2337H x 737W x 1194D Weight: 3307lb (1500kg)

(3) Modules, per module: Inches: 92H x 29W x 47D Millimeters: 2337H x 737W x 1194D Weight: 3307lb (1500kg)

(4) Modules, per module: Inches: 92H x 29W x 47D Millimeters: 2337H x 737W x 1194D Weight: 3307lb (1500kg)

Inches92H x 29W x 47D Millimeters: 2337H x 737W x 1194D Weight: 3307lb (1500kg)

PCUs 12 PCUs: Pallet (12 PCUs): Inches: 22H x 44W x 48D Millimeters: 559H x 1118W x 1219D Weight: 258lb (117kg)

24 PCUs: Pallet (24 PCUs): Inches: 38H x 44W x 48D Millimeters: 965H x 1118W x 1219D Weight: 486lb (220kg)

36 PCUs: 1st Pallet (30 PCUs): Inches: 46H x 44W x 48D Millimeters: 1168H x 1118W x 1219D Weight: 600lb (272kg)

48 PCUs: 1st Pallet (30 PCUs): Inches: 46H x 44W x 48D Millimeters: 1168H x 1118W x 1219D Weight: 600lb (272kg)

2nd Pallet (6 PCUs): Inches: 14H x 44W x 48D Millimeters: 356H x 1118W x 1219D Weight: 144lb (65kg)

2nd Pallet (18 PCUs): Inches: 30H x 44W x 48D Millimeters: 762H x 1118W x 1219D Weight: 372lb (169kg)

7.4 Monitoring Capability

Standard: Web-based monitoring, alarm reporting via SNMP, and integration with Liebert SiteScan via SiteLink-E module.

Optional: Energy Master Remote Supervision available from Emerson.

System · Module · w/ Batteries

Page 65 of the Emerson 582145500 user manual — 3/8" (M10) 6 AWG 54136
Page 65 · click to enlarge
Page 65

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.5 Electrical Characteristics

7.5.1 Termination Type, Recommended Wire Size, Recommended Lugs

AC Input

Table 10 AC Input and AC Input Grounding (per DC UPS module)

Recm.

Wire Size1 Conduit Size

Screw Clamp 2/0 AWG 2" 400Vac 110A

Recommended Lug (Thomas & Betts P/N)

Recm.

Compression 1-Hole; 3/8" Bolt

480Vac 5/16" (M8) 1/0 AWG 2" 54109 400Vac

1 Wire sizes based on recommendations of the American National Standards Institute (ANSI) approved National Fire Protection Association's (NFPA) National Electrical Code (NEC). Table 310-16 for copper wire at 90°C conductor temperature operating in ambient of 35°C was used. For other operating ambient temperatures, refer to the NEC. For operation in countries where the NEC is not recognized, follow applicable codes.

Equipment grounding conductors must be provided with the AC input conductors supplied to the module. Frame ground terminals must be connected to earth ground, not power system neutral. Equipment grounding conductor size based on recommendations of the NEC Table 250-122 for copper wire. When aluminum or copper clad aluminum grounding conductor is used, refer to Table 250 122 for increased conductor size. For operation in countries where the NEC is not recognized, follow applicable codes.

Cabinet Frame Grounding

Table 11 Cabinet Frame Grounding (per DC UPS module)

Recommended Lug (Thomas & Betts P/N)

Recm.

Compression 1-Hole; 3/8" Bolt

3/8" (M10) 6 AWG 54136

Show 17 more labels / short text on this page
AC Input · Input Voltage · Maximum · Terminal · Input Current · Type · 480Vac 92A · 380Vac 116A · AC Input Grounding · Input Voltage · Bolt Size · Conduit · Wire Size1 · Size · Bolt Size · Wire · Size
Page 66 of the Emerson 582145500 user manual — Battery
Page 66 · click to enlarge
Page 66

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

DC Distribution

Table 12 DC Distribution (Distribution Circuit Breaker Option - per circuit breaker position)

Recm. Wire Size1 Lug Requirement Recommended Lug (Thomas & Betts P/N)

@ 54V

1/0 AWG 2-Hole, 1" Centers 54209

1/0 AWG 2-Hole, 1" Centers 54209

3/8" (M10)

