Fiberglass Cooling Towers Part Number: 882.00440.00 Bulletin Number: SC6-610.6 Effective: 9/10/07 Write Down Your Serial Numbers Here For Future Reference: _________________________ __________________.
Fiberglass Cooling Towers ii Shipping Information Unpacking and Inspection You should inspect your equipm ent for possible shipping damage. Thoroughly check the equipment for any damage that m ight have occu rred in transit, such as broken or loose wiring and components, loose hardware and mounting screws, etc.
Fiberglass Cooling Towers iii Table of Contents CHAPTER 1: SAFETY ................................................................ 6 1-1 How to Use Th is M anual ................................................................................. 6 Safety Symbols Used in this Manual .
Fiberglass Cooling Towers iv 6-3 Parts Li st ....................................................................................................... 24 6-4 Electrical Sc hematic s .......................................................................
Fiberglass Cooling Towers v List of Figures Figure 1: Structural Stee l Support Requirements ......................................................................... 11 Figure 2: Rigging Arrangement ...................................................
Fiberglass Cooling Towers Chapter 1: Safety Page 6 of 25 Chapter 1: Safety 1-1 How to Use This Manual Use this manual as a guide and reference for installing, operating, and maintaining your equipment. The purpose is to assist you in a pplying efficient, proven techniques that enhance equipment productivity.
Fiberglass Cooling Towers Chapter 1: Safety Page 7 of 25 1-2 Warnings and Precautions Our equipment is designed to provide safe and reliable operation when installed and operated within design specifications, following national and local safety codes.
Fiberglass Cooling Towers Chapter 2: Functional Description Page 8 of 25 Chapter 2: Functional Description 2-1 Models Covered in This Manual This manual covers fiberglass cooling tower m odels. Model numbers are listed on the serial tag. A model number followed by –Q is specially-constructed, and the information in this manual may not apply.
Fiberglass Cooling Towers Chapter 2: Functional Description Page 9 of 25 2-4 Optional Features Side Outlet. The side outlet is used when th e tower basin is used as a reservoir. Starter Package. The starter package includes a st arter, a re mote On/Off switc h, a thermostat, and a well.
Fiberglass Cooling Towers Chapter 3: Installation Page 10 of 25 Chapter 3: Inst allation 3-1 Tower Installation Location Roof Installation Select a location over or nearest to the heavi est building structural members. These members should be outside load-bearing walls, building co l umns, or roof joists.
Fiberglass Cooling Towers Chapter 3: Installation Page 11 of 25 Figure 1: Structural St eel Support Requirements TSE50 Structural steel A C C B B C C D 2 X 2 angle to support tower basin, flush with top of structural steel rails Model A B C D number in.
Fiberglass Cooling Towers Chapter 3: Installation Page 12 of 25 3-2 Assembling the Cooling Tower in the Field Your cooling tower may have been shipped on two skids to reduce shipping charges. One skid contains the lower section, identifie d by the black fill wrapped in plastic on the inside of the lower section.
Fiberglass Cooling Towers Chapter 3: Installation Page 13 of 25 Do not let the rigging transfer any load to the cooling tower shell. Provide support to the bottom of the cooling tower when riggi ng. Do not rig from the corners of the o p tional base. Do not ri g less than 8 inches from the corners.
Fiberglass Cooling Towers Chapter 3: Installation Page 14 of 25 Install the piping according to the piping diagra ms in Figure 3 on page 14, Figure 4 on page 14, and Figure 5 on page 15.
Fiberglass Cooling Towers Chapter 3: Installation Page 15 of 25 Figure 5: Flexible PVC Outlet Coupler Tower outlet Flexible PVC coupling (from AEC) Outlet pipe must be supported from building structur.
Fiberglass Cooling Towers Chapter 3: Installation Page 16 of 25 3-6 Setting Up the Water Balancing Valve Install the plug provided in the unused water in let on the side of the tower.