2/0 AWG 2-Hole, 1" Centers 54210

3/0 AWG 2-Hole, 1" Centers 54211

1 Wire sizes based on recommendations of the American National Standards Institute (ANSI) approved National Fire Protection Association's (NFPA) National Electrical Code (NEC). Table 310-16 for copper wire at 75°C conductor temperature operating in ambient of 35°C was used. For other operating ambient temperatures, refer to the NEC. For operation in countries where the NEC is not recognized, follow applicable codes. Sizes assume one layer of cables in open cable tray. Alternate sizing may be required for other installation configurations. Refer to the NEC or contact Emerson Services (contact information provided at the end of this document).

Table 13 DC Distribution (Distribution Fuse Option - per fuse position)

Recm. Wire Size1 Lug Requirement Recommended Lug (Thomas & Betts P/N)

@ 54V

3/0 AWG

1/2" (M12)

2-Hole, 1.75" Centers

(2) 250 kcmil (2) 54275 Return

1 Wire sizes based on recommendations of the American National Standards Institute (ANSI) approved National Fire Protection Association's (NFPA) National Electrical Code (NEC). Table 310-16 for copper wire at 75°C conductor temperature operating in ambient of 35°C was used. For other operating ambient temperatures, refer to the NEC. For operation in countries where the NEC is not recognized, follow applicable codes. Sizes assume one layer of cables in open cable tray. Alternate sizing may be required for other installation configurations. Refer to the NEC or contact Emerson Services (contact information provided at the end of this document).

Battery

The battery cables are factory provided and sized accordingly.

Show 19 more labels / short text on this page
Maximum · OCP Device Rating · Output Current · Terminal Bolt Size · 100A 80A Load · Return 1-Hole 54109 · 150A 120A Load · Return 1-Hole 54109 · 175A 140A Load · Return 1-Hole 54110 · 200A 160A Load · Return 1-Hole 54111 · Maximum · OCP Device Rating · Output Current · Terminal Bolt Size · 200 160 Load · 54265 Return · 500 400 Load
Page 67 of the Emerson 582145500 user manual — 7.5.3 AC Input Specifications
Page 67 · click to enlarge
Page 67

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Alarm/Control

Screw Size Recm. Wire Size

M2 24-16 AWG

7.5.2 Power Ratings

Table 15 Power Ratings

Full 70 kW 70 kW 70 kW 70 kW

N + 1 64 kW 70 kW 70 kW 70 kW

7.5.3 AC Input Specifications

Table 16 AC Input Specifications

Power Factor 0.99 at full load, 0.98 at 50% load

Input Voltage – Nominal 400 / 480V, 3 wire + ground

Input Voltage – Range 304-530 VAC; shall withstand up to 600 VAC input without damage.

Internal AC Input Breaker Size 150A

Internal AC Input Breaker AIC Rating 65,000A

Nominal 480V: 115A @ 384V; 92A @ 480V Nominal 400V: 138A @ 320V; 110A @ 400V Nominal 380V: 145A @ 304V; 116A @ 380V

Max Input Current / Module

Inrush Current Inrush current does not exceed 150% of the

rated input steady state peak value.

Total Harmonic Distortion

Show 11 more labels / short text on this page
Table 14 Alarm/Control · Power Rating · Primary Module 1 · Expansion · Expansion · Expansion · Module 2 · Module 3 · Module 4 · Phase 3 · Frequency 45-65 Hz
Page 68 of the Emerson 582145500 user manual — Hold Up Time
Page 68 · click to enlarge
Page 68

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.5.4 DC Output Specifications

Table 17 DC Output Specifications

Normal Operation-54.5 VDC (battery float)
Nominal-48VDC Range: -42 to -58 VDC

96% peak (system level including branch distribution losses).

See Figure 30.

Energy Optimization Mode; Intelligent Power Matching

Allows operation at near-peak efficiency

down to 5% overall load.

Distribution Types 22 Circuit Breakers, 100-200A each; Optional: 6 Fuses, 100-500A each

Figure 30 System Efficiency Curve

Emerson 582145500 — 7.5.4 DC Output Specifications diagram (page 68)
Fig. 45 · 7.5.4 DC Output Specifications

Regulation (PCU)

  • a. Voltage Regulation: ±1%. b. Load Regulation: ±0.5%. c. Line Regulation: ±0.1%. d. Overshoot at Startup: ±1%. e. Dynamic Response (at rated input and output voltage values):
  • Response time is 200 µ s, and the overshoot is 5% for load changes at 50%-25%-50% and 50%- 75%-50%.
  • Overshoot or undershoot is 5% and within ±1% of the regulation band, 4 ms at 50 µ s for load changes at 10%-90% and 90%-10%.

Filtering

Typical readings were taken at nominal input voltage, nominal output voltage, 50% load, and 25 degrees C ambient.

a. Wide Band Noise: Complies with Telcordia GR-947-CORE. 1. Typically 55 millivolts peak-to-peak. Does not exceed 200 millivolts peak-to-peak 2. Typically 15.9 millivolts rms. Does not exceed 100 millivolts rms.

Hold Up Time

10 ms (The DC voltage is allowed to decrease to 42V from 54V during the test.)

Voltage · System Efficiency

Page 69 of the Emerson 582145500 user manual — CAPACITY
Page 69 · click to enlarge
Page 69

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.5.5 Battery Specifications

Table 18 Battery Specifications

Type VRLA, Emerson Excellence EB4, 200 Ah

Arrangement 3 strings; eight 6V blocks per string

Per 6V Block Per 70 kW Module

Capacity - Ah 200 4800

Acid Weight - lb. (kg) 14.9 (6.7) 357.6 (160.8)

Total Acid Volume - gal. (L) 0.97 (3.67) 23.2 (87.8)

Free Acid Volume - gal. (L) 0.1 (0.37) 0.23 (0.88)

Lead Weight - lb. (kg) 54.7 (24.8) 1312.8 (595.2)

Total Weight - lb. (kg) 77.2 (35.0) 1852.8 (840)

Backup Time See backup time table at various loads.

Case Material UL94-HB or UL94-V0

Design Life 15 years @ 68°F (20°C); 10 years @ 77°F (25°C)

Recharge Time (to 97% of nominal capacity)

Less than 3 hours for > 35% load; Less than 4 hours > 15% load.

MECHANICAL

Dimensions DepthWidth: Height:

377 mm, including connectors and covers 135 mm, including ventilation spacing 250 mm

CAPACITY

Constant Power Discharge @ 20°C (w/cell):

End Voltage Operating Time To End Voltage (minutes)

Per Cell 600 480 360 300 240 180 120 60

Constant Current Discharge @ 20°C (A):

End Voltage Operating Time To End Voltage (minutes)

Per Cell 600 480 360 300 240 180 120 60

  • OTHER TECHNICAL FEATURES
  • Valve-regulated lead-acid battery with AGM technology.
  • Validation in accordance with IEC 896-2.

(24 blocks)

Page 70 of the Emerson 582145500 user manual — 7.5.5 Battery Specifications
Page 70 · click to enlarge
Page 70

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Emerson 582145500 — 7.5.5 Battery Specifications diagram (page 70)
Fig. 46 · 7.5.5 Battery Specifications

280kW 10kW 130 300 480 630 20kW 55 130 210 300 30kW 28 90 130 180 40kW 17 55 90 130 50kW 12 41 70 100 64kW 7 24 50 75 70kW 3 21 43 69 80kW 17 34 55 90kW 14 27 47 100kW 12 22 40 110kW 10 19 34 120kW 8 17 28 134kW 6 16 25 140kW 3 14 22 150kW 12 19 160kW 10 17 170kW 9 15 180kW 8 14 190kW 7 13 204kW 4 11 210kW 2 10 220kW 9 230kW 9 240kW 8 250kW 7 260kW 6 274kW 3 280kW 1

Page 71 of the Emerson 582145500 user manual — 7.5.7 SM-DU+
Page 71 · click to enlarge
Page 71

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.5.6 Advanced Control Unit Plus (ACU+) Controller

Display LCD with 4 × 16 Characters

Communication RS232, RS485, Ethernet, USB

Protocol HTTP, SNMP, EEM, SocTpe, RSoc

Local Indicators Green LED: Illuminates when CPU is working correctly. Red LED: Illuminates when there is a critical or warning alarm. Yellow LED: Illuminates when there is an information alarm.