Fiberglass Cooling Towers Chapter 4: Operation Page 17 of 25 Chapter 4: Operation 4-1 Bleed-Off and Evaporation Rates A proper bleed-off rate is important to limit the concentration of minerals and foreign materials in re-circulated water. A bleed-off e qual to the evaporation rate, normally about two gallons per hour per ton (7.
Fiberglass Cooling Towers Chapter 5: Maintenance Page 18 of 25 Chapter 5: Maintenance 5-1 Preventative Maintenance Water Treatment Control of slime, algae, and bacteria growth is extremely important. Cooling towers and reservoir pump tanks are superb environments for microorganism growth.
Fiberglass Cooling Towers Chapter 5: Maintenance Page 19 of 25 5-2 Corrective Maintenance Replacing Nozzles and Fill The PVC fill used in these cooling towers provides years of maintenance-free service under normal conditions.
Fiberglass Cooling Towers Chapte r 6: Appendix Page 20 of 25 Chapter 6: Appendix 6-1 Technical Assistance Parts Department Call Toll-Free 7am–6pm CST [ 800 ] 423-3183 or call [ 262 ] 641-8 610 Our Parts Department is ready to provide th e parts to keep your s ystems up and running.
Fiberglass Cooling Towers Chapte r 6: Appendix Page 21 of 25 6-2 Drawings and Specifications C A0536711 A Fan guard B Top View Access Fan motor Fan blade Nozzle adaptor Nozzle door Rigid PVC tower fil.
Fiberglass Cooling Towers Chapte r 6: Appendix Page 22 of 25 Figure 8: Tower Performance c Cooling Fan NEC Nominal Model capacity Nozzles motor amp draw air flow number tons Kcal/hr no. hp kW rpm 460/3/60 cfm cmh SF2003 50 151,200 1 2 1.5 1,200 3.4 12,000 20,388 SF2004 75 226,800 4 5 3.
Fiberglass Cooling Towers Chapte r 6: Appendix Page 23 of 25 Figure 9: Cooling Tower Nozzle Capacity.
Fiberglass Cooling Towers Chapte r 6: Appendix Page 24 of 25 6-3 Parts List Figure 10: Supplied Parts for Field Assembly Part Number Quantity Description A0101485 1 Silicone A0533163 110 Stainless ste.
Fiberglass Cooling Towers Chapte r 6: Appendix Page 25 of 25 6-4 Electrical Schematics Figure 12: Typical Wiring Diagram 115/1/60 208-230-460/3/60 Starter with overloads M Fan ON/OFF switch Thermostat.
An important point after buying a device Sterling 882.00440.00 SC6-610.6 (or even before the purchase) is to read its user manual. We should do this for several simple reasons:
If you have not bought Sterling 882.00440.00 SC6-610.6 yet, this is a good time to familiarize yourself with the basic data on the product. First of all view first pages of the manual, you can find above. You should find there the most important technical data Sterling 882.00440.00 SC6-610.6 - thus you can check whether the hardware meets your expectations. When delving into next pages of the user manual, Sterling 882.00440.00 SC6-610.6 you will learn all the available features of the product, as well as information on its operation. The information that you get Sterling 882.00440.00 SC6-610.6 will certainly help you make a decision on the purchase.
If you already are a holder of Sterling 882.00440.00 SC6-610.6, but have not read the manual yet, you should do it for the reasons described above. You will learn then if you properly used the available features, and whether you have not made any mistakes, which can shorten the lifetime Sterling 882.00440.00 SC6-610.6.
However, one of the most important roles played by the user manual is to help in solving problems with Sterling 882.00440.00 SC6-610.6. Almost always you will find there Troubleshooting, which are the most frequently occurring failures and malfunctions of the device Sterling 882.00440.00 SC6-610.6 along with tips on how to solve them. Even if you fail to solve the problem, the manual will show you a further procedure – contact to the customer service center or the nearest service center