System Output Voltage Battery Voltage Battery Temperature Ambient Temperature Battery Shunt (for Battery Current)

3 Battery Fuses 2 DC Distribution Fuses 8 Generic Digital Inputs (where D15 reserved for "Fan CB Tripped" and D16 for "Fan Alarm") 1 Contactor Status

DC Power Plant Alarms AC Mains Failure, PCU Failure, High Voltage Shutdown, Fan Failure, Thermal Derating (of PCU output due to high temperature)

Monitoring Capability SNMP/Web Based Monitoring Included; Compatibility with SiteScan Available

EnergyMaster Remote Monitoring (contact your Emerson Representative)

7.5.7 SM-DU+

Communication RS485, CAN, RS232

Local Indicators Green LED: Illuminates when CPU is working correctly. Flashes (1/3Hz) to indicate communication fault with controller. Flashes (1Hz) to indicate communicating with controller. Red LED: Illuminates when there is a critical or warning alarm. Yellow LED: Illuminates when there is an information alarm.

Inputs 22 Current Measurements 22 DC Fuse/Breaker Status Detection

Show 6 more labels / short text on this page
Inputs · 5 Analog Inputs · 14 Digital Inputs · Outputs · 1 Output · Contactor Control
Page 72 of the Emerson 582145500 user manual — 24VDC / 250VAC, 5A
Page 72 · click to enlarge
Page 72

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.5.8 SM-DU (used in Expansion Modules only in place of Controller)

Communication RS485, CAN, RS232

Local Indicators Green LED: Illuminates when CPU is working correctly. Flashes (1/3Hz) to indicate communication fault with controller. Flashes (1Hz) to indicate communicating with controller. Red LED: Illuminates when there is a critical or warning alarm. Yellow LED: Illuminates when there is an information alarm.

Output Voltage Output Current 3 Battery Fuse Alarms 1 Fan Alarm 2 DU Fuse Alarms

7.5.9 SM-AC

Communication RS232 / RS485

Local Indicators Green LED: Illuminates when CPU is working correctly. Red LED: Illuminates when there is an alarm.

12 Digital Inputs Alarms/Events

3 Mains/Phase Voltage 3 Phase Current 1 Battery Voltage 1 Temperature 1 Network Frequency 3 Apparent Powers 3 Active Powers 3 Reactive Powers 3 Current Distortions Energy

0-600 VAC, 0-346 VAC 0-5 A External Current Transformer 0-36 VDC -25°C to +80°C / -13°F to +176°F 45-65 Hz kVA (calculated in software) kW (calculated in software) kVA (calculated in software) 0-100% (calculated in software), THD (Total Harmonic Distortion) kWh (calculated in software)

24VDC / 250VAC, 5A

7.5.10 SM-BRC

  • Reports...
  • Total battery voltage.
  • Battery current.
  • 24 cell/block voltages.
  • Ambient temperature (battery compartment)
Show 10 more labels / short text on this page
Inputs · Outputs · Contactor Control · Digital Inputs · Analog Inputs · Digital Outputs · 4 Relay Outputs · Battery Cells Monitored · Inputs · 24 Battery Cells
Page 73 of the Emerson 582145500 user manual — 7.5.11 Standard Features
Page 73 · click to enlarge
Page 73

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

7.5.11 Standard Features

Type of Power Conversion Circuit: High frequency.

Float Charging Output Mode: In this mode of operation, system output voltage is constant and output current does not exceed the current limit setting. During normal operation, the battery is not required to furnish load current and remains in a fully charged condition.

Float voltage is set via the Controller, default @ 54.5V for furnished batteries.

Input Protection:

a. Input Over/Under Voltage Protection: The PCU shuts down and its protection indicator (yellow) illuminates when the input voltage is lower than 260VAC or higher than 530VAC. This condition is reported to the power system Controller and the power system Controller processes the alarms accordingly. b. Input Fusing: Input fuse is provided in each PCU. This fuse is not customer replaceable.

Output Protection:

  • a. Current Limiting: The maximum current delivered by the system is programmed via the Controller. The Controller automatically adjusts the current limit circuit on each PCU so that this value is not exceeded. If a PCU fails, the Controller automatically resets each remaining PCU's current limit point to maintain this value. The Controller also insures that the current limit circuit on any PCU is not set above 110% of its capacity. The default current limit setting is the sum of each installed PCU's output rating. If an additional PCU is added to the system, the system current limit is automatically increased by the rating of the new PCU and the new current limit value is displayed. The current limiting point is set via the Controller. b. Output Fusing: Output fuse is provided in each PCU. If a fuse opens, local and remote PCU Fail Alarms activate. This fuse is not customer replaceable. c. High Voltage Shutdown: 1. Internal: If PCU output voltage exceeds an adjustable preset value, the PCU shuts down.
  • After approximately 5 seconds, the PCU automatically restarts. If PCU output voltage again exceeds the high voltage shutdown value within 5 minutes, the PCU shuts down and locks out. Manual restart is then required. If the PCU does not experience a high voltage condition within the 5 minute time period, the restart circuit is reset.
  • Only the PCU causing the high voltage condition shuts down.
  • The high voltage shutdown point is set via the Controller. 2. Backup: If PCU output voltage exceeds a second (non-adjustable) value, the PCU shuts down and locks out regardless of load. Manual restart is then required. The fixed hardware HVSD is 59.5V (within the range of 58.5 to 60V).

High Temperature Protection:

a. When the PFC board temperature is higher than 85°C, the PCU turns off. When the PFC board temperature is lower than 75°C, the PCU resumes normal operation, and the hysteresis is at least 10°C. b. When the difference between “ambient temperature" and "PFC board temperature” is greater than 5°C, the PCU turns off. When the difference between “ambient temperature" and "PFC board temperature” is less than 2°C, the PCU resumes normal operation, and the hysteresis is at least 3°C. c. When the DC board temperature is higher than 105°C, the PCU turns off. When the DC board temperature is lower than 95°C, the PCU resumes to normal operation, and the hysteresis is at least 10°C.

Page 74 of the Emerson 582145500 user manual — 7.5.11 Standard Features
Page 74 · click to enlarge
Page 74

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

Fan Fault Protection: An alarm will be generated upon a fan fault. In such cases, the fault indicator (red) on the PCU front panel will flash and the PCU will also inhibit its output. Auto- recovery is enabled upon the clearing of the corresponding fault.

PFC Over/Under Voltage: The PCU will shut down when its bus voltage is higher than the over voltage set point or is lower than the under voltage set point. During such conditions, the PCU does not output any power and its protection indicator (yellow) will light up.

Active Load Sharing (PCU): The PCU uses advanced digital active load sharing technology that maintains balancing to within ±3A. The difference in the average current between PCUs is

Startup TimeThe PCU has two startup modes:

a. Normal Soft Start Time: The duration from the time when the PCU is powered on to the time when the PCU provides output voltage is 8s at 90% of the rated load, and the maximum time is 90s at 100% of the rated load.

Hot Swappable: The PCU is designed to be plug-and-play. The PCU can be inserted or removed from a live DC power system with no damage. When the PCU is plugged into the system, the system output voltage will not be affected.

Cooling: Each PCU contains a fan for forced convection cooling.

Fan Control: When the PFC bus voltage is within a normal range, the built-in processor adjusts the fan’s speed according to the PCU’s internal temperature and output current. For example, a higher temperature or output current will increase the fan speed. Above 45°C at full load, the fan operates at full speed. When the PFC bus voltage is abnormal, such as very low bus voltage, the fan turns off.

Communication Failure: The PCU’s protection indicator (yellow) will flash should it experience a communication failure. The failure information will be reported to the Controller and the Controller will process the failure accordingly. During a communication failure, in order to protect the battery, the PCU output voltage will automatically adjust to 53.5 V (this is a default value which can be modified using the Controller). The PCU will revert to normal operation once normal communication is restored.

Unbalance of PCU Output Current: When the output current of the PCUs in a DC power system is unbalanced, the PCU having the unbalanced output current will be identified automatically and its protection indicator (yellow) will turn on.

The failure information will be reported to the Controller and the Controller will process the failure accordingly.

Local Status and Alarm Indicators:

a. Power (Green) b. Protection (Yellow) c. Alarm (Red) d. A 10-segment Green LED is located on the front panel to represent output current, each segment represents 10A.

Page 75 of the Emerson 582145500 user manual — Spare Parts Email DCpower.Spares@Emerson.com OSP.Spares@Emerson.com
Page 75 · click to enlarge
Page 75

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

NetPerform™ Optimization Services

At Emerson Network Power, we understand the importance of reliable equipment – it’s critical to both your business and your bottom line. That is why we offer a wide array of services to meet all of your network infrastructure needs.

Technical Support Email [email protected] [email protected]

Answers technical product and system questions; determines status of warranties and contractual agreements for repair. Phone 1.800.800.5260

Services - Design, Deployment & Optimization Email ES.Services@Emerson.com Provides quotes and bid responses, order placement and scheduling for design, and deployment and optimization services. Download service & maintenance reports online.

Phone 1.800.800.1280, option 7

FreedomCare Secure.EmersonNetworkPower.com

Spare Parts Email [email protected] [email protected]

Pricing and PO processing of spare parts, including but not limited to breakers, cables, fuses, rectifier fans, misc. breaker and fuse panels, enclosure fans, doors & switches, etc. Phone 1.800.800.1280, option 5

DC Power Depot Repair Email DCpower.Repair@Emerson.com Creates and processes RMAs, determines lead times and pricing, provides repair shipping information and status. Phone 1.800.800.1280, option 6

DC Power Product Training Email DCpower.Training@Emerson.com Requests for quotes, order placement and

scheduling. Phone 1.800.800.1280, option 8

For More Information To learn more about service offerings from Emerson Network Power, please contact your sales representative, call 1-800-800-1280 option 7, email ES.Services@Emerson.com or visit www.EmersonNetworkPower.com/EnergySystems

Page 76 of the Emerson 582145500 user manual — 7.5.11 Standard Features
Page 76 · click to enlarge
Page 76

NetSure™ ITM with eSure™ Technology Installation Manual, Section 6040 (Issue AB, April 8, 2013)

The information contained in this document is subject to change without notice and may not be suitable for all applications. While every precaution has been taken to ensure the accuracy and completeness of this document, Emerson Network Power, Energy Systems, North America, Inc. assumes no responsibility and disclaims all liability for damages result- ing from use of this information or for any errors or omissions. Refer to other local practices or building codes as applicable for the correct methods, tools, and materials to be used in performing procedures not specifically described in this document.

The products covered by this instruction manual are manufactured and/or sold by Emerson Network Power, Energy Systems, North America, Inc. This document is the property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy Systems, North America, Inc. Any copying, use or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.

Names of companies and products are trademarks or registered trademarks of the respective companies. Any questions regarding usage of trademark names should be directed to the original manufacturer.

Learn more about the NetSure™ ITM DC UPS from Emerson at: EmersonNetworkPower.com/NetSureITM

EmersonNetworkPower.com/EnergySystems (North America) EmersonNetworkPower.eu/EnergySystems (EMEA)

© Emerson Network Power, Energy Systems, North America, Inc. 2013.

Business-Critical Continuity™, Emerson Network Power™, the Emerson Network Power logo, Emerson™ and Consider it Solved are service marks and trademarks of Emerson Electric Co. EnergyMaster™, eSure™, NetPerform™, NetReach™, NetSpan™, NetSure™ and NetXtend™ are trademarks of Emerson Network Power, Energy Systems, North America, Inc.

Sources

References & links

Pages referenced in this manual — manufacturer, support and downloads.

Ask about the Emerson 582145500

Owners and our team usually reply within a day — and your question helps the next person too.

Add your email to get notified when it’s answered — no spam, ever.

0 questions
No questions yet about the Emerson 582145500

Be the first to ask — other owners or our team will answer.

Original document

Emerson 582145500 manual PDF

76 pages·15.9 MB·Power Supply·PDF
Click any page above to open it here
Page 1 / …
100%
Loading pages